NEW BRIDGE ACROSS THE RIVER NILE AT JINJA

Structural Health Monitoring Breakdown


Keisokugiken
Unit Rate
No. Items Description Unit Q'ty Amount Remarks
Monitoring System
1 KUMONOS Crack Mapping Nos. 1 44,000.00 44,000.00 Original
2 Stay Cable Monitoring by Forced Vibration Method Stay Cable Force Nos. 1 7,135.00 7,135.00 Original
3 Lightning Protection for Monitoring Equipment L/S 1 105,736.58 105,736.58
4 Strain Gauge Nos. 24 1,220.68 29,296.32
5 Inclinometer Nos. 3 4,191.36 12,574.08
6 Survey Pin for 3D Total Station L/S 1 1,555.56 1,555.56
Pylons:2 Nos.
Differential Global Positioning System (DGPS) on Real Time Kinematic Satellite
7 Nos. 4 56,712.96 226,851.84 Box Girder:2
Pylon Crown Navigation System (RTK)
Nos.
Portal Frame for Weight-in-Motion System and Traffic 2 Nos.
16 Galvanized Nos. 2 135,000.00 270,000.00
Monitoring Cameras Span: 15m
17 Accelerometer (Seismometer) Location: A1, P1, P2, A2 Nos. 1 89,768.52 89,768.52
18 Expansion Joint Movement Sensor Nos. 4 2,006.67 8,026.68
19 Weather Transmitter WXT530 L/S 1 8,037.04 8,037.04
21 Transportation (DDT Jinja) WiM and Frame L/S 1 80,000.00 80,000.00
including Commissioning Test, OM
28 Supervisor for installation L/S 1 170,459.26 170,459.26
and Training UNRA except of WIN
29 Performance bond for Keisokugikenn L/S 1 20,000.00 20,000.00
Total 1,073,440.88

Keisokugiken Total 1,073,440.88

Keisokugiken 50% of Total 536,720.44