You are on page 1of 40

GS 118-10

WELDING OF TRANSMISSION
PIPELINES
Supplementary to BS 4515: 1996
December 1998
(Amended February 2000)

Copyright © The British Petroleum Company p.l.c.


Copyright © The British Petroleum Company p.l.c.
All rights reserved. The information contained in this document is subject to the terms and
conditions of the agreement or contract under which the document was supplied to the
recipient's organisation. None of the information contained in this document shall be
disclosed outside the recipient's own organisation without the prior written permission of
Manager, Standards, BP International Limited, unless the terms of such agreement or
contract expressly allow.
BP GROUP RECOMMENDED PRACTICES AND SPECIFICATIONS FOR ENGINEERING

Issue Date December 1998


Doc. No. GS 118-10 Latest Amendment Date February 2000

SUPPLEMENTARY TO BS 4515: 1996


(Replaces BP Engineering Std 192 Part 1 and BP GS 118-10 April 1986)

APPLICABILITY
Regional Applicability: International

SCOPE AND PURPOSE

This BP Group

AMENDMENTS
Amd Date Page(s) Description
___________________________________________________________________
01 01 Feb 2000 19-20 Reference BS EN 1435 replacing BS 2910
23-24 Amendment to Table 8(j)
29-30 Amendment to list of referenced standards.

Approved for issue:- ……………………….


December 1998 John Hammond
DOCUMENT CUSTODIAN
CUSTODIAN (See Current Status List for Contact)
Welding
Issued by:-
Engineering Practices Group, BP International Limited, Research & Engineering Centre
Chertsey Road, Sunbury-on-Thames, Middlesex, TW16 7LN, UNITED KINGDOM
Tel: +44 1932 76 4067 Fax: +44 1932 76 4077 Telex: 296041
CONTENTS

Section Page

FOREWORD ..................................................................................................................... iii

1. GENERAL .......................................................................................................................1
1.1 Scope and General Applicability .................................................................................1
1.3 Definitions .................................................................................................................1
1.4 Information to be supplied, items to be approved and requirements to be
agreed and documented ..............................................................................................2
1.5 Equipment .................................................................................................................4
1.6 Welding Processes......................................................................................................4
1.7 Welding Consumables.................................................................................................5
1.8 General Requirements.................................................................................................6

2. TESTING, QUALIFICATION AND APPROVAL OF WELDING -


PROCEDURES....................................................................................................................7
2.1 General .................................................................................................................7
2.3 Welding Procedure .....................................................................................................7
2.4 Changes Affecting Qualification and Approval (Essential Variables)............................7
2.5 Testing of Butt Joints for Procedure Qualification.....................................................10
2.6 Testing of Fillet Welds for Procedure Approval ........................................................12
2.7 Testing of Repair Welds for Procedure Qualification.................................................12

3. TESTING, QUALIFICATION AND APPROVAL OF WELDER..............................13


3.1 General ...............................................................................................................13
3.5 Changes Affecting Qualification and Approval (Essential Variables)..........................13
3.6 Non-destructive Testing............................................................................................13
3.7 Destructive Testing...................................................................................................13
3.8. Retests ...............................................................................................................13
3.9 Records ...............................................................................................................13
3.10. Mechanized Welding..............................................................................................13

4. PRODUCTION WELDING ..........................................................................................14


4.1. Proximity of Welds ..................................................................................................14
4.2 Pipe End Preparation................................................................................................14
4.3. Fusion Faces............................................................................................................14
4.4 Alignment ...............................................................................................................15
4.5 Line-up Clamps and Pipe Supports ...........................................................................15
4.6 Tack Welds ..............................................................................................................15
4.8 Stray Arcs ...............................................................................................................15
4.9 Weather Conditions ..................................................................................................16
4.10 Preheating and Post-weld Heat Treatment...............................................................16
4.11 Branches ...............................................................................................................16
4.12 Inter-run Cleaning...................................................................................................17

GS 118-10 PAGE i
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
4.13 Partially Completed Joints.......................................................................................17

5. INSPECTION AND TESTING .....................................................................................18


5.1 Inspection and Testing ..............................................................................................18
5.1 General ...............................................................................................................18
5.2 Personnel Qualification.............................................................................................18
5.4 Radiographic Testing................................................................................................18
5.5. Manual Ultrasonic Testing .......................................................................................21
5.6. Automatic Ultrasonic testing....................................................................................21
5.7 Magnetic Particle Testing .........................................................................................21
5.8 Destructive Testing...................................................................................................22

6. ACCEPTANCE AND RECTIFICATION OF WELDS ...............................................23


6.1 Non-Destructive Testing Acceptance Criteria ...........................................................23
6.2 Rectification of Welds...............................................................................................24
There are no requirements additional to BS 4515:1996.......................................................

ANNEX C TO BS 4515 (INFORMATIVE).


PROPOSED WELDING PROCEDURE SPECIFICATION..........................................25

ANNEX D TO BS 4515 (INFORMATIVE)


EXAMPLE OF A RECORD FORM FOR WELDER QUALIFICATION TEST. .........26

ANNEX E TO BS 4515 (INFORMATIVE) .


GUIDANCE FOR ESTABLISHING PREHEATING REQUIREMENTS .....................26

ANNEX F TO BS 4515 (INFORMATIVE).


EXAMPLE OF A RADIOGRAPHIC SPECIFICATION................................................26

APPENDIX A.....................................................................................................................27
DEFINITIONS AND ABBREVIATIONS ........................................................................27

APPENDIX B.....................................................................................................................29
LIST OF REFERENCED DOCUMENTS ..................................................................29

APPENDIX C.....................................................................................................................32
ALTERNATIVE TECHNIQUE FOR BATCH TESTING OF WELDING
CONSUMABLES.........................................................................................................32

FIGURE C1........................................................................................................................33
PROCEDURE FOR ESTABLISHING BATCH TEST REQUIREMENT......................33

GS 118-10 PAGE ii
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
FOREWORD

Introduction to BP Group Recommended Practices and Specifications for Engineering

The Introductory Volume contains a series of documents that provide and introduction to the
BP Group Recommended Practices and Specifications for Engineering (RPSEs). In particular,
the ‘General Foreword’ sets out the philosophy of the RPSEs. Other documents in the
Introductory Volume provide general guidance on using the RPSEs and background
information to Engineering Standards in BP. There are also recommendations for specific
definitions and requirements.

Value of this Guidance for Specification

This Guidance for Specification specifies all BP general requirements for welding of
transmission pipelines that are within its stated scope, and for use with a supplementary
specification to adapt it for each specific application.

This Guidance for Specification is based upon an industry specification.

The value of this Guidance for Specification to its users will be significantly enhanced by their
regular participation in its improvement and updating. For this reason, users are urged to
inform BP of their experiences in all aspects of its application.

