You are on page 1of 4

4/15/2016 Table 1.

                                                                                                                                                            
         

 
  COST ESTIMATES FOR WORK ITEM OF PROJECTS (PESOS)
as of March 2015
  Table 1.4
              
  A. Preventive Maintenance           
              
 
UNIT COST/KM. (PESOS)
SURFACE TYPE SCOPE OF WORK
  NCR CAR REGION I REGION II REGION III REGION IV­A
ASPHALT/CONCRETE Overlay 50mm       6,375,465.65       9,680,395.46       8,463,098.67       9,031,863.18       6,261,273.65            7,676,225.71
    Overlay 80mm      10,208,344.39      15,463,551.29      13,271,900.31      14,457,874.44      10,034,872.30          12,297,490.01
  Overlay 100mm      12,557,259.55      19,184,134.70      16,739,152.85      17,883,144.54      12,336,934.44          15,164,862.96
                 
Overlay 50mm with minor
  ASPHALT
corrections
      7,025,167.77      10,199,562.15       9,052,337.64       9,634,636.15       6,870,035.41            8,311,581.78
(Assumption : Half of the Overlay 80mm with minor
  existing  pavement  w/ corrections
     10,858,046.51      15,982,717.97      14,133,053.52      15,060,647.41      10,643,634.06          12,932,846.09
corrections)
  Overlay 100mm with minor
corrections
     13,206,961.67      19,703,301.40      17,328,391.83      18,485,917.52      12,945,696.21          15,800,219.05
                 
CONCRETE Reblocking with overlay 50mm       9,638,085.76      13,363,387.10      11,777,347.80      12,679,715.20       9,520,817.31          11,043,006.50
  (Assumption  :  30%  for Reblocking with overlay 80mm      13,472,318.30      19,148,771.43      16,859,362.03      17,888,496.79      13,295,924.10          15,665,721.37
reblocking) Reblocking with overlay 100mm      15,822,124.75      22,870,842.96      20,055,553.80      21,533,802.15      15,598,982.85          18,534,051.63
                 

              
              
  UNIT COST/KM. (PESOS)
SURFACE TYPE SCOPE OF WORK
REGION IV­B REGION V REGION VI REGION VII REGION VIII REGION IX
 
ASPHALT/CONCRETE Overlay 50mm      11,842,998.97      12,546,365.10      10,029,277.68       7,619,023.32       9,943,035.90          11,926,793.33
    Overlay 80mm      18,939,779.21      20,069,582.77      16,037,060.61      12,189,034.50      15,896,844.89          19,090,082.57
  Overlay 100mm      23,505,425.05      24,911,904.01      19,878,384.37      15,052,971.23      19,704,033.53          23,675,635.94
 
               
Overlay 50mm with minor
  corrections
ASPHALT      11,781,112.18      13,186,018.22      10,615,302.33       8,207,890.10      10,519,755.92          12,596,864.12
  (Assumption : Half of the Overlay 80mm with minor
existing  pavement  w/ corrections
     19,560,856.92      20,709,235.89      16,623,085.26      12,777,901.28      16,473,564.91          19,760,153.36
  corrections)
Overlay 100mm with minor
corrections
       24,126,502.77      25,551,557.14      20,464,409.02      15,641,838.03      20,280,753.56          24,345,706.74
               
  Reblocking with overlay 50mm

CONCRETE      15,788,290.49      16,145,038.44      13,844,834.96      11,375,786.09      14,114,321.88          15,867,137.54


 
(Assumption  :  30%  for Reblocking with overlay 80mm
reblocking)
       22,886,930.29      23,670,064.68      19,854,485.64      15,947,385.91      20,069,986.29          23,032,474.96
Reblocking with overlay 100mm
 
     27,453,812.52      28,513,587.51      23,697,051.36      18,812,374.17      23,878,408.48          27,619,393.41
 
 
UNIT COST/KM. (PESOS)  
SURFACE TYPE SCOPE OF WORK
  REGION X REGION XI REGION XII REGION XIII  
ASPHALT/CONCRETE Overlay 50mm      10,860,614.59      10,312,487.26      10,362,063.12      12,080,317.38  
 
