  COST ESTIMATES FOR WORK ITEM OF PROJECTS


as of December 2019
  Table 10
              
 
A. Preventive Maintenance           
              
 
UNIT COST/KM. (PESOS)
SURFACE TYPE SCOPE OF WORK
  NCR CAR REGION I REGION II REGION III REGION IV-A
Overlay 50mm      8,170,685.80     10,178,837.18      8,988,648.86      9,655,929.36      8,128,363.54      8,092,573.35
  ASPHALT/ CONCRETE Overlay 80mm     12,991,163.00     16,139,585.70     14,268,071.38     15,325,100.57     12,946,270.67     12,863,262.15
Overlay 100mm     15,984,205.60     19,989,939.45     17,604,128.69     18,922,562.90     15,910,564.36     15,827,658.89
 
               
  Overlay 50mm with
ASPHALT      8,849,622.78     10,884,382.01      9,660,784.93     10,291,013.53      8,776,150.83      8,801,535.12
minor corrections
Overlay 80mm with
  minor corrections
    13,670,099.98     16,845,130.52     14,940,207.44     15,960,184.74     13,594,057.96     13,572,223.93
(Assumption : Half of the existing
pavement w/ corrections) Overlay 100mm with
  minor corrections
    16,663,142.58     20,695,484.27     18,276,264.75     19,557,647.07     16,558,351.66     16,536,620.66

               
 
Reblocking with overlay
CONCRETE     11,805,918.98     14,534,717.10     13,037,754.52     14,126,645.00     12,121,588.30     12,285,442.44
50mm
 
Reblocking with overlay
    16,626,396.18     20,495,465.61     18,317,177.03     19,795,816.21     16,939,495.43     17,056,131.25
(Assumption : 30% for 80mm
  reblocking) Reblocking with overlay
    19,619,438.77     24,345,819.37     21,653,234.35     23,393,278.55     19,903,789.13     20,020,527.98
100mm
              
A. Preventive Maintenance           
               
UNIT COST/KM. (PESOS)
SURFACE TYPE SCOPE OF WORK
REGION IV-B REGION V REGION VI REGION VII REGION VIII REGION IX
Overlay 50mm     12,277,764.31     13,795,609.68     10,280,928.41     10,112,445.85     10,809,251.20     12,773,830.41
ASPHALT/ CONCRETE Overlay 80mm     19,530,491.43     21,963,678.02     16,303,844.82     16,080,218.89     17,171,064.23     20,322,348.83
Overlay 100mm     24,208,639.17     27,234,899.97     20,174,002.95     19,834,918.29     21,226,202.91     25,176,377.84
               
Overlay 50mm with
ASPHALT     12,977,064.56     14,472,085.63     10,931,750.04     10,774,361.22     11,462,459.10     13,486,738.56
minor corrections
Overlay 80mm with
    20,229,791.68     22,640,153.96     16,954,666.45     16,742,134.26     17,824,272.14     21,035,256.98
(Assumption : Half of the existing minor corrections
pavement w/ corrections) Overlay 100mm with
    24,907,939.42     27,911,375.91     20,824,824.58     20,496,833.67     21,879,410.81     25,889,285.99
minor corrections
               
Reblocking with overlay
CONCRETE     17,131,270.82     18,079,552.76     14,919,786.11     14,774,064.58     15,782,584.00     17,608,963.23
50mm
Reblocking with overlay
    24,383,997.95     26,247,621.10     20,942,702.52     20,741,837.62     22,144,397.04     25,157,481.65
(Assumption : 30% for 80mm
reblocking) Reblocking with overlay
    29,062,145.68     31,518,843.05     24,812,860.65     24,496,537.03     26,199,535.71     30,011,510.67
100mm
               
A. Preventive Maintenance           
               
UNIT COST/KM. (PESOS)  
SURFACE TYPE SCOPE OF WORK
REGION X REGION XI REGION XII REGION XIII AVERAGE  
Overlay 50mm     11,587,386.84     12,170,478.35     10,956,990.99     16,927,600.51     10,931,707.79  
ASPHALT/ CONCRETE Overlay 80mm     18,419,213.92     19,314,800.24     17,404,616.52     27,001,232.36     17,377,810.17  
Overlay 100mm     22,796,410.16     23,962,350.91     21,520,710.78     33,496,689.96     21,491,891.43  
              