Application

This Guidance for Specification is intended to guide the purchaser in the use or creation of fit-
for-purpose specification for enquiry or purchasing activity.

This document may refer to certain local, national or international regulations but the
responsibility to ensure compliance with legislation and any other statutory requirements lies
with the user. The user should adapt or supplement this document to ensure compliance for
the specific application.

Previous Changes from Previous Editions

This document completely supersedes the earlier BP Standard 192 Part 1 (April 1986) which
was later reformatted into BP GS 118-10 (1986), both former documents being based on BS
4515:1984. This document is based on BS 4515:1996 and reflects the extensive revision of the
base document.

GS 118-10 PAGE iii


DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
Feedback and Further Information

Users are invited to feed back any comments and to detail experiences in the application of BP
RPSEs, to assist in the process of their continuous improvement.

For feedback and further information, please contact Standards Group, BP International or the
Custodian. See Current Status List for contacts.

GS 118-10 PAGE iv
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
1. GENERAL

1.1 Scope and General Applicability

1.1.1 This BP Group RPSE specifies general BP requirements for the welding
of transmission pipelines in accordance with BS 4515: 1996.

To apply this BP Group RPSE, supplementary specification and


approval actions by BP are required to adapt it to each specific project
application.

The titles and numbering of the text of this BP Group RPSE follow
those of BS 4515:1996 for the convenience of the user. As a result of
this, gaps in the numbering sequence may occur. Text either qualifies,
substitutes, modifies or adds to its requirements those of BS 4515:
1996. Where additional text is to be read as an extension of the text of
BS 4515:1996, the text numbering of BS 4515:1996 has been extended
accordingly.

1.1.2 BP Group GS 118-10 is applicable where statutory regulations require


that the pipeline is welded in accordance with BS4515:1996, as in the
UK, or other areas where BS 4515:1996 may have been adopted by a
statutory authority or by choice as the pipeline welding code. It’s
alternative companion GS, BP Group GS 118-9 is applicable where
statutory regulations or similar adoption of API standards require that
the pipeline is welded in accordance with API Standard 1104.

1.3 Definitions

In this standard, the following definitions shall apply in addition to or


modifying or supplementing those of Section 1.3 of BS 4515:1996.

Any specific application of the terms and responsibilities for the parties
defined as follows is a matter for the Conditions of Contract on a
project.

1.3.1 (a) employer: BP, acting directly or through an authorised


representative.

(b) BP The British Petroleum Company p.l.c, an


associate or subsidiary, or other organisation as
defined in the conditions of contract.

1.3.2 contractor: a contractor responsible BP for the welding of the


pipeline

1.3.22 inspector: an employee of the contractor with overall

GS 118-10 PAGE 1
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
responsibility for ensuring that all construction,
inspection and testing are undertaken in accordance
with the requirements of this GS

1.3.23 batch: a single cast of filler wire, a single blend of flux, or, for
covered electrodes , the combination of a single cast of
core wire with a single dry blend of covering.

1.3.24 duty: pipeline service which is to be defined by BP as


normal or severe. Welds in severe duty pipelines will
(may) be subject to more onerous requirements than
those in normal duty pipelines.

1.3.25 service: to be defined by BP as either sour or non-sour (see


1.3.13 of BS 4515:1996).

1.3.26 quality assurance (QA):


all those planned and systematic actions necessary to
ensure quality and technical compliance. (i.e. to provide
adequate confidence that a product will be fit for its
intended service).

1.3.27 quality manual


a document setting out the general quality policies,
procedures and practices of an organisation

1.3.28 quality plan (QP)


a document prepared by the contractor, setting out the
specific quality practices, resources and sequence of
activities relevant to the particular pipeline welding
contract.

1.4 Information to be supplied, items to be approved and


requirements to be agreed and documented

1.4.1 Information to be Supplied by the Employer

Where possible, the information to be supplied is provided below under


the appropriate clause numbers. However, in addition to the items
identified by BS 4515: 1996, the following information will be supplied
by the employer:-

(i) Test pressure for pipeline field hydrostatic test

(ii) The pipeline duty and service.

(iii) Requirement for Charpy testing of welding consumables on


severe duty pipelines.

GS 118-10 PAGE 2
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
(iv) Whether any change in heat input is considered significant.
(See 2.4, Table 1 j5.)

(v) Whether additional hardness surveys on macro-sections are


required.

(vi) Alternative Charpy test temperatures.

(vii) Use of fluorometallic screens.

(viii) Sensitivity levels for gamma radiography.

(ix) Welds and areas requiring ultrasonic testing

(x) Further limitations on root undercut and shrinkage groove for


sour service pipelines.

1.4.2 Items to be Approved by the Employer

Where BP have specific requirements, these are stated below under the
appropriate clause numbers. However, in addition to the items
identified by BS 4515: 1996 the following additional approvals are
required:-

(i) Use of automatic and semi-automatic welding systems (See 1.6)

(ii) Quality plan prior to production welding. (See 1.8.3)

(iii) Acceptance of batch testing failure before re-tests are allowed.


(See 1.7.1)

(iv) Acceptance of re-welding in procedure qualification tests (See


3.8)

(v) Acceptance of material grouping. (See 3.5)

(vi) Acceptance of diameter and thickness group combination.


(See 3.5c)

(vii) Acceptance of Charpy V-notch impact test results.


(See 2.5.2.5)

(viii) Acceptance of pipe diameter or wall thickness changes.


(See 3.5)

(ix) Welder re-training programme. (See 3.8).

GS 118-10 PAGE 3
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
(x) Alternative 'pup' piece length. (See 4.1)

(xi) Angle of field bevel if different from mill bevel. (See 4.2)

(xii) Alternative method for pipe end cleaning. ( See 4.3)

(xiii) Corrective action for misalignment. (See 4.4)

(xiv) Use of fabricated fittings. (See 4.11).

(xv) Use of Iridium 192. (See 5.4.1)

(xvi) Use of gamma-radiography. (See 5.4.2)

(xvii) Use of permanent magnets or prods. (See 5.7)

(xviii) Limits on size and location of weld repair excavations.


(See 6.2.4)

1.4.3 Requirements to be Agreed

Where appropriate, the requirements of BP are stated under the


appropriate clause numbers. However, in addition to the items
identified by BS 4515: 1996 the following requirements shall be subject
to specific agreement between BP and the contractor.

(i) Use of wall thickness and pipe diameter grouping for welder
qualification on severe duty pipelines. (See 3.5)

1.5 Equipment

The contractor shall supply all necessary equipment for welding, heat
treatment, mechanical handling, testing and radiographic processing.

1.6 Welding Processes

The contractor shall specify in his tender the welding process, or


processes or combination of processes proposed for the pipelay welding
operation. Manual processes, semi-automatic or automatic welding
systems may be offered. Where a process or system is proposed of
which BP has no previous experience BP will specify welding and NDT
trials which are to be undertaken by the contractor and completed
successfully before the proposed technique can be approved for
qualification testing. Separate qualification of a manual metal arc
procedure may also be required, for possible use in the event of failure
of semi-automatic or automatic equipment in production welding.