  Overlay 80mm      17,378,552.11      16,472,095.43      16,582,162.39      19,324,066.19  
    Overlay 100mm      21,542,769.80      20,443,775.47      20,542,323.22      23,983,497.55  
             
  Overlay 50mm with minor
corrections
  ASPHALT      11,496,715.03      10,858,688.11      10,989,061.95      12,710,970.39  
(Assumption : Half of the Overlay 80mm with minor
existing  pavement  w/ corrections
     18,014,652.56      17,018,296.28      17,209,161.22      19,954,719.20  
corrections)
Overlay 100mm with minor
corrections
     22,178,870.26      20,989,976.33      21,169,322.06      24,614,150.57  
             
Reblocking with overlay 50mm
CONCRETE      14,676,548.59      13,856,767.87      14,139,191.09      15,946,609.19  
(Assumption  :  30%  for Reblocking with overlay 80mm
reblocking)
     21,196,635.13      20,018,192.57      20,360,967.81      23,192,542.78  
Reblocking with overlay 100mm
     25,362,286.70      23,991,079.63      24,322,240.77      27,853,432.43  
             

        
B. Rehabilitation/Reconstruction           
              
SURFACE TYPE SCOPE OF WORK UNIT COST/KM. (PESOS)
    NCR CAR REGION I REGION II REGION III REGION IV­A
ASPHALT Recon AC 50mm      10,714,595.91      15,442,300.80      12,435,929.19      13,718,813.46      10,668,804.48          11,834,905.38
(Assumption : with base Recon AC 80mm      14,458,521.65      21,061,306.98      17,432,261.03      19,027,104.89      14,340,086.97          16,358,782.28
failure) Recon AC 100mm      16,746,415.13      24,669,368.75      20,569,710.40      22,371,654.03      16,571,977.12          19,159,359.19
               

CONCRETE Reconstruction PCC 230mm      12,818,027.62      14,676,426.66      12,985,758.14      14,441,888.14      13,125,774.24          13,475,405.17


(Assumption : with base Reconstruction PCC 280mm      14,638,954.40      16,811,231.04      14,861,448.54      16,552,460.40      14,936,908.37          15,385,337.50
failure) Reconstruction PCC 300mm      15,373,755.70      17,673,735.28      15,618,683.11      17,404,134.94      15,668,009.15          16,155,578.61
               
ASPHALT Upgrade to Concrete 230mm      12,294,102.28      13,468,262.79      12,080,045.26      12,713,113.14      12,479,814.99          12,399,586.44
  Upgrade to Concrete 280mm      13,319,329.75      16,459,037.05      13,382,210.58      15,362,397.08      13,435,710.27          13,791,627.94
  Upgrade to Concrete 300mm      14,041,844.18      17,309,380.11      14,248,775.11      16,200,559.54      14,152,675.76          14,547,571.35
               
CONCRETE Reblocking 230mm       5,536,097.62       6,240,557.13       5,631,816.93       6,175,755.14       5,527,666.04            5,697,728.87
(Assumption  :  50% Reblocking 280mm       6,431,165.28       7,292,720.69       6,554,392.44       7,214,114.02       6,415,526.84            6,634,785.76
reblocking) Reblocking 300mm       6,792,412.48       7,717,882.21       6,926,906.70       7,633,185.24       6,773,999.58            7,012,747.45

http://www.dpwh.gov.ph/infrastructure/infra_stat/ATLAS%202014/2014%20Atlas/new_page_139.htm 1/4
4/15/2016 Table 1.4
         
SURFACE TYPE SCOPE OF WORK UNIT COST/KM. (PESOS)
    REGION IV­B REGION V REGION VI REGION VII REGION VIII REGION IX
ASPHALT Recon AC 50mm      16,754,021.17      17,803,461.42      15,189,722.00      12,394,752.29      14,961,338.06          17,616,773.19
(Assumption  :  with  base Recon AC 80mm      23,718,297.78      25,198,537.11      21,064,311.35      16,855,541.63      20,782,987.49          24,631,386.89
failure) Recon AC 100mm      28,193,096.71      29,952,998.98      24,814,315.42      19,644,576.62      24,499,565.08          29,115,016.90
               

CONCRETE Reconstruction PCC 230mm      15,886,354.89      14,323,765.96      15,573,742.84      14,816,527.61      16,627,915.18          16,285,210.80