Overlay 50mm with
ASPHALT     12,300,629.12     12,822,949.35     11,636,945.97     17,620,074.53     11,609,284.20  
minor corrections

https://www.dpwh.gov.ph/dpwh/2019 DPWH ATLAS/Tables & Graphs (Roads)/Road Data 2016/ATLAS 2016/Table 1.4.htm 1/5
6/17/2021 Table 10
(Assumption : Half of the existing Overlay 80mm with     19,132,456.19     19,967,271.24     18,084,571.50     27,693,706.37     18,055,386.58  
pavement w/ corrections) minor corrections
Overlay 100mm with
    23,509,652.43     24,614,821.91     22,200,665.75     34,189,163.97     22,169,467.84  
minor corrections
              
Reblocking with overlay
CONCRETE     16,148,597.52     16,445,015.79     15,300,295.62     21,641,707.10     15,358,993.99  
50mm
Reblocking with overlay
    22,980,424.60     23,589,337.69     21,747,921.15     31,715,338.94     21,805,096.37  
(Assumption : 30% for 80mm
reblocking) Reblocking with overlay
    27,357,620.84     28,236,888.35     25,864,015.41     38,210,796.54     25,919,177.63  
100mm
              
B. Rehabilitation/Reconstruction           
              
UNIT COST/KM. (PESOS)
SURFACE TYPE SCOPE OF WORK
NCR CAR REGION I REGION II REGION III REGION IV-A
ASPHALT Recon AC 50mm     13,789,514.55     16,057,694.77     13,202,230.25     14,646,485.25     13,336,813.45     13,768,568.91
Recon AC 80mm     18,482,417.02     21,861,770.75     18,400,042.74     20,197,638.34     18,056,261.40     18,429,473.04
(Assumption : with base failure)
Recon AC 100mm     21,377,438.87     25,593,887.66     21,669,282.70     23,703,204.39     20,941,648.99     21,307,683.52
               
Reconstruction PCC
CONCRETE     14,490,241.43     15,980,181.90     14,475,114.34     16,199,325.69     14,543,001.28     15,354,659.96
230mm
Reconstruction PCC
    16,425,517.61     18,294,285.88     16,591,074.23     18,612,389.72     16,579,635.48     17,569,911.82
280mm
(Assumption : with base failure)
Reconstruction PCC
    17,216,332.67     19,238,418.40     17,454,307.76     19,594,766.46     17,412,531.90     18,471,187.41
300mm
               
Upgrade to Concrete
    12,693,211.29     14,943,252.34     12,839,992.87     14,737,024.80     12,723,441.13     13,561,708.91
230mm
Upgrade to Concrete
ASPHALT     14,906,400.09     17,607,162.29     15,138,317.05     17,412,347.05     14,976,717.30     16,017,230.14
280mm
Upgrade to Concrete
    15,811,983.43     18,695,562.35     16,076,927.10     18,502,988.96     15,899,141.05     17,017,764.09
300mm
               
CONCRETE Reblocking 230mm      6,314,200.76      7,517,942.02      7,005,428.90      7,725,125.15      6,877,535.53      7,230,689.63
Reblocking 280mm      7,276,074.20      8,669,366.42      8,057,782.23      8,926,016.33      7,890,171.92      8,332,681.95
(Assumption : 50% reblocking)
Reblocking 300mm      7,672,296.95      9,142,389.01      8,490,352.59      9,418,195.16      8,307,714.64      8,784,292.05
              
B. Rehabilitation/Reconstruction           
               
UNIT COST/KM. (PESOS)
SURFACE TYPE SCOPE OF WORK
REGION IV-B REGION V REGION VI REGION VII REGION VIII REGION IX
ASPHALT Recon AC 50mm     17,755,564.46     19,539,023.76     15,827,302.84     15,476,532.70     16,254,732.83     18,726,427.43
Recon AC 80mm     24,861,911.57     27,570,424.03     21,714,164.59     21,334,286.07     22,476,403.84     26,126,887.92
(Assumption : with base failure)
Recon AC 100mm     29,429,026.05     32,737,339.04     25,479,819.68     25,002,529.64     26,424,744.93     30,868,764.40
               
