You are on page 1of 3

SPECIAL REPORT

From quarries to roads:


blasting the way ahead
using Orica Technical Services for blast design and environmental
With recent growth and expansion of the monitoring. Bulk explosives were manufactured on-site using
Victorian aggregate market, Francis Haden Orica's Mobile Manufacturing Units (MMUs). These units are
and Leigh Hahn take a look at a significant capable of producing a range of bulk products to suit different
ground conditions.
road construction project, and user of quarry Blasting along the length of the freeway was conducted in four areas:
products – the Craigieburn Bypass.  Taylor's Cut
 Craigieburn Road East Cut
 Northern Cut
 Railway Cut

F
rom April 2002, Abigroup has been designing a much-needed
bypass linking the Hume Highway at Craigieburn with the
Metropolitan Ring Road in Thomastown. The federally-funded, TAYLOR'S CUT
$306 million project managed by VicRoads has required the blasting Initial blasting commenced at the Taylor's Cut during January 2004.
of cuttings, ramps and pre-split walls along its 17-kilometre length. Blasting of bedrock was required along the full width of the
Upon completion, the project will have used over 100 thousand tonnes carriageway for a distance of 440 metres. For this stage of the
of crushed rock for pavements, built 14 bridges and excavated 2.4 project, blast sizes typically featured, on average, 600 blast holes of
million bank cubic metres (BCM) of bulk earthworks. 89mm diameter. A maximum of 800 blastholes were loaded and
The Craigieburn Bypass will link the Hume Freeway near Mt Ridley fired in one day.
Road at Craigieburn, to the Metropolitan Ring Road at Thomastown* The significant number of holes to be primed, loaded, stemmed
This significant road construction project in Victoria is due to be and connected demanded prompt bulk product delivery and loading
completed in the second half of 2005. efficiency. To assist with the tying in of up to 800 blast holes, Orica
employed EXEL Goldets, which are non-electric signal tube-based
BLASTING REQUIREMENTS detonators, consisting of a constant in-hole delay detonator with a
From its base at Deer Park, and in its role as blasting contractor, surface delay detonator. These detonators are configured as a single
Orica Quarry Services provided a load, tie and fire service to the site unit, simplifying blast design and tie-up. After stemming, the surface

16 Quarry April 2005


connector is drawn across to the corresponding blasthole on the next buried optic fibre lines, Orica organised and conducted a full-scale
echelon and snapped onto the signal tube from that particular hole. field trial with the asset owners, in the Taylor's Cut section.
This removed the need for a separate surface delay detonator (EXEL Sections of optic fibre supplied by the asset owner were directly
Connectadet) other than for tying in the control row. Due to the very laid adjacent to a blast. The distance from buried cables to the near
large number of holes and the uniform design, this increased the edge of the blast was chosen to reflect and replicate conditions
productivity for tying up each blast. throughout the site, in an attempt to assess the potential destruction
Leigh Hahn of Abigroup said, "Orica was still able to tie a large of cable transmission and relate this to PPV. Accelerometers capable
number of blast-holes (providing Abigroup with a greater amount of of handling much higher vibration levels than traditional vibration
excavatable material earlier) and also conduct those blasts during monitors were used for monitoring. After firing each shot, all cables
Abigroup's normally scheduled lunchbreak - thereby not disrupting were tested by the asset owner and found to be unaffected.
other activities, especially the earthworks haulage fleet." Blasting was then successfully completed for over a kilometre, at
times firing more than 17 tonnes of Handibulk Supawet GT at
CRAIGIEBURN ROAD EAST CUT distances less than 30 metres from the cable. This enabled Abigroup
In conjunction with the need to fire large blasts was the requirement to continue bulk excavation and prevented what would have been an
to do so near pressurised pipelines and overhead cables. As with excessive delay and enormous cost if blasting was not able to proceed.
Taylors Cut, Craigieburn Road East Cut required bulk explosives
deliveries and 'paddock' style blasts up to 550 blastholes. This RAILWAY CUT
section of the project was located parallel to the Craigieburn Road This cut contained some of the deepest blasting throughout the
East and adjacent to Australbricks' office and factory. On the north project, and was technically the most challenging. Blasts routinely
side of the Craigieburn Road East were overhead powerlines (22kV required two MMUs as blasting operations approached the
and 66kV), and beneath them a 150mm high-pressure gas main and Melbourne--Sydney railway boundary from the southern side. The
telecommunication service. These services were 50 metres away at requirement for blasts to be loaded and fired promptly became
the closest point during blasting. Abigroup and Orica arranged to increasingly important as blasts approached the rail corridor. Firing
survey the blast sites then monitor the services, as well as close the times were dictated by the need to inspect all three tracks immedi-
road for the duration of each blast. This information was then used to ately after the blast, to ensure no fragments had intruded. This was
create a site vibration law for further environmental blast management. achieved by railway representatives physically walking each line for
several hundred metres.
This final stage of blasting was complicated because of the location

