Professional Documents
Culture Documents
Section-C Group 10
ALISHA SURABHI PGP/PGDM/0157/55
1 Although the criticality rate was high for shuttle flights pertaining to the O-ring
problem, it was an acceptable risk which they perceived as lowering their
standards doing it over and over again since the risk was not so high at the first
place.
This perception prevailed on day 1 as even after knowing that the foam size
was comparatively unusually high, managers struck down that because it was
of low concern. The team was classified as DAT instead of Tiger team with no
clear structure to support the team following lack of communication between
engineers and managers.
2,3,4 Going further, engineers were not keen on consulting with more experienced
engineers with prior experience as such they discounted the data which could
have led to possible risks. Further, there was no answer from the inspection
team and hence had a loose analysis leading to an inability to draw the
conclusion.
5 There was lack of cooperation among the employees and they did not feel that
they were responsible and hold the authority of leading the project as such
when they were directed to meet daily they met only five times out of total 15
days. The problems defined were considered more reasonable and important
than the foam hitting the Orbiter. A specific problem was unconsidered. Rocha
was asked to seek new imagery but she was requested to do this through
engineering division rather than following the relevant path of Shuttle
Program’s chain of command. This further delayed her request for outside
agency assistance, which was not accepted readily.
6 This day showed the extremely bureaucratic and hard to navigate culture
followed and propagated in NASA where engineers were not allowed to send
messages or show their concerns to the top tier management team. Hence
their inputs were not taken into account while making decisions. The structure
was not followed by the lower hierarchies as they could not prove the requests
or requirements. On the other hand, everything was very rule-oriented and
protocol-oriented that even after knowing the importance of imagery, it was
canceled on the basis of not following the structures.
7 Remarks which came from the Schomburg’s clearly states the decision were
made on the basis of past situations and the managers lack technical
competency. Also, an email reminded the military officials that all requests had
to follow the proper channels otherwise it could slip through the system. This
email clearly indicated that NASA was more concerned about the
organizational communication channel through the official route even in the
crisis situation.
Q4. What differences did you perceive in the behavior of managers versus engineers?
The Challenger Look for factual proofs before making Rojer Boisjoly – Used logical arguments
Disaster decisions. and knowledge to present his point.
Columbia accident Managers in Mission evaluation NASA engineer - Rodney Rocha became
investigation - The rooms entered in their log that the worried as he recalls - gasping loudly
digitized clip strike was of low concern
Accountability `Decision was taken on the basis of After the first meeting of DAT, they
uncertainties which were confirmed agreed on getting additional visual data
over email by JSC engineers to Ham. on the basis of their engineering
When Rocha approached Shack about expertise. Rocha tried multiple times to
the choice that was made by the request for the need of visual data but
management about not making efforts was delayed as the managers were
to obtain images, he was not bothered thinking that foam strikes were normal
to explain the rationale behind the things. This instance showed the
decision. accountability of the engineers.
Attitude towards Managers Ham and Dittemore from The engineers were focussed on
the Problem time to time say that the foam was not researching and presenting their results
a factor as they could not do much to the MMT. Their attitude can be
about it, or that the flight rationale perceived serious towards the issue
was lousy.
Focus Managers were mission oriented. They Engineers were more focussed on the
wanted to meet the deadlines of problems at hand. They were task -
NODE 2 and avoid the scrutiny being oriented. They focussed on performing
faced by Space station program. This the tasks they were assigned.
led them to be negligent towards
problems at hand
Following the chain Managers were the rule-oriented and Engineers were more focused on finding
of command protocol-oriented. Ham canceled the the fastest way by communicating with
requests because she could not find the appropriate person who could get
who needed imager1y. She only the task done as soon as possible
contacted the MMT i.e. followed the instead of following the chain of
chain of command command.
Day 5 and 6 Managers, for example, Ham was Rocha wrote an email to address the
known for her domineering issue of additional imaging help from
management style. She was more any outside source, but she didn't send
assertive regarding executing a task the mail to her supervisor. They were
not to message higher authority. This
shows that they don't have the liberty
to assert a decision which was purely
related to technical expertise.