(Assumption  :  with  base Reconstruction PCC 280mm      18,179,527.47      16,384,860.44      17,737,609.57      16,952,853.36      19,058,339.49          18,530,940.35
failure) Reconstruction PCC 300mm      19,104,215.07      17,218,124.33      18,613,349.30      17,815,844.34      20,041,013.53          19,437,219.16
               
ASPHALT Upgrade to Concrete 230mm      12,957,336.79      12,884,546.61      12,970,552.24      12,591,279.89      12,951,118.76          13,218,391.99
  Upgrade to Concrete 280mm      16,593,648.32      15,351,964.54      15,940,653.54      15,550,812.14      17,462,935.41          16,592,002.60
  Upgrade to Concrete 300mm      17,501,646.22      16,171,856.10      16,798,643.31      16,399,734.13      18,428,994.17          17,478,752.12
               
CONCRETE Reblocking 230mm       6,655,525.80       6,095,305.09       6,430,703.47       6,356,689.65       7,032,465.91            6,627,740.02
(Assumption  :  50% Reblocking 280mm       7,781,212.82       7,109,099.76       7,490,412.24       7,407,229.13       8,226,871.81            7,726,156.02
reblocking) Reblocking 300mm       8,235,201.76       7,519,035.53       7,919,397.11       7,831,680.11       8,709,891.18            8,169,520.77
      
          
UNIT COST/KM. (PESOS)
SURFACE TYPE SCOPE OF WORK
REGION X REGION XI REGION XII REGION XIII
ASPHALT Recon AC 50mm      16,775,586.64      15,340,265.64      15,409,538.41      18,062,744.96
(Assumption : with base Recon AC 80mm      23,136,212.33      21,371,101.08      21,512,756.34      25,146,089.86
failure) Recon AC 100mm      27,192,591.33      25,254,488.82      25,392,770.11      29,695,565.16
           

CONCRETE Reconstruction PCC 230mm      15,958,935.26      14,069,904.00      15,134,597.29      15,856,209.45


(Assumption : with base Reconstruction PCC 280mm      18,086,351.49      16,088,616.97      17,275,321.59      18,036,625.64
failure) Reconstruction PCC 300mm      18,946,347.10      16,905,144.80      18,141,249.45      18,917,970.10
           
ASPHALT Upgrade to Concrete 230mm      13,362,478.15      12,904,810.49      12,704,793.66      13,406,943.05
  Upgrade to Concrete 280mm      16,191,249.22      15,182,772.84      15,631,801.38      16,660,130.75
  Upgrade to Concrete 300mm      17,031,374.11      15,986,558.94      16,481,873.76      17,524,143.15
           
CONCRETE Reblocking 230mm       6,418,760.51       6,007,550.80       6,378,443.50       6,516,641.85
(Assumption  :  50% Reblocking 280mm       7,457,593.08       7,000,942.97       7,428,949.15       7,585,147.71
reblocking) Reblocking 300mm       7,877,645.52       7,402,826.01       7,853,975.33       8,017,143.90

C. Road Upgrading              
               
LEVEL OF SCOPE OF UNIT COST/KM. (PESOS)
IMPROVEMENT WORK FLAT TERRAIN
    NCR CAR REGION I REGION II REGION III REGION IV­A
GRAVEL TO ASPHALT AC 50mm        8,989,108.54      13,293,122.62      10,771,153.32      11,853,252.82        8,884,694.93      10,082,507.21
  AC 80mm      12,547,775.08      18,583,945.25      15,591,481.77      16,921,969.40      12,345,593.20      14,405,431.30
  AC 100mm      14,712,162.43      21,973,218.00      18,611,595.53      20,106,801.96      14,437,227.19      17,072,039.67

               

GRAVEL TO CONCRETE PCC 230mm      11,661,789.87      13,558,042.71      11,872,853.65      13,463,395.83      12,085,682.22      12,445,549.86


 
PCC 280mm      13,663,656.35      15,873,792.61      13,930,302.70      15,792,247.23      14,119,937.36      14,555,003.88
  PCC 300mm      15,160,983.91      17,497,820.21      15,452,238.81      17,553,078.09      15,782,992.06      16,272,073.54
               