GS 118-10 PAGE 4
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
1.7 Welding Consumables

The contractor shall supply all necessary welding electrodes, filler


wires, fluxes, shielding and backing gases and all other consumable
items required for the work.

1.7.1 General

Where the duty of the pipeline is specified by BP as severe, each batch


of welding consumables shall pass the Charpy V-notch impact test
required for welding procedure qualification. This requirement will be
waived if further tests from the qualification weld still meet the
specified values when tested 20°C below the specified test temperature.
All batch testing shall be completed prior to the start of field welding.
No re-tests are permitted unless a satisfactory explanation for the failure
can be given and is accepted by BP.

1.7.2 Storage and handling.

1.7.2.1 General

Each coil of filler wire, bag of flux and tin or packet of electrodes shall
be clearly marked with its batch number (and shall be stored completely
separated). The storage and handling of welding consumables shall be
generally in accordance with BP Group GS 118-4. The contractor's
detailed proposals shall form part of the quality plan.

1.7.2.1 Shielding Gases - General

Where appropriate, gases or gas mixtures complying with BS EN 439


shall be used:-

(a) argon,
(b) carbon dioxide
(c) gas mixtures that have been proved to be satisfactory as a result
of procedure approval tests.

When a gas mixture is used which has specified additions e.g. 2% O2,
5% CO2, the variation of such addition shall not exceed ±10% of that
stated.

1.7.2.2 Shielding Gases - Storage and Handling

Shielding gases shall be stored away from extremes of temperature. In


the field, only gases specified in 1.7.2.1, as supplied by the
manufacturers, in specially marked containers, shall be used. Gases that
are of questionable purity and those in containers which show signs of
damage shall not be used.

1.7.3 Welding Consumables for Fillet Welds

GS 118-10 PAGE 5
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
Basic coated low hydrogen electrodes or other approved low hydrogen
process shall be used for any fillet welding directly on to the pipeline,
but rutile coated electrodes may be used for fillet welds between non-
pressure bearing parts such as structural supports.

1.8 General Requirements

1.8.1 Supervision of the Work

The contractor shall employ competent supervisors to ensure that both


the standard of workmanship, and the quality of materials used, comply
with the requirements of this BP Group RPSE.

1.8.2 Field Hydrostatic Test

The completed pipeline shall be hydrostatically tested for a minimum


period of 24 hours. The test pressure, which will be defined by BP,
shall not normally exceed that required to produce a hoop stress equal
to 95% of the specified minimum yield strength in a pipe with the
specified minimum wall thickness.

The completed pipeline shall be proved free from internal obstructions


by the passing of a pig fitted with a gauging plate, of dimension 96% of
nominal bore.

1.8.3 Quality Assurance

1.8.3.1 Responsibility for quality assurance shall rest with the contractor. The
contractor shall devise and implement a quality plan for the systematic
control of the construction, inspection and testing required by the
particular contract. This quality plan, which shall be based on ISO
9002/9003 shall be submitted to BP for approval prior to production
welding, and shall include evidence that the inspector and his team are
independent of production management.

1.8.3.2 The inspector shall ensure that all documentation required by this
Standard is gathered, collated, indexed, stored and subsequently
presented to BP. He shall compile a log identifying by number each
pipe and fitting, and indicating the weld numbers joining them to other
items. Each circumferential weld (whether a field joint or a shop-made
weld) shall be allocated a unique number, which shall be used for
reference to the weld in all reports, radiographs and NDT documents.

GS 118-10 PAGE 6
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
2. TESTING, QUALIFICATION AND APPROVAL OF WELDING -
PROCEDURES

2.1 General

(a) All welding procedure qualification tests shall be conducted in


the presence of a BP representative.

(c) A test shall be allowed to cool for a minimum of 24 hours in


simulated site conditions. After this 24 hour period, the
procedure qualification test welds shall be fully radiographed,
ultrasonic tested and magnetic particle tested prior to
conducting destructive tests.

(h) For pipelines designated as severe duty, BP will require welding


procedures to be specifically qualified on the actual material for
construction. Previous weld qualification test results will not be
acceptable for such applications.

2.3 Welding Procedure

Procedure approval tests shall be carried out on pipe, made from the
same material, from the same source and in the same supply condition
that is to be used for pipeline construction.

2.4 Changes Affecting Qualification and Approval (Essential


Variables)

Table 1. Welding Procedure Specification Details and


Changes Affecting Approval.

The following additional restrictions or changes apply to all welding


procedure specifications:-

Item Relevant Change or Restriction

(a) Welding process The gas tungsten arc process (GTAW)


shall be used for welding on all pipe
diameters less than 60 mm.

(b) Material Specification Pipe, valves, flanges and fittings from


different sources, or made from
material from different sources, or in
different supply conditions shall be
treated separately and shall require
separate procedure qualification,
unless some form of material grouping
is approved by BP
.
(c/d) Diameter /Thickness Different wall thicknesses and

GS 118-10 PAGE 7
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
diameters shall be qualified separately,
unless approved otherwise approved
by BP.

(e5) Joint configuration The use of permanent backing rings is


not permitted.

(f) Filler metal Basic coated low hydrogen electrodes


or approved low hydrogen process
shall be used for all fillet welds to the
pipeline

(g) Number of runs The number and position of weld beads


shall be selected to give the finished
weld a substantially uniform cross-
section.
No two weld beads shall start
at the same point, unless the area is
dressed clean and sound before the
second bead is started. Single pass
welds are not permitted

(i) Electrical For Manual Shielded Metal Arc


Welding characteristics of pipe
diameters above 300 mm welded d.c.
electrode positive (d.c.e.p) polarity
shall be used.
An increasing tendency towards use
of d.c electrode negative (d.c.e.n) for
polarity for root runs of pipe of all
diameters is noted. Where a
contractor proposes use of d.c.e.n the
welding procedure qualification test
shall include this feature. Arbitrary
change from d.c.e.p to d.c.e.n. or vice
versa is not permissable.

(j5) Heat input Any change in heat input outwith the


limiting values calculated from values
of arc voltage (j2), wire feed speed (j3)
and travel speed (j4) or considered
significant by BP.

(l) Direction of welding For all tie-ins (closing welds), all welds
where external line-up clamps are
used, and for all repair welds, vertical-
up welding shall be used for the root
runs. For pipe diameters less than 150
mm and for all welds to valves, flanges
or fittings including fillet welds, the

GS 118-10 PAGE 8
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
complete weld shall be vertical-up.

(o) Time lapse When vertical-down welding is


employed between runs the second run
(hot pass) shall be deposited
immediately after completion of the
root run (stringer bead), and the time
lapse shall not be greater than that
used in the welding procedure
qualification test.

