The Transcity team used Brokk demolition machines to excavate cross passages on their Legacy Way tunnel project in Brisbane, Australia. Tests showed that a Brokk 400 could excavate at a rate of 2.5 cubic meters per hour while causing low vibration, allowing it to work in the sensitive urban location. Brokk 800s and 400s excavated over 35 cross passages, achieving up to 40% higher productivity than other options and completing the work on schedule. The Brokk machines proved very capable of working in the complex geometry required while minimizing interruptions to the main tunnel drives.
The Transcity team used Brokk demolition machines to excavate cross passages on their Legacy Way tunnel project in Brisbane, Australia. Tests showed that a Brokk 400 could excavate at a rate of 2.5 cubic meters per hour while causing low vibration, allowing it to work in the sensitive urban location. Brokk 800s and 400s excavated over 35 cross passages, achieving up to 40% higher productivity than other options and completing the work on schedule. The Brokk machines proved very capable of working in the complex geometry required while minimizing interruptions to the main tunnel drives.
The Transcity team used Brokk demolition machines to excavate cross passages on their Legacy Way tunnel project in Brisbane, Australia. Tests showed that a Brokk 400 could excavate at a rate of 2.5 cubic meters per hour while causing low vibration, allowing it to work in the sensitive urban location. Brokk 800s and 400s excavated over 35 cross passages, achieving up to 40% higher productivity than other options and completing the work on schedule. The Brokk machines proved very capable of working in the complex geometry required while minimizing interruptions to the main tunnel drives.
number of the key logistical and space primary support was installed in the form of proofing problems whilst using relatively fibre reinforced shotcrete and rock bolts. powerful hammers. In cross passages where drill and blast Hence, the team decided to perform a test operations were required; the Brokk using a Brokk 400 with a 550kg hammer in machines were used to trim the blasted void similar geology as expected in the cross to the required profile in extremely hard passages. This was to measure the sustained geological conditions. Given the complex vibration caused by hammering in these geometry of the cross passages, this proved conditions and thus the resulting regenerated to be approximately 20% of the overall noise through surface structures could be excavation volume that could not be removed modelled. It also offered an opportunity to through blasting. quantify the expected instantaneous breaking “In certain cross passages, we were able to rate this Brokk and hammer combination achieve 40% more productivity from the could achieve. Transcity understood from Brokk 400s than we concluded from the early management strategy that the results of our trials”, says Sean Ivers, Project IN 2011, Transcity, a JV between Ghella, construction of the spoil conveyor tunnel to a Engineer of Ghella. “The maximum Acciona and BMD Constructions won the bid nearby quarry offered the perfect opportunity production outcome achieved was for the Legacy Way project in Brisbane, to perform this test and enlighten realistic approximately 3.5 cubic meters an hour – Australia. The heart of the project and the expectations for the TBM tunnel construction over twice the capacity of an over two times most challenging part was the 4.6km long phase. heavier excavator. The Brokk machines’ twindrive tunnel, aimed at bringing traffic The Brokk 400, with its high frequency abilities were also challenged immensely in underground and shorten travel times with a hammer operation, was measured to have a the trimming of blasted cross passages and modern twolane motorway. low vibration output when compared to they proved a very capable solution to the While the excavation of the two parallel larger tunnel excavator and hammer problem at hand. In various geological tunnels was to be carried out in parallel by combinations whilst still achieving a high conditions, the Brokk machines achieved two TBM machines, the method for the instantaneous breaking rate of approximately production rates like nothing else I have seen excavation of the 35 crosspassages 2.5 cubic metres / hour. close to their size!” measuring 4.5 x 5 x 10m was not clear. The Thus, Transcity procured two Brokk 800 The Transcity team also appreciated the traditional options all had significant demolition machines with 1,000kg hydraulic other Brokk advantages; especially the downsides: possibility to operate • Drill and blast generates impulsive in confined spaces vibrations which was particularly restrictive combined with the given the sensitive urban location of works. operator safety A full scale drill and blast operation also features thanks to causes significant interruptions to the other the remote control work in the tunnels. And, considering the was another valued excavation profile was larger than the asset. segment opening available, machines By using Brokk would inevitably be required to finish the machines for the excavation after blasting. crosspassages and • Roadheaders are large and would block substations, access past the cross passage at which it is interruptions to the working preventing concurrent tunnel TBM progress could activities and slow TBM progress. be kept to a • Tunnel excavators with large hydraulic minimum and hammer attachments could cause Transcity completed significant sustained vibrations through the the 4.6km drive in geological conditions present. This in turn only six months. would cause regenerated noise through breakers and two Brokk 400 demolition By using TBM cutter head data, the surface structures potentially affecting machines with 550kg breakers to carry out Transcity team could plan the cross passage production hours available and create this extensive tunnelling project. The plan was excavation work and add complementary community problems for Transcity and to use these machines as the primary method drilling and blasting in areas where the rock client Brisbane City Council. In addition, of excavation in cross passages with more hardness spiked. The cross passage and traditional tunnel excavators would also favourable geology, whilst offering the substation work with the Brokk machines block access past the cross passage at perfect supplement to drill and blast started February 2013 and was finished in which it is working. operations in harder geology. November that year. The complete Legacy With the geology in the tunnel, where rock Where excavation was carried out solely Way project is scheduled for completion in hardness could surpass 100MPa, drill and using Brokk machines, the procedure was to the first half of 2015. blast was still considered the best option of use the Brokk 800 for initial bulk volume "We finished the cross passages on time the traditional methods, but it was not a excavation with the Brokk 400 to follow in and I would definitely recommend the Brokk satisfying solution on its own. order to trim the edges of the profile. Once machines to other similar projects. We like all Transcity realised Brokk machines the Brokk machines had completed an the Brokk features; safety, production rate, potentially had significant advantages excavation advance to the permitted weight, physical size, reach – a great machine because of their size which satisfied a distance, spoil was completely removed and that delivers everyday” said Sean Ivers.