               
LEVEL OF SCOPE OF UNIT COST/KM. (PESOS)
IMPROVEMENT WORK FLAT TERRAIN
    REGION IV­B REGION V REGION VI REGION VII REGION VIII REGION IX
GRAVEL TO ASPHALT AC 50mm      14,795,840.91      15,873,568.08      13,225,132.73      10,569,331.83      13,007,198.90      15,559,740.54
  AC 80mm      21,492,290.57      23,009,167.71      18,830,542.28      14,806,571.52      18,561,709.87      22,275,663.75
  AC 100mm      25,788,538.21      27,590,645.55      22,401,093.14      17,446,573.43      22,100,195.15      26,560,166.76

               

GRAVEL TO CONCRETE PCC 230mm      14,920,141.87      13,263,454.60      14,706,827.27      13,773,900.91      15,715,428.21      15,500,907.64


 
PCC 280mm      17,485,002.20      15,531,999.05      17,172,899.55      16,131,936.20      18,423,782.58      18,087,607.66
  PCC 300mm      19,540,192.24      17,233,650.52      19,299,463.37      17,921,175.49      20,559,196.72      20,401,072.73
           
LEVEL OF SCOPE OF UNIT COST/KM. (PESOS)  
IMPROVEMENT WORK FLAT TERRAIN  
    REGION X REGION XI REGION XII REGION XIII  
GRAVEL TO ASPHALT AC 50mm      14,664,223.57      13,397,467.53      13,545,208.71      15,936,896.92  
  AC 80mm      20,709,650.42      19,167,475.42      19,410,387.54      22,699,214.93  
  AC 100mm      24,555,896.86      22,876,978.12      23,131,708.57      27,034,672.30  

             

GRAVEL TO CONCRETE PCC 230mm      15,186,988.94      12,967,694.95      14,183,991.74      14,974,591.60  


 
PCC 280mm      17,662,590.24      15,179,327.45      16,585,912.76      17,448,404.18  
  PCC 300mm      19,958,956.60      13,307,178.28      18,537,152.54      19,544,929.68  

             

 
           

D. Flooded Sections (Raising of Grade and Drainage)           
               
UNIT COST/KM. (PESOS)
SURFACE TYPE SCOPE OF WORK
NCR CAR REGION I REGION II REGION III REGION IV­A

ASPHALT AC 50mm      33,473,900.32      36,657,801.23      31,029,967.86      33,563,540.24      33,037,955.44          38,129,800.02


(Assumption  :  raising  of
grade  by  1.00  meter  & AC 80mm      37,405,489.34      42,535,833.25      36,177,965.60      39,068,226.70      36,913,566.85          42,846,525.84
removal/replacement  of
RCPC at both sides)
AC 100mm      39,820,231.06      46,319,700.86      39,418,177.33      42,545,971.86      39,283,659.62          45,777,561.03
               

http://www.dpwh.gov.ph/infrastructure/infra_stat/ATLAS%202014/2014%20Atlas/new_page_139.htm 2/4
4/15/2016 Table 1.4
CONCRETE PCC 230mm      36,171,704.17      36,414,733.45      31,979,121.06      34,859,140.96      36,170,072.87          40,414,708.56
(Assumption  :  raising  of
grade  by  1.00  meter  &
removal/replacement  of PCC 280mm      38,290,720.75      38,812,150.19      34,103,155.62      37,258,606.86      38,319,463.94          42,657,389.33
RCPC at both sides) PCC 300mm      39,146,796.66      39,781,735.09      34,961,772.01      38,228,266.56      39,188,356.83          43,563,258.70
               

ASPHALT AC 50mm      22,417,087.02      24,974,392.75      20,651,031.88      22,443,290.90      22,340,348.70          23,041,360.27


(Assumption  :  raising  of
grade  by  1.00  meter AC 80mm      26,348,676.04      30,852,424.77      25,799,029.63      27,947,977.36      26,215,960.11          27,758,086.10
without  replacement  of
RCPC at both sides) AC 100mm      28,763,417.76      34,636,292.37      29,039,241.35      31,425,722.52      28,586,052.89          30,689,121.28
               