(p) Partially completed joint Welds shall not be cooled below


preheat temperature before:-

For pipe to pipe welds onshore


4 runs minimum completed.

For welds offshore. All runs


completed.

For welds on fittings, tie-in welds and


repair welds. All runs completed.

(q) Type of line-up clamp if used For pipe over 150 mm diameter an
clamp, internal line-up clamp shall be
used.
Where the use of an internal clamp is
impracticable, an external line-up
clamp shall be used.

(r) Lowering-off or barge move-up as The pipe shall not be lowered-off


applicable until both the root pass and the
second pass are complete, unless the
contractor can demonstrate to the
satisfaction of BP that the root run
alone is adequate to resist deformation
and cracking. For offshore pipelay,
barge move-up shall not occur until the
hot pass is complete

(t6) Interpass temperature Interpass temperature in construction


shall not exceed the maximum value
achieved in the welding procedure
qualification test, which in any case
shall not exceed 250°C.

GS 118-10 PAGE 9
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
(t7) Ambient temperature Minimum ambient temperature below
which preheating is to be applied.

(u) Post weld heat-treatment The temperature range of any PWHT


shall be selected, taking into account
the steel composition and
manufacturing route. The PWHT
temperature, time and method of
application used in pipeline
construction shall fall within the range
used in the welding procedure
qualification test.

2.5 Testing of Butt Joints for Procedure Qualification.

2.5.1 Non-destructive Testing

All test joints shall be examined visually followed by:-

(i) Radiography in accordance with clause 5.4.

(ii) Ultrasonic examination in accordance with clause 5.5.

(iii) A magnetic particle test in accordance with clause 5.7 at


external and internal weld surfaces.

The acceptance criteria for non-destructive testing shall be in


accordance with clause 6.1.

2.5.2 Destructive Testing

The following additional tests are required:-

2.5.2.1 Test Specimens

For pipe outside diameters up to and including 114.3 mm, two


transverse weld tensile test specimens shall be taken.

For pipe outside diameters up to and including 114.3 mm, two sets of
three Charpy impact specimens shall be taken at the 9 o'clock position.

For pipe outside diameters over 114.3 mm, two additional sets of three
specimens shall be taken at the 6 o'clock position.

When specified (separately) for severe duty pipelines, two sets of three
CTOD specimens shall be taken. An all weld tensile test to BS 709 :

GS 118-10 PAGE 10
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
1983 is also required on each weld from which CTOD tests are taken,
on material from a location as close as possible to the CTOD tests.

2.5.2.2 Transverse Tensile Test

2.5.2.2.1 Requirements

If any specimen breaks outside the weld at a tensile strength below the
specified minimum tensile strength, the material shall be considered
suspect and its physical properties shall be investigated before any
additional tests are made.

2.5.2.2.2 Method

The test specimens shall not be flattened before testing.

2.5.2.4 Hardness Survey

2.5.2.4.1 Requirements

In addition to the requirements of Table 4, where the pipeline service is


defined as sour, no individual hardness value shall exceed 248 HV10
(see BP Group RPSE GS 136-1).

2.5.2.4.2 Method

BP may require additional hardness surveys on macro-sections taken


from different locations.

A macro-photograph shall be supplied to show the location of all


hardness indents.

2.5.2.5 Charpy V-Notch Impact Test

2.5.2.5.1 Requirements

Unless otherwise specified by BP, the impact test temperature shall be


the minimum design temperature and energy requirements for the weld
shall be 40 J minimum average of three specimens and 30 J minimum
individual value.

2.5.2.5.2 Method

For pipe diameters up to and including 114.3 mm, one set of Charpy V-
notch test specimens shall be notched in the weld metal and the other in
the heat affected zone.

For pipe diameters over 114.3 mm, the additional sets of Charpy tests
at the 6 o'clock position shall be notched and tested as the other
samples.

GS 118-10 PAGE 11
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
For pipe wall thickness over 20 mm, both sets of test specimens at the 3
o'clock position shall be positioned at the weld root. One set of test
specimens shall be notched in the weld metal and the others in the heat-
affected zone. For weld metals, the percentage of shear area of each
fracture surface shall be estimated and reported. If the results are
inconsistent with the measured energy, BP may require further
investigation before approving the test results.

2.5.2.6 Crack Tip Opening Displacement (CTOD) Testing

Detailed CTOD testing was removed from BS 4515 when the 1996
edition was prepared, leaving only a minor note (3) to clause 2.5.2.5.1.

Exact CTOD requirements are not specified in this GS as these will be


dependent on each individual application. Where an Engineering
Criticality Assessment (ECA) approach is required as part of pipeline
design for installation or operation, it is the responsibility of each
project to define the ECA philosophy and specify the methodology for
CTOD testing and acceptance values according to its own needs.

It is suggested that use should be made of BS PD 6493 for any ECA philosophy. The
selection of material and sampling of each respective zone for CTOD testing shall
take into account the importance of identifying the zone of potentially lowest
fracture toughness. All CTOD tests shall be conducted in accordance with BS
7448: Part 2: 1998 at the minimum design temperature.

Where possible the specimens shall be full wall thickness, preferred geometry and
the pipe curvature shall not be machined from the sample. The exact notch
positions and geometry in the CTOD test samples should be subject to agreement
but should include the weld metal and the heat affected zone.

2.6 Testing of Fillet Welds for Procedure Approval

2.6.2.4 Hardness Survey

2.6.2.4.1 Requirements

In addition to the requirements of Table 4, where the pipeline service is


defined as sour, no individual hardness value shall exceed 248 HV10
(see BP Group GS 136-1).

2.6.2.4.2 A macro-photograph (or sketch) shall be supplied which shows the


locations of all hardness indents.

2.7 Testing of Repair Welds for Procedure Qualification

Section 2.7 of the new 1996 edition of BS 4515 deals with the testing of repair welds
for procedure qualification and is deemed to meet BP’s general requirements
without a supplement.

GS 118-10 PAGE 12
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
3. TESTING, QUALIFICATION AND APPROVAL OF WELDER

3.1 General

Welders’ qualification tests shall be witnessed by a BP representative.

3.5 Changes Affecting Qualification and Approval (Essential


Variables)

If the following additional item is changed, the welder using the new
procedure shall require re-approval:-

(f) For manual metal-arc welding a change in electrode trade name.

3.6 Non-destructive Testing

For manual metal-arc, tungsten inert gas (TIG) and submerged-arc


welding the test weld shall be assessed by X-radiography as specified in
clause 5.4. For metal inert gas (MIG)/metal active gas (MAG), CO2
and non-shielded welding, the weld shall be assessed by X-radiography
to clause 5.4 and ultrasonic examination as specified in clause 5.5.

3.7 Destructive Testing

In addition to NDT, destructive testing shall be used for examination of


welds made by any process other than manual metal arc, TIG and
submerged arc.

