WEEKLY REPORT

PENYELENGGARAAN CERUN DI JALAN PERSEKUTUAN


SEMENANJUNG MALAYSIA MELALUI KONTRAK
JANGKAMASA PANJANG MULAI TAHUN 2017

Name Noor Affendi bin Location Laluan FT324 Project 16/8/19


Dikkir Seksyen 1.9 Start
Position Assistant Resident Month/ October/2st Week Project 15/11/19
Engineer(Central) Week End

District/State: Sepang/Selangor Method: Stone Pitching

Monday (7/10/19)
Activity
Activity- lay rock for stone pitching
(interlocking works)

Remarks- may have revision on drawing about


the area of remedial of stone pitching

Schedule % : 92%
Actual % : 20%

Prepared by, Checked by,

…………………………………….. ……………………………………..
(Noor Affendi Bin Dikkir) (Mohd Fadly Arif Bin Abdullah)
Assistant Resident Engineer Resident Engineer
Date : 11/10/2019 Date : 11/10/2019