CONCRETE PCC 230mm      25,114,890.87      24,731,324.97      21,600,185.08      23,738,891.62      25,472,466.14          25,326,268.82
(Assumption  :  raising  of
grade  by  1.00  meter PCC 280mm      27,233,907.45      27,128,741.70      23,724,219.64      26,138,357.52      27,621,857.21          27,568,949.58
without  replacement  of
RCPC at both sides) PCC 300mm      28,089,983.36      28,098,326.61      24,582,836.03      23,821,415.00      17,888,446.15          28,474,818.96
          
               
UNIT COST/KM. (PESOS)
SURFACE TYPE SCOPE OF WORK
REGION IV­B REGION V REGION VI REGION VII REGION VIII REGION IX

ASPHALT AC 50mm      42,713,302.10      45,261,332.80      41,369,413.34      34,917,299.15      43,308,190.64          40,752,705.39


(Assumption  :  raising  of
grade  by  1.00  meter  & AC 80mm      49,927,128.32      52,892,638.06      47,505,703.51      39,577,075.77      49,372,619.34          47,992,366.21
removal/replacement  of
RCPC at both sides) AC 100mm      54,570,832.44      57,807,044.52      51,432,726.52      42,500,879.51      53,253,582.02          52,656,314.63
               
CONCRETE PCC 230mm      42,640,536.33      42,448,900.51      42,710,041.83      37,934,520.83      45,672,728.85          40,318,391.40
(Assumption  :  raising  of
PCC 280mm      45,331,096.71      44,833,602.29      45,318,955.57      40,384,681.57      48,495,902.39          43,016,540.87
grade  by  1.00  meter  &
removal/replacement  of
RCPC at both sides) PCC 300mm      46,417,757.88      45,798,629.18      46,376,051.92      41,375,680.69      49,638,752.89          44,107,541.55
               

ASPHALT AC 50mm      29,717,900.93      29,936,059.63      29,655,079.14      22,908,068.17      27,727,785.39          29,928,833.71


(Assumption  :  raising  of
grade  by  1.00  meter AC 80mm      36,931,727.15      37,567,364.88      35,791,369.31      27,567,844.79      33,792,214.09          37,168,494.53
without  replacement  of
RCPC at both sides) AC 100mm      41,575,431.27      42,481,771.34      39,718,392.32      30,491,648.53      37,673,176.77          41,832,442.95
               
CONCRETE PCC 230mm      29,645,135.16      27,123,627.34      30,995,707.63      25,925,289.85      30,092,323.59          29,494,519.72
(Assumption  :  raising  of
grade  by  1.00  meter PCC 280mm      32,335,695.54      29,508,329.12      33,604,621.37      28,375,450.58      32,915,497.14          32,192,669.19
without  replacement  of
RCPC at both sides) PCC 300mm      33,422,356.71      30,473,356.01      34,661,717.72      29,366,449.70      34,058,347.63          33,283,669.87
 
UNIT COST/KM. (PESOS)  
SURFACE TYPE SCOPE OF WORK
REGION X REGION XI REGION XII REGION XIII  

ASPHALT AC 50mm      45,107,440.48      39,820,005.98      44,628,052.78      48,201,007.27  


(Assumption  :  raising  of
AC 80mm      51,756,197.58      46,093,605.10      50,974,382.96      55,580,393.22  
grade  by  1.00  meter  &
removal/replacement  of
RCPC at both sides) AC 100mm      56,007,660.47      50,141,306.06      55,018,722.51      60,330,282.05  
             
CONCRETE PCC 230mm      45,330,660.47      39,228,992.83      45,231,245.24      46,963,101.50  
(Assumption  :  raising  of
PCC 280mm      47,940,987.19      41,567,176.80      47,780,874.70      49,581,589.77  
grade  by  1.00  meter  &
removal/replacement  of
RCPC at both sides) PCC 300mm      48,997,978.58      42,513,658.03      48,813,261.98      50,641,406.00  
             

ASPHALT AC 50mm      30,936,896.77      28,000,891.93      30,150,611.48      32,717,752.79  


(Assumption  :  raising  of
grade  by  1.00  meter AC 80mm      37,585,653.87      34,274,491.06      36,496,941.65      40,097,138.73  
without  replacement  of
RCPC at both sides) AC 100mm      41,837,116.76      38,322,192.02      40,541,281.21      44,847,027.56  
             