3.8. Retests

If, in the opinion of BP, An individual welder is responsible for a high


level of repairs in production, he/she shall be removed from the work
and shall undergo a re-training programme approved by BP before
being retested.

3.9 Records

The details of each welder’s approval test and test results shall be
recorded by the contractor and be available for inspection by BP. The
contractor shall submit all documentation relating to welder approval
tests to BP for approval prior to the welder commencing production
work. BP will specify the period for which records shall be maintained.
(The content and requirement for this may vary from project to project
and will be individually specified).

3.10. Mechanized Welding

Welders for mechanised welding shall be approved for all parts of the
operation. The inspection, testing and re-testing of welds for approval
purposes and records shall be in accordance with the following:-

GS 118-10 PAGE 13
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
(i) Visual examination to clause 3.6.

(ii) X-radiography to clause 5.4.

(iii) Ultrasonic examination to clause 5.5

(iv) Destructive testing to clause 3.7.

(v) Retests to clause 3.8.

(vi) Records to clause 3.9.

The acceptance criteria for NDT shall be in accordance with 6.1.2.

4. PRODUCTION WELDING

4.1. Proximity of Welds

Branches, fittings and attachments shall be sited away from other welds
(including longitudinal and circumferential welds) on the pipeline. The
minimum separation between any two welds shall be the largest of the
diameter of the branch or fitting, six times the wall thickness of the
thicker component, or 150 mm.

No two circumferential welds shall be closer than the diameter of the


pipe, but if a ‘pup’ piece is used to replace a defective section, its length
shall not be less than twice its diameter, unless otherwise approved.

4.2 Pipe End Preparation

The pipe end bevel may be specified by the contractor and shall be
suitable for the welding process to be used. In general, the API 5L
standard bevel will be considered suitable for manual welding
processes, but for thick-wall pipe or for certain types of GMAW
mechanised welding, an alternative compound bevel may be proposed.
The bevel design shall be subject to agreement by BP.

Manual cutting shall not be used for bevelling.

If the blending of burns, small score marks, indentations or other minor


imperfections within the joint area is agreed, then it shall be confirmed
by ultrasonic measurement that the remaining wall thickness is above
the allowable minimum.

Weld repairs to pipe ends shall not be permitted.

4.3. Fusion Faces

Before welding, the pipe shall be cleaned inside and out using power
driven wire brushes, grinding or other method approved by BP, for a
minimum distance of 40 mm from the edge of the weld bevel.

GS 118-10 PAGE 14
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
4.4 Alignment

Where misalignment exceeds 1.5 mm, corrective action shall be subject


to the approval of the BP representative in each case. Hammering of the
pipe to obtain correct alignment should be kept to a minimum and shall
be carried out using only a bronze headed hammer. The mass of the
bronze headed hammer shall not exceed 5 kg. Any surface
contamination of the pipe surface from the hammering shall be
removed. Heat shall not be used for corrective purposes.

4.5 Line-up Clamps and Pipe Supports

4.5.1 Power operated internal clamps shall be used for pipe of over 150 mm
diameter, and they shall be demonstrated as capable of reducing the
maximum permitted out-of-roundness of the as-manufactured pipe
sufficiently to meet the alignment requirements of clause 4.4. External
clamps shall be used only when the root run is deposited by the vertical-
up technique.

4.5.2 For on-land pipelines, at least the root run and the second run shall be
completed before the pipe is lowered on to skids or, in the case of
fittings, the support is removed, unless the contractor is able to
demonstrate to the satisfaction of BP that the root run alone is adequate
to resist deformation and cracking.

4.6 Tack Welds

Tack welds are allowed for vertical up welding only. All tack welds
shall be deposited by approved welders and in accordance with the
welding procedure specification. Where pre-heat is required for the
root run, this shall be applied prior to tack welding and maintained until
the joint is completed.

4.8 Stray Arcs

Repair of stray arcs in sour service pipelines may be restricted by BP.


When repair is allowed this shall be bt grinding only. Repairs by
welding are not allowed.

If grinding to remove the effects of stray arcs reduces the wall thickness
below the minimum specified in the data sheet, the defective pipe
section shall be cut out and the pipe re-bevelled and re-welded. If a
‘pup’ piece has to be used to replace the defective section, its length
shall not be less than twice its diameter. Note that stray arcs are also
possible between the pipe and the return cable and shall be avoided by
good electrical connections.

GS 118-10 PAGE 15
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
4.9 Weather Conditions

When necessary, the end of the pipe shall be covered to prevent water
being channelled into the weld root. Windshields shall be used when
necessary.

4.10 Preheating and Post-weld Heat Treatment

4.10.2 Preheating

Except as permitted under clause 4.13, preheating shall be maintained


throughout the entire welding of the joint.

4.10.3 Post-weld Heat Treatment Temperatures

Thermocouples shall be used for recording post-weld heat treatment


temperature. As a minimum, thermocouples shall be placed at the 6 and
12 o'clock positions. For pipe sizes above 600 mm outside diameter,
thermocouples shall also be placed at the 3 and 9 o'clock positions. The
pipe shall be heated for a minimum distance of 2.5 Rt (where R is the
external radius and t is the wall thickness) on either side of the joint.
The temperature at the edge of this heated band shall not be less than
half the peak temperature at the centre (in °C).

4.10.4 Thermocouple Attachment and Junctions

Thermocouples shall be attached by the capacitance discharge method.


After use, thermocouples shall be removed by grinding and the area
shall be examined by magnetic particle inspection as for a stray arc.

4.11 Branches

Unless otherwise approved by BP, forged fittings shall be used for


branches and other pressure containing attachments. To simplify the
welding of some large fittings such as tees or elbows into the line, a
'pup' piece may be welded to the fitting and the length of such pup
pieces should be sufficient to accommodate the line-up clamp to be
used. Other large fittings may be girth welded directly into the pipeline
provide that wall thickness of the fitting and pipe are reasonably
matched and that suitable clamping can be accommodated.

Items such as weld-o-lets may be welded directly on to the pipeline,


using the appropriate qualified procedures. Large weld-o-lets and heavy
fittings may require special support, particularly when welded on to thin
section pipelines.

Where accessible, all welds to valves, flanges and fittings shall be


ground back smooth internally prior to radiography.

GS 118-10 PAGE 16
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
4.12 Inter-run Cleaning

Each run shall be thoroughly cleaned by power tools.

4.13 Partially Completed Joints

(i) Land Pipelines

The welding of fittings, tie-ins and repairs shall be completed in


one cycle. When production conditions are such that pipe-to-
pipe joints have to be left partially completed, at least four weld
runs shall be completed prior to cooling unless a procedure
qualification test involving fewer runs has been carried out.

(ii) Submarine Pipelines and land pipelines in construction on steep


gradients.

All welds shall be completed in one cycle.

