Professional Documents
Culture Documents
K.M. Priyanka
Final Year, Civil Engineering Department,
Kumaraguru College of Technology, Coimbatore, Tamilnadu, India
ABSRACT
Planning and scheduling are the foremost necessary aspects contributive to the
success of a project, however these factors have an effect on the development
productivity is studied and mentioned during this project. The techniques
unremarkably been used for project scheduling, are particularly the bar graph and
critical Path methodology during this project, the favored Primavera (P6.0) code is
employed as a tool for investigation this observe of CPM scheduling. correct job
monitoring is another facet that directly contributes to the advance of construction
productivity, while not correct planning and scheduling it results in spoil the work.
during this project it quoted regarding construction productivity, while not correct
coming up with and programing it results in spoil the work. during this project it
quoted concerning the planning and scheduling for Balanced Cantilever bridge to
beat the time, value and predict the losses incidence during this project. Construction
projects are initiated in advanced and dynamic environments leading to circumstances
of high uncertainty and risk, that area unit combined by tightened time constraints.
Risk assessment may be a tool to spot those risks in an exceedingly project and
manage it consequently with correct treatment. Risk assessment is outlined during this
study as a method that aims to spot and estimate risks to personnel and property
wedged upon by a project.
1. INTRODUCTION
1.1. General
Project management is that the art and science of mobilizing and managing individuals,
materials, instrumentation and cash to finish the allotted project work on time with in
budgeted prices and nominative technical performance standards. It aims at achieving the
required objectives with efficiency and effectively by managing human energies and
optimizing the non-human resources placed at their disposal. Planning involves deciding
before what's to be done, however and in what order is to be wiped out order to realize the
objectives. designing aims at deciding au fait the long run course of action. an idea shows the
committed course of action. Schedule depicts once the planned activities square measure to be
carried, it puts the set up on calendar date scale. briefly planning and scheduling involves the
following:
a) Crystallizing the objectives
b) Collecting and synthesizing the knowledge
c) Developing the choice courses of action among nominative constraints
d) Comparing alternatives in terms of objectives practicability and consequences
e) Selecting and programming the optimum course of action
Scheduling suggests that swing the set up on calendar basis . A project network shows the
sequence and interdependencies of activities, their time durations and their earliest and latest
completion time, however this has to be regular to work out commencement and termination
date of every activity, mistreatment optimum resources or operating with in resource
constraints. A time schedule outlines the project work scheduling, it's a diary of labor.
1.1.1. Scheduling
It is a time based mostly arrangement of project activities; a model of showing the sequence
and temporal order of events needed for a construction project
2. RISK MANAGEMENT
Risk is outlined as associate exposure to the results of uncertainty. Risk is sometimes thought-
about as associate unwanted event that may be known and quantified through its impact and
likelihood of prevalence. The classical definition of risk states that,
Risk = likelihood x Impact
A likelihood of prevalence of that event.
Impact of the event occurring (Magnitude of quantity loss/gain)
2. Workshops
3. Interviews
4. Questionnaire survey
5. Feedback from similar projects
6. Use of specialists
3. PROJECT DETAILS
3.1. Description
Construction of a Balanced Cantilever Bridge Across Coleroon River in District Connecting
Muttam and Manalmedu Village
Minor bridge
Road works
Road Work Forming Embankment
Providing and laying Sub grade work
Providing and laying Course Gravel
Handing over
Table 2
Project Very low Low Moderate High Very high
objective 0.05 0.10 0.20 0.40 0.80
Cost Insignificant <10% 10-20% 20-40% >40%
cost impact cost impact cost impact cost impact cost impact
Schedule Insignificant <5%Schedule 5-10% 10-20% >20%
Schedule impact Schedule Schedule Schedule
impact impact impact impact
control and mitigate their negative impacts. The objective is to understand, and mitigate (or)
control risks.
Understanding the risks inherent with each potential project alternative is important to
controlling cost and developing estimates that reflect the cost of accepted risks. To assist
project management in understanding and controlling contingency as the project progresses
through its development which is a dynamic and continuous process throughout project
development.
5. CONCLUSIONS
Based on the project work carried out the following conclusion are made:
The planning and scheduling is carried out for each phase of the bridge project.
Use of Primavera project planner during execution stage proved to be very useful which
avoided many problems that are arising in office (or) any other places.
By allocating the resources for each activity (or) task the risk involved in the project
identified. The risk assessment for financial, Labour, schedule, environmental hazards is
studied in the project.
The impact of each risk in the project is identified by using the software.
Based on the work carried out the risk report sheet and impact report sheet is presented.
REFERENCES
[1] Amir Tavakoli., (1990) “Effective Progress Scheduling and Control for Construction
Projects”, Journal of Construction Engineering and Management
[2] Harris, R. B., (1998) „„Scheduling projects with repeating activities‟ Journal of Constr.
Eng. Management., 124(4) 269–278.
[3] Hassanein .A and Moselhi. O (2014) “Planning and Scheduling Construction of bridges ”
Journal of Construction Engineering and Management, Vol. 130, No. 5, October 1,
©ASCE
[4] KhaliedHyari and Khaled El-Rayes (2006) “Optimal Planning and Scheduling for
Repetitive Construction Projects “Journal of Management in Engineering, Vol. 22, No. 1,
January 1 ©ASCE,
[5] Kumaraswamy, M.M. and Chan, D.W.M. (1995). “Determinants of construction
duration.” Construction Management and Economics, 13(3), 209-217.
[6] K.K.Chitkara (1994) „Construction Project Management‟ – Tata McGraw-Hill
[7] Publishing Company Limited, New Delhi, pp. 180-218
[8] Ming Lu, M.ASCE and Hoi-Ching Lam (2008)“Critical Path Scheduling Under Resource
Calendar Constraints” Journal of construction engineering and management”, vol.134,
no. 1, January 1 ©ASCE
[9] Mulholland .B and Christian.J (1999)“Risk Assessment In Construction Schedules”
Journal of Construction Engineering and Management, Vol. 125, and No. 1, January
/February, ASCE
[10] Osama Ahmed jannadi and Salman almishari (2003) “Risk Assessment In Construction”
Journal of Construction Engineering and Management, vol.129, no. 5, October 1 ©ASCE
[11] Simaan Abou Rizk, Yasser Mohamed “Optimal Construction Project Planning”-
Proceedings of the 2002 Winter Simulation Conference
[12] Shelly A. Brotherton “Applying the Work Breakdown Structure to the Project
Management Lifecycle” PMP; Robert T. Fried, PMP; Eric S. Norman, PMP, PgMP
[13] “A Note on Project Scheduling”, July 24, 2003 University of Rochester
[14] Suhas S Vokunnaya, Ravindranatha and Tanaji.Thite, Construction Stage Analysis of
Segmental Cantilever Bridge. International Journal of Civil Engineering and Technology,
8(2), 2017, pp. 373–382.
[15] Sreekanth Sura, Alka Sawale and M Satyanarayana Gupta. Dynamic Analysis of
Cantilever Beam. International Journal of Mechanical Engineering and Technology, 8(5),
2017, pp. 1167 –1173.
[16] R. Ganesh, K. Karthik, A. Manimaran and M. Saleem. Vibration Damping Characteristics
of Cantilever Beam Using Piezoelectric Actuator. International Journal of Mechanical
Engineering and Technology, 8(6), 2017, pp. 212–221.