CONCRETE PCC 230mm      31,160,116.76      27,409,878.79      30,753,803.94      31,479,847.02  
(Assumption  :  raising  of
grade  by  1.00  meter PCC 280mm      34,827,434.87      29,748,062.76      33,303,433.40      34,098,335.29  
without  replacement  of
RCPC at both sides) PCC 300mm      34,827,434.87      30,694,543.98      34,335,820.67      35,158,151.52  
           

E. Drainage and Slope Protection           
             
UNIT COST/L.M. (PESOS)
SURFACE TYPE SCOPE OF WORK
NCR CAR REGION I REGION II REGION III REGION IV­A
SLOPE PROTECTION Grouted Riprap (H=3.00)              6,008.70              4,579.52              4,289.58              8,369.84              4,668.62                  5,076.05
(Per Linear Meter) Stone Masonry (H=3.00)            13,779.67            11,549.18            10,748.57            18,896.69            11,289.72                 12,199.36
               
DRAINAGE                        Grouted Line Canal (2.01x.57),v­shaped              1,379.44              1,104.85              1,053.55              1,749.89              1,158.22                  1,225.99
(Per Linear Meter) Concrete Lined Canal (H=1.00x0.60)              8,007.19              7,629.04              9,278.38              7,959.44              7,835.40                  8,943.08
RCPC (910mm. Dia.)/Manhole              7,100.62              7,577.39              6,755.49              7,183.77              6,904.15                  9,151.04
               
UNIT COST/L.M. (PESOS)
SURFACE TYPE SCOPE OF WORK
REGION IV­B REGION V REGION VI REGION VII REGION VIII REGION IX
SLOPE PROTECTION Grouted Riprap (H=3.00)              5,124.98              4,792.70              5,529.25              5,831.49              5,427.83                  6,454.72
(Per Linear Meter) Stone Masonry (H=3.00)            12,790.20            11,930.79            13,302.01            13,768.85            13,247.14                 15,292.87
               
DRAINAGE                        Grouted Line Canal (2.01x.57),v­shaped              1,257.53              1,155.78              1,347.61              1,349.90              1,309.08                  1,526.30
(Per Linear Meter) Concrete Lined Canal (H=1.00x0.60)              8,437.50              8,655.67              8,301.75              8,470.56            10,050.80                  8,072.71
RCPC (910mm. Dia.)/Manhole              8,242.73              9,431.80              7,713.25              7,766.16              9,783.38                  7,203.28
               
UNIT COST/L.M. (PESOS)    
SURFACE TYPE SCOPE OF WORK
REGION X REGION XI REGION XII REGION XIII    
SLOPE PROTECTION Grouted Riprap (H=3.00)              5,411.45              4,946.60              6,182.49              4,812.05    
(Per Linear Meter)
Stone Masonry (H=3.00)            13,078.18            12,165.26            14,739.91            11,985.87    
               
DRAINAGE                        Grouted Line Canal (2.01x.57),v­shaped              1,360.80              1,182.66              1,425.96              1,218.87    
(Per Linear Meter) Concrete Lined Canal (H=1.00x0.60)              8,109.56              7,462.61              8,276.55              8,407.98    
RCPC (910mm. Dia.)/Manhole              8,975.68              7,631.66              9,124.76              9,640.01    
Note :              
1. The price of construction materials are based on the regional average prices plus 15% mark­up for the hauling cost (4th Quarter of CY­2014), equipment rates are based from the
latest ACEL Rates (24th Edition) and labor rates are based on regional labor average  (February 2015).

2. Item A to C, the Estimated Cost excludes cost for Drainage and Slope Protection Works.

3. The Estimated Cost was assumed for a flat terrain condition. A cost factor of 10% for rolling mountainous terrain condition may be applied.  

 
 
http://www.dpwh.gov.ph/infrastructure/infra_stat/ATLAS%202014/2014%20Atlas/new_page_139.htm 3/4
4/15/2016 Table 1.4
 

Back Home Up Next

For questions regarding this Web site contact dpwh_feedback@yahoo.com or the DPWH CFMC .
Last updated: 10/09/15.

best viewed using Internet Explorer 10 or Firefox ver. 28

Disclaimer

http://www.dpwh.gov.ph/infrastructure/infra_stat/ATLAS%202014/2014%20Atlas/new_page_139.htm 4/4

You might also like