GS 118-10 PAGE 17
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
5. INSPECTION AND TESTING

5.1 Inspection and Testing

5.1 General

The frequency of non-destructive testing shall be as specified under the


separate clauses 5.4, 5.5 and 5.7.

Prior to examination of the weld, each joint shall be thoroughly cleaned


using power driven wire brushes. All spatter, bonding media and any
inks or dyes used for crack detection, shall be removed. The completed
weld shall be examined visually prior to being examined by radiography.

Ultrasonic and magnetic particle flaw detection testing equipment shall


be available to supplement radiography on any area nominated by BP.

When automatic and semi-automatic welding systems have been


approved by BP, ultrasonic testing shall be required to supplement
radiography. The extent of this testing will be specified by BP.

5.2 Personnel Qualification

All inspection personnel shall be experienced in the appropriate


inspection and control and control techniques and shall hold current,
valid certificates demonstrating approval to either BGAS Transco,
CSWIP or PCN systems.

Note that the BGAS Transco and CSWIP examinations are run by TWI Training &
Examinations Dept. The Certification body for CSWIP is TWI Certification Ltd,
Granta Park, Great Abington, Cambridge, UK. PCN is administered by the British
Institute of Non-Destructive Testing (BINDT) at Northampton, UK).

Both Institutes are able to verify the validity of individual certificates. Certificates
are issued for specific periods only and an out-of-date certificate is invalid. Care
should be taken to ensure that the certificate and approval category covers
competence in the required skills for the job. e.g. BGAS Transco Senior Pipeline
Inspector covers welding inspection and radiographic interpretation, but CSWIP
welding inspector and radiographic interpreter are discrete and different
categories.

5.4 Radiographic Testing

5.4.1 General

100% radiographic testing is required in the following cases:-

(a) All welds in severe duty pipelines.

(b) All welds between pipes of different nominal bore.

GS 118-10 PAGE 18
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
(c) All welds to valves, flanges and fittings.

(d) All tie-ins (closing welds).

(e) All welds in river and other crossings.

On a pipe-lay barge, the weld shall not be moved past the weld repair
station until the interpretation of the radiograph is complete and the
weld is judged satisfactory. Unless otherwise approved by BP, coating
and wrapping of the joint shall not begin until the weld is judged
satisfactory.

For normal duty pipelines, the first five welds of each thickness and
diameter made by each welder shall be 100% radiographically tested. If
any of these welds requires a repair, all subsequent welds by the same
welder shall be 100% radiographically tested until five consecutively
produced welds are judged to be satisfactory. Thereafter, BP will select
at least one weld from every ten welds, and radiograph this 100%. If
any of these one-in-ten welds should require repair, BP will require
some or all of the other nine to be radiographed 100%.

BP may specify 100% radiography for some normal duty pipelines.

Radiography shall be conducted using X-rays. Under certain


circumstances BP may approve the use of Iridium 192, but other
sources of gamma rays are not permitted.

As exposure of any part of the human body to X-rays or gamma rays


can be injurious, it is essential that whenever X-ray equipment or
radioactive sources are in use, adequate precautions are taken to
protect the radiographer and all other personnel in the vicinity.

Note 1. The use of X-ray machines and gamma-radiography sealed sources in


factories and certain other premises and works coming within the scope of the
Factories Act is controlled by the Ionising Radiations (Sealed Sources) Regulations
1969 and th Radioactive Substances Act (1960).

Note 2. Attention I is drawn to the ‘Code of Practice for Site Radiography’ prepared
by the Oil and Chemical Plant Contractors Association and published by Kluwer-
Harrap Handbooks, Brentford. Attention is also drawn to the need for audible and
visual warning arrangements and for regular monitoring of radiation levels.

The above paragraph and two notes formed section 37.2 ‘Protection’ of BS 4515:
1984 - but were not included in BS 4515:1996. The proposal of WEE/21/7 was that
the warning should be covered in separate regulations, rather than in the base
standard for pipeline welding but, as it is uncertain where such warnings are
covered elsewhere, it is deliberately included in this BP GS.

5.4.2 Approved Radiographic Procedures

The following details shall be included in the radiographic procedure.

(The following items were additional to section 37.3 of BS 4515: 1984 but the
format of the whole section - now 5.4.2 of BS 4515: 1996 has changed, the list has

GS 118-10 PAGE 19
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
been dropped and reference has been made to BS 2910. In 1997, BS 2910 was
superseded by BS EN 1435. Amendment No 1 of this GS draws on BS EN 1435 in
respect of the following details of radiographic technique and assessment of
radiogrpahic sensitivity. .

(a) technique Radiographic techniques shall be in accordance


with BS EN 1435 Class B (Improved
techinques). The preferred technique for
radiographic examination of pipeline girth welds
is film outside with the source of radiation inside
the pipe.(BS EN 1435 Para 6.1.4 and Figure 5).
Exceptionally, where the preferred technique is
not practicable, a double wall single image (BS
EN 1435 Para 6.1.8 and Fig 13) may be
considered

(b) type of film Fine grain, high contrast, direct type BS EN 584-
1 Class C3 or better.

(c) intensifying Lead screens shall be used, unless fluorometallic


screens screens have been approved by BP Amoco.

(d) limit of film The limit of diagnostic film coverage length for
pipes over 1 metre in diameter shall not exceed
one third of the pipe circumference. (BS EN
1435 Para 5.6)

(e) Image quality A wire-type image quality indicator* (IQI)


indicator conforming to BS EN quality 462-1: 1994 shall
be used. (* Also termed penetrameter). The IQI
shall be used in accordance with placement
directions in Para 5 of BS EN 462-1: 1994.

(f) Processing All radiographic film shall be dried thoroughly


prior to viewing and shall be processed to allow
storage of the film without deterioration for a
period of at least five years.

5.4.3 Acceptable Radiographic Sensitivity Levels

Radiographic sensitivity is expressed as a percentage, and is defined by


the ratio of the diameter of the smallest IQI wire clearly visible on the
radiograph to the material thickness. The radiographic sensitivity
achieved for the single wall single image (SWSI) techniques shall be as
defined by Table B3 of BS EN 1435 and for the double wall single
image (DWSI) technique, as defined by Table B11.

Gamma-radiography is not normally acceptable where the pipewall

GS 118-10 PAGE 20
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
thickness is below 12 mm and its use shall be subject to approval by
BP.. If approved, sensitivity levels will be specified by BP.

The radiographic procedure shall be repeated at the discretion of BP


whenever any change is made to the operating techniques, or whenever
production films differ appreciably from the detail, contrast, or density
of the qualifying radiographs.

5.5. Manual Ultrasonic Testing

5.5.1 General

BP will require ultrasonic testing of the following areas:-

(a) Following field cut back of pipe, a zone extending 100 mm back
from the new field bevel shall be ultrasonically tested for
laminations.

(b) A zone 100 mm wide around the planned cut-outs of nozzles for
laminations.