NORTHERN CUT
This was the major area of blasting with a total of 21 blasts occurring
between December 2003 and March 2004. The Northern Cut at its
south end was bordered by the Melbourne-Sydney railway line and
optic fibre services. The optic fibre ran parallel to the eastern
boundary of the cut. As the depth of the cut increased, it drew closer
to the optic fibre services. Further restrictions came from two
bridges: one under construction, and another previously completed.
The completion of this cut was of critical importance to Abigroup's
bulk earthworks program. The peak particle velocity (PPV) limits
imposed by the asset owners, proximity of the services to the blast
site (< 30 metres), and shallowness of the cut potentially meant that
earthworks could be stalled. Given that initial areas of ground to be
blasted were shallow in depth, it became crucial to maintain an
advance of blasted material ahead of earthmoving equipment. The
confidence to fire large blasts close to fibre optic cables was,
therefore, of paramount importance in maintaining project excava-
tion rates. As no historical data existed for blasting adjacent to these
AWE030475
SPECIAL REPORT

Faced with the challenge of not damaging or disrupting


communication services, Orica employed several strategies to
prevent damage, and manage risk while blasting the final ground. A
site law was developed specifically for the area, using prior
knowledge of sustainable vibration levels when blasting next to fibre
optics. This information was incorporated in the blast design.
Accurate timing and complete loading control was vital for
managing vibration levels as successive blasts approached the
buried cables. A combination of packaged explosives types were
used to control charge weights: Buster, a packaged emulsion, and
Shearcord a high strength (70g/m) detonating cord. The delay
'scatter' associated with pyrotechnic detonators meant that only
electronic detonators would provide peace of mind in knowing
exactly when charges would fire. Orica's electronic detonator
system, i-kon, enabled engineers to design each blast with precise
control over the maximum charge weight of explosives firing at each
of fibre optic communications contained within the rail easement, millisecond instant. The absence of delay 'scatter' ensured accurate
which was not accessible to the blasting team. These communica- sequencing of all blasts, and enabled blasts to be sped up or slowed
tion services were of particular concern: down to improve digability and fragmentation. Adjustments were
 The nearest services were parallel to, and only three metres from, made to designs following feedback from plant operators.
a pre-split and five metres from production blastholes. All blasts were fired successfully without damaging the fibre optic
 The direct laid cables could not be relocated because they were on cables. After firing during lunchbreaks, blasted material was
inaccessible land and the nearest access points were kilometres apart. immediately excavated: this minimised disruption, and generated a
 Two of the three services were active and carried a significant steady volume of material for excavation.
volume of Melbourne-Sydney data and communications.
 Each service was owned independently so no redundancy existed * Source: VicRoads website.
should any or all three assets be damaged. Francis Haden works for Orica Quarry Services

