You are on page 1of 1

PRODUCT NEWS

Brokk for Legacy cross passages


number of the key logistical and space primary support was installed in the form of
proofing problems whilst using relatively fibre reinforced shotcrete and rock bolts.
powerful hammers. In cross passages where drill and blast
Hence, the team decided to perform a test operations were required; the Brokk
using a Brokk 400 with a 550kg hammer in machines were used to trim the blasted void
similar geology as expected in the cross to the required profile in extremely hard
passages. This was to measure the sustained geological conditions. Given the complex
vibration caused by hammering in these geometry of the cross passages, this proved
conditions and thus the resulting regenerated to be approximately 20% of the overall
noise through surface structures could be excavation volume that could not be removed
modelled. It also offered an opportunity to through blasting.
quantify the expected instantaneous breaking “In certain cross passages, we were able to
rate this Brokk and hammer combination achieve 40% more productivity from the
could achieve. Transcity understood from Brokk 400s than we concluded from the
early management strategy that the results of our trials”, says Sean Ivers, Project
IN 2011, Transcity, a JV between Ghella, construction of the spoil conveyor tunnel to a Engineer of Ghella. “The maximum
Acciona and BMD Constructions won the bid nearby quarry offered the perfect opportunity production outcome achieved was
for the Legacy Way project in Brisbane, to perform this test and enlighten realistic approximately 3.5 cubic meters an hour –
Australia. The heart of the project and the expectations for the TBM tunnel construction over twice the capacity of an over two times
most challenging part was the 4.6km long phase. heavier excavator. The Brokk machines’
twindrive tunnel, aimed at bringing traffic The Brokk 400, with its high frequency abilities were also challenged immensely in
underground and shorten travel times with a hammer operation, was measured to have a the trimming of blasted cross passages and
modern twolane motorway. low vibration output when compared to they proved a very capable solution to the
While the excavation of the two parallel larger tunnel excavator and hammer problem at hand. In various geological
tunnels was to be carried out in parallel by combinations whilst still achieving a high conditions, the Brokk machines achieved
two TBM machines, the method for the instantaneous breaking rate of approximately production rates like nothing else I have seen
excavation of the 35 crosspassages 2.5 cubic metres / hour. close to their size!”
measuring 4.5 x 5 x 10m was not clear. The Thus, Transcity procured two Brokk 800 The Transcity team also appreciated the
traditional options all had significant demolition machines with 1,000kg hydraulic other Brokk advantages; especially the
downsides: possibility to operate
• Drill and blast generates impulsive in confined spaces
vibrations which was particularly restrictive combined with the
given the sensitive urban location of works. operator safety
A full scale drill and blast operation also features thanks to
causes significant interruptions to the other the remote control
work in the tunnels. And, considering the was another valued
excavation profile was larger than the asset.
segment opening available, machines By using Brokk
would inevitably be required to finish the machines for the
excavation after blasting. crosspassages and
• Roadheaders are large and would block substations,
access past the cross passage at which it is interruptions to the
working preventing concurrent tunnel TBM progress could
activities and slow TBM progress. be kept to a
• Tunnel excavators with large hydraulic minimum and
hammer attachments could cause Transcity completed
significant sustained vibrations through the the 4.6km drive in
geological conditions present. This in turn only six months.
would cause regenerated noise through breakers and two Brokk 400 demolition By using TBM cutter head data, the
surface structures potentially affecting machines with 550kg breakers to carry out Transcity team could plan the cross passage
production hours available and create this extensive tunnelling project. The plan was excavation work and add complementary
community problems for Transcity and to use these machines as the primary method drilling and blasting in areas where the rock
client Brisbane City Council. In addition, of excavation in cross passages with more hardness spiked. The cross passage and
traditional tunnel excavators would also favourable geology, whilst offering the substation work with the Brokk machines
block access past the cross passage at perfect supplement to drill and blast started February 2013 and was finished in
which it is working. operations in harder geology. November that year. The complete Legacy
With the geology in the tunnel, where rock Where excavation was carried out solely Way project is scheduled for completion in
hardness could surpass 100MPa, drill and using Brokk machines, the procedure was to the first half of 2015.
blast was still considered the best option of use the Brokk 800 for initial bulk volume "We finished the cross passages on time
the traditional methods, but it was not a excavation with the Brokk 400 to follow in and I would definitely recommend the Brokk
satisfying solution on its own. order to trim the edges of the profile. Once machines to other similar projects. We like all
Transcity realised Brokk machines the Brokk machines had completed an the Brokk features; safety, production rate,
potentially had significant advantages excavation advance to the permitted weight, physical size, reach – a great machine
because of their size which satisfied a distance, spoil was completely removed and that delivers everyday” said Sean Ivers.

TUNNELLING JOURNAL 49

You might also like