(c) To verify minimum wall thickness.

(d) To verify defects found by radiography.

(e) Additional welds and areas as requested by BP, including welds


involving the use of automatic and semiautomatic welding
systems.

5.5.4 Reporting and Evaluation - Testing of Pipe Material

The acceptance criteria for ultrasonic examination within the pipe ends
and at the planned cut-outs for nozzles shall be to quality grade B4
given in Table 1 of BS 5996, unless an alternative quality has been
agreed with BP.

5.6. Automatic Ultrasonic testing.

The use of automatic ultrasonic testing shall be subject to the approval


of BP in each instance.

5.7 Magnetic Particle Testing

The following welds shall be tested using the magnetic particle flaw
detection method:

(a) All repair welds.

(b) All welds to fittings.

GS 118-10 PAGE 21
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
(c) All fillet welds.

(d) In severe duty pipelines, the finished weld bevel shall be


magnetic particle flaw detected following field cut back of pipe.

Electromagnetic (a.c.) yoke and/or adjacent cable techniques are


preferred. Permanent magnets or prods shall not be used without prior
BP approval.

5.8 Destructive Testing

BP will require completed welds to be removed for testing if there is


any suspicion that they have not been produced strictly in accordance
with the approved procedure. The contractor may attempt to guard
against this eventuality by qualifying welding procedures at the extreme
parameters which the welders may consider using.

The above requirement which related to 36.3 of BS 4515: 1984 was not included in
BS 4515: 1996 but is retained in this BP GS as the qualification of a welding
parameter range is routinely carried out.

GS 118-10 PAGE 22
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
6. ACCEPTANCE AND RECTIFICATION OF WELDS

6.1 Non-Destructive Testing Acceptance Criteria

6.1.1 General

The acceptance criteria for non destructive testing shall be in


accordance with 6.1.2.

Acceptance criteria based on engineering critical assessment to clause


6.1.3 of BS 4515:1996 do not apply to this Standard except in specific
instances, where the design of the pipeline specifies ECA in accordance
with PD 6493.

6.1.2 Acceptance Criteria Based on Quality Control

In areas of weld preparation such as pipe ends, fusion faces and


branches, planar defects are not acceptable.

TABLE 8. Acceptance Criteria for Welds

The following limits on acceptance modify those given in BS


4515:1996:-

Flaw type Acceptance Criteria

(c) Root penetration Not to exceed 1.5 mm for pipe


diameters less than 60 mm.

(d) Root concavity At no point shall the weld be thinner


than the calculated design thickness of
the pipe.

(e) Root undercut BP may specify further limitations for


root undercut and shrinkage groove for
pipelines in sour service.

(f) Incomplete root These defects are unacceptable in sour-


penetration service pipelines.

(h) Cap undercut Undercut exceeding 0.5 mm in depth is


unacceptable in severe duty and shall
be blended out by light grinding prior
to radiography.If this reduces the pipe
wall thickness below the specified
minimum, the entire circumferential
weld shall be cut out and bevelled and
re-welded.

GS 118-10 PAGE 23
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
(j) Porosity (other than elongated Not to exceed a total area, when
porosity in the root run) projected radially through the weld of
1% of any 600 mm2 of projected weld
area. An isolated pore greater than
20% of the pipe thickness or 1.5 mm,
whichever is the smaller, in any
direction, shall be considered
unacceptable.

(k) Tungsten inclusions Tungsten inclusions shall not exceed


two per weld and shall be separated by
a minimum of 50 mm

6.1.3 Acceptance Criteria Based on Engineering Critical Assessment

Not applicable to this BP Group GS unless the design of the pipeline


specifies ECA in accordance with BS PD 6493.

6.2 Rectification of Welds

6.2.2 Preparation for Re-welding

6.2.2.1 Partial Removal of Weld

Defects shall be removed by grinding and the repair excavation checked


by magnetic particle inspection to ensure complete removal of the
defect. Cracked welds shall be cut out and the weld re-made

6.2.3 Re-welding

Root sealing or single run repairs shall not be practised. There shall be
no internal welding on sour service pipelines. For severe duty pipelines
a repair shall only be attempted once, thereafter the weld shall be
completely removed. For normal duty pipeline a second repair may be
made. If this second repair fails to meet the requirements of clause 6.1
the entire circumferential weld shall be cut out and re-bevelled.

For offshore pipe-lay of submarine pipelines, the limits on size and


location of proposed weld repair excavations beyond the final tensioner
shall be submitted to BP for approval, supported with calculations and
appropriate diagrams.

NOTE: Stresses imposed by construction techniques existing at the time of making a


repair such as at a lay-barge repair station, may be such that to remove 20% of the
weld length may render this operation unsafe. In such cases, the permitted length of
a repair should be reduced to ensure that the stress applied to the weld under repair
does not exceed 80% of the specified yield stress of the pipe.

A full record of all repairs shall be maintained by the contractor. The


record shall be made as each defect is discovered, and shall include the
following:

GS 118-10 PAGE 24
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
(i) The weld number.

(ii) The type and size of defect.

(iii) The circumferential location (defined to an approved system).

(iv) An estimate of the depth (assessed by ultrasonic test where


possible).

(v) Name and/or number of the welder who produced the defect.

(vi) Repair welding procedure number.

(vii) Name and/or number of repair welder.

(viii) Copy of the inspection report for the repair.

(ix) Date of repair.

GS 118-10 PAGE 25
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
ANNEX C TO BS 4515 (INFORMATIVE).
PROPOSED WELDING PROCEDURE SPECIFICATION

There are no requirements additional to BS 4515:1996. The contractor may propose


alternative format welding procedure specification forms to those shown in Annex C of
BS 4515:1996 but any alternative shall be subject to approval by BP.

ANNEX D TO BS 4515. (INFORMATIVE)


EXAMPLE OF A RECORD FORM FOR WELDER QUALIFICATION TEST.

There are no requirements additional to BS 4515:1996. The contractor may propose


alternative format welding procedure specification forms to those shown in Annex D of
BS 4515:1996 but any alternative shall be subject to approval by BP.

ANNEX E TO BS4515. (INFORMATIVE) GUIDANCE FOR ESTABLISHING


PREHEATING REQUIREMENTS

This informative annex is for guidance only. Where necessary the contractor shall
undertake trials to establish an adequate level of preheat to ensure compliance with the
requirements of this standard. The precise preheat level shall be as proven satisfactory
by the welding procedure qualification test. A minimum preheat of 150°C shall apply to
the welding of fittings, repair welds and tie in welds.

ANNEX F TO BS 4515. EXAMPLE OF A RADIOGRAPHIC SPECIFICATION

There are no requirements additional to BS 4515. Any specification of alternative


format shall be subject to approval by BP.

GS 118-10 PAGE 26
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
APPENDIX A

DEFINITIONS AND ABBREVIATIONS

Definitions

Standardised definitions may be found in the BP Group RPSEs Introductory Volume.