P L A N T H I R E T R A N S P O R T Q U A R R Y I N
DEMOLITIONLANDSCAPINGPUBLICWORK
O W N E R / O P E R AT O R D R I L L I N G & B L A S T I N
C I V I L C O N S T R U C T I O N WA S T E M A N A G E M E N
DRILLINGCRUSHING&SCREENINGDEMOLITIO
LANDSCAPINGPUBLICWORKSPLANTHIR
TRANSPORTQUARRYINGCIVILCONSTRUCTIO
O W N E R / O P E R AT O R B L A S T I N G P L A N T H I R
TRANSPORTQUARRYINGDEMOLITIO
L A N D S C A P I N G P U B L I C W O R K S O W N E R / O P E R AT O
WA S T E M A N A G E M E N T D R I L L I N G & B L A S T I N
QUARRYINGPLANTHIRETRANSPORTQUARRYIN
DEMOLITIONLANDSCAPINGPUBLICWORK
O W N E R / O P E R AT O R D R I L L I N G & B L A S T I N
C I V I L C O N S T R U C T I O N WA S T E M A N A G E M E N
DRILLINGSCREENING&CRUSHINGDEMOLITIO
LANDSCAPINGPUBLICWORKSPLANTHIR
TRANSPORTQUARRYINGCIVILCONSTRUCTIO
O W N E R / O P E R AT O R B L A S I N G P L A N T H I R E T R A N S P O
QUARRYINGDEMOLITIONLANDSCAPIN
P U B L I C W O R K S O W N E R / O P E R AT O
WA S T E M A N A G E M E N T D R I L L I N G & B L A S T I N
QUARRYINGPLANTHIRETRANSPORTQUARRYIN
DEMOLITIONLANDSCAPINGPUBLICWORK
O W N E R / O P E R AT O R D R I L L I N G & B L A S T I N
C I V I L C O N S T R U C T I O N WA S T E M A N A G E M E N
• National Marketing Campaign An international standard exhibition
DRILLINGCRUSHING&SCREENINGDEMOLITIO
L A NdDeSlivCeA rinPgI NaGccPeUssBto LIC keW y dOeRciKsiSonP L A N T H I R
• “Meet the Buyer” Program TRAN mSaPkO erRs TiQ
n UthAeRcRiYviIlNcGonCstIrVuIcLtC n,N S T R U C T I O
ioO 8 t h –1 1 t h
O Wq NuEarRr y/inOgP, Eco
TRANSPORTQUARRYINGDEMOLITIO
OcRtio
R nAsTtru BnL A mSatIeNriaGlsP L A N T H I R NOVEMBER

2005
• Supported by CMEIG & related industries.
LANDSCAPINGPUBLICWORKSOWNER/OPERATORWASTE
A N A G E M E N T D R I L L I N G & B L A S T I N
QUARRYINGPLANTHIRETRANSPORTQUARRYIN
• Parallel to CCF Annual Conference DEMOLITIONLANDSCAPINGPUBLICWORK
BOOK YOUR STAND NOW!
O W N E R / O P E R AT O R D R I L L I N G & B L A S T I N
• Opportunity for Live Demonstrations
Contact Frank Matus
C I V I L C O N S T R U C T I O N WA S T E M A N A G E M E N
l: G
D R I L LTIeN 02C R9U4S2H 2I N25G6&2S C R E E N I N G D E M O L I T I O SYDNEY
L A NfD raSnkC.mAaPtuI sN
@G reePdUeBxhLibI C
itioWnsO K .Sau
.coR m PLANTHIR
O L Y M P I C PA R K
• Focus on Career Development TRANSPORTQUARRYINGCIVILCONSTRUCTIO AUSTRALIA
OWNER/OPERATORBLASINGPLANTHIRETRANSPORTQUAR
www.nce.reedexhibitions.com.au
I N G D E M O L I T I O N L A N D S C A P I N
• Seminar Program with LANDSCAPINGPUBLICWORKSPLANTHIR
TRANSPORTQUARRYINGCIVILCONSTRUCTIO
“Toolbox” Sessions O W N E R / O P E R AT O R B L A S I N G P L A N T H I R
TRANSPORTQUARRYINGDEMOLITIO
LANDSCAPINGPUBLICWORKSOWNER/OPERATORWASTE
A N A G E M E N T D R I L L I N G & B L A S T I N

You might also like