General Exclusions (To be considered by ANCG)

 Man Hole Covers


 Trench covers
 Excavation Works
 Demolishing & Relocation Works for any existing MEP Services
 Arch.Louvers in Generator room
 GRP kiosk & GRP enclosures for Supply Fans & Penstock
 All Ladders , gratings, Chequered Plates & platforms (Including SS ladders & platforms inside
dry & wet well)
 All Civil and Builders works
 Core drilling & Slab penetration
 External works
 Concrete supports for Pipes & Equipment
 Authority Approvals by MC

Qualifications

GENERAL

 DLP 1 year. Operation and Maintenance not considered.


 As there is not specified vendors for HVAC in Revised Specification-R1,Our price is based on
using any DM approved Vendors / Makes, as per DM general manufacturers list, from any of
their manufacturing facilities available worldwide
 We have considered FAT only for the following MEP items
a) Chillers
b) AHU
c) Dry-pit Pump
d) Transformer
e) MV Panels
f) Generator
g) MV-VFD
h) UPS
i) LV Panel

ELECTRICAL

 We have considered only provision for integeration with existing Central SCADA System.
 We have considered GSM based RTUs for external networks.
 In absence of Cable Cellar containment details we have considered allowance for Cable trays.
 Power provision for external Flow Meter RTUs considered with in 100m from the Flowmeter
chamber
 Network Switches for Telecoms.

HVAC

 Chillers shall be direct driven chillers in lieu of gear driven type.


PLUMBING

 Valve Chambers (Complete with Valves, interconnecting Pipes & Accessories - Isolation Valve
Chambers - 19 nos, Air Valve Chamber - 65 nos, Washout Valve Chamber - 41 no, Future
Connection Chamber - 31 nos)