Other definition which supersede, qualify or are an addition to Section 1.3 of BS 4515:1996
are found in the corresponding section of this standard

Abbreviations

API American Petroleum Institute

BGAS Transco A qualification and certification system, formerly known as ERS, for
pipeline inspection personnel, originally instituted and run by the former
British Gas Engineering Research Station, Killingworth, UK. Now
known as BG Approval Scheme and managed by TWI Certification Ltd
for Transco

BS British Standard

CSWIP Certification Scheme for Welding and Inspection Personnel managed by


TWI Certification Ltd Granta Park, Great Abington, Cambridge, UK

CTOD Crack Tip Opening Displacement

DIN Deutsches Institut fur Normung

GMAW Gas Metal Arc Welding

HV Vickers hardness

MAG Metal Active Gas

MDT Minimum design temperature

MIG Metal Inert Gas

NACE National Association of Corrosion Engineers

NDT Non-Destructive testing

PCN Personal Certification in Non-Destructive Testing ( a scheme for the


qualification of non-destructive testing and inspection personnel

GS 118-10 PAGE 27
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
managed by The British Institute of Non-Destructive Testing (BINDT)
Northampton, UK

PWHT Post Weld Heat Treatment

SI Systeme International d'Unites

TIG Tungsten Inert Gas

TWI The Welding Institute, Granta Park, Great Abington,


Cambridge CB1 6AL, UK
.
UNITS This Standard employs SI metric units.

WEE/21/7 British Standards Sub-Committee responsible for BS 4515

GS 118-10 PAGE 28
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
APPENDIX B

LIST OF REFERENCED DOCUMENTS

A reference invokes the latest published issue or amendment unless stated otherwise.

Reference standards may be replaced by equivalent standards that are internationally or


otherwise recognised provided that it can be shown to the satisfaction of the purchaser'’
professional engineer that they meet or exceed the requirements of the referenced standards.

American Standards

API Standard 1104 Standard for welding pipelines and related facilities

British Standards

BS 709:1983 Methods of destructive testing fusion welded joints and weld metal in
steel.

BS 3971:1980/(1985) Specification for image quality indicators for industrial


radiography(including guidance on their use)
* Partly replaced by BS EN 462-2:1994

BS 639: 1986 Covered carbon and carbon manganese steel electrodes


for manual metal-arc welding (The former standard BS 639 has been
withdrawn and is superseded by BS EN 499:1995. However, reference
to the former BS 639 is retained here for the method of testing specified
in Appendix C)

PD 6493:1991 Guidance on methods for accessing the acceptability of flaws in fusion


welded structures.

BS 4515: 1996 Specification for process of welding of steel pipelines on land and
offshore

BS 5996: 1993 Specification for acceptance levels for internal imperfections in steel
plate, strip and wide flats, based on ultrasonic testing.

BS 7448 Part 1: 1991: Fracture mechanics toughness tests. Part 1 Method for determination
of K1c, critical CTOD and critical J values of metallic materials

BS 7448 Part 2: 1998 Fracture mechanics toughness tests. Part 2 Method for determination
of fracture toughness of weldments in metallic materials.

BS EN 439: 1994 Welding Consumables - Shielding Gases for Arc Welding and Cutting

GS 118-10 PAGE 29
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
BS EN 462-1: 1994 Image quality indicators (wire type). Determination of image quality
value. * Partly replaces BS3971: 1980 (1985)

BS EN 462-2: 1994 Image quality indicators (step/hole type). Determination of image


quality value. * Partly replaces BS3971: 1980 (1985)

BS EN 499: 1995 Welding consumables. Covered electrodes for manual metal arc welding
of non-alloy and fine grained steels. Classification.

BS EN 584-1: 1995 Non-destructive testing - Industrial radiographic film. Part 1.


Classification of film systems for industrial radiography.

BS EN 1435:1997 Non-destructive examination of welds. Radiographic examination of


welded joints

BS EN ISO 9002: 1994 Quality systems. Model for quality assurance in production,
installation and servicing.

BS EN ISO 9003: 1994 Quality systems. Model for quality assurance in final inspection and
test.

BP Group RPSE

GS 136-1 Materials for sour service to NACE Standard MR-01-75 (1990


Revision) Note latest NACE MR-01-75 is 1998 Revision

GS 118-4 Storage and control of welding consumables

GS 118-9 Welding of transmission pipelines. Part 2.


Supplementary to API Standard 1104

GS 118-10 PAGE 30
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
German Standard

DIN 54 109 : Part 1 Nondestructive testing; image quality of radiographs of metallic


materials; definitions, image quality indicators, determination of image
quality index

Note:

1. The definitions for employer and inspector replace those given in BS 4515:1996.

GS 118-10 PAGE 31
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
APPENDIX C

Alternative Technique for Batch Testing of Welding Consumables

Batch tests of welding consumables are not intended to undertaken as a routine measure for all
pipelines, but may be required by BP for certain offshore pipelay operations and land-based
pipelines designed for certain categories of critical service. When batch testing is specified by
BP it shall be carried out in accordance with this Appendix by the consumable manufacturer
rather than by the pipe-welding contractor. All batch test welds shall be made as all-weld-
metal deposits as defined in former standard BS 639: 1986. In the following list of steps, the
illustrative results (given in parenthesis) refer to this Addendum, Figure C1 :-

(i) BP will define the Charpy test requirements for the welding procedure qualification
test (Average 50 J at -10°C).

(ii) The contractor shall obtain acceptable results from the welding procedure qualification
test at mid-wall thickness (Average 80 J at -10°C).

(iii) The consumable supplier shall prepare an all-weld-metal deposit using the same batch
of consumables that was used in the welding procedure qualification test. Where more
than one size of consumable is used, a separate deposit should be made for each size.
Consumables used for the root run only do not require batch testing.

(iv) The consumable supplier shall test a set of three Charpy test pieces, of the same size as
those taken from the welding procedure qualification test, at the temperature of the
welding procedure qualification test (Average 160 J at -10°C).

(v) The consumable supplier shall test further sets of three Charpy test pieces, decreasing
temperature by -10°C per set, until the average falls below that specified for the
welding procedure qualification test:-

150 J at -20°C
140 J at -30°C
90 J at -40°C
40 J at -50°C

(vi) By interpolation, the temperature will be found, at which the all-weld-metal deposit
gives the same energy as that measured in the welding procedure qualification test
(-42°C).

(vii) All batch tests shall be carried out at this temperature, against the same energy
requirement as that specified for the welding procedure qualification test (50 J).

GS 118-10 PAGE 32
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515
FIGURE C1
Procedure for Establishing Batch Test Requirement

GS 118-10 PAGE 33
DRAFT WELDING OF TRANSMISSION PIPELINES
PART 1 - SUPPLEMENTARY TO BS 4515

You might also like