Reconstruction PCC
CONCRETE     18,209,933.01     15,652,157.30     17,390,097.89     17,020,765.14     18,483,263.82     18,228,500.72
230mm
Reconstruction PCC
    20,840,129.02     17,920,658.34     19,847,006.81     19,503,749.89     21,190,846.29     20,838,879.55
280mm
(Assumption : with base failure)
Reconstruction PCC
    21,911,196.94     18,846,656.95     20,847,550.64     20,516,588.73     22,290,558.01     21,900,896.31
300mm
               
Upgrade to Concrete
    16,035,192.64     14,386,441.38     15,219,362.18     15,108,867.73     16,468,163.15     15,997,259.41
230mm
Upgrade to Concrete
ASPHALT     18,978,015.54     16,958,830.55     17,967,908.53     17,831,228.90     19,477,288.67     18,923,033.06
280mm
Upgrade to Concrete
    20,178,214.08     18,010,215.23     19,088,933.81     18,942,976.90     20,701,539.06     20,115,329.84
300mm
               
CONCRETE Reblocking 230mm      8,328,148.49      7,388,684.93      8,001,267.97      8,042,611.04      8,572,080.99      8,322,575.08
Reblocking 280mm      9,637,634.13      8,517,330.55      9,224,056.64      9,278,458.87      9,920,256.35      9,622,155.34
(Assumption : 50% reblocking)
Reblocking 300mm     10,174,084.78      8,981,227.40      9,725,384.19      9,785,878.37     10,471,038.34     10,154,072.86
               
B. Rehabilitation/Reconstruction           
              
UNIT COST/KM. (PESOS)  
SURFACE TYPE SCOPE OF WORK
REGION X REGION XI REGION XII REGION XIII AVERAGE  
ASPHALT Recon AC 50mm     18,075,118.58     17,266,210.75     16,400,869.55     22,974,701.93     16,443,612.00  
Recon AC 80mm     24,737,097.03     24,291,984.49     22,727,123.69     32,890,578.60     22,759,904.07  
(Assumption : with base failure)
Recon AC 100mm     28,986,989.32     28,847,015.26     26,749,380.67     39,267,212.32     26,774,122.97  
               
Reconstruction PCC
CONCRETE     17,526,960.14     15,395,183.25     16,097,723.46     17,753,002.31     16,425,006.98  
230mm
Reconstruction PCC
    19,897,039.95     17,652,404.42     18,365,149.59     20,247,128.20     18,773,487.93  
280mm
(Assumption : with base failure)
Reconstruction PCC
    20,864,817.37     18,572,149.96     19,291,593.41     21,263,112.67     19,730,791.60  
300mm
               
ASPHALT Upgrade to Concrete
    15,350,942.56     14,149,351.41     14,206,962.25     15,795,111.34     14,638,517.84  
230mm

https://www.dpwh.gov.ph/dpwh/2019 DPWH ATLAS/Tables & Graphs (Roads)/Road Data 2016/ATLAS 2016/Table 1.4.htm 2/5
6/17/2021 Table 10
Upgrade to Concrete     18,083,832.43     16,673,253.12     16,737,513.67     18,628,905.30     17,269,873.98  
280mm
Upgrade to Concrete
    19,201,415.82     17,703,051.04     17,772,648.46     19,785,126.92     18,343,988.63  
300mm
               
CONCRETE Reblocking 230mm      7,871,260.51      7,383,110.90      7,523,065.35      8,108,472.88      7,638,262.51  
Reblocking 280mm      9,050,668.58      8,506,055.05      8,651,172.87      9,349,923.46      8,806,862.81  
(Assumption : 50% reblocking)
Reblocking 300mm      9,535,524.67      8,966,985.19      9,115,294.06      9,858,832.39      9,286,472.67  
               
C. Road Upgrading            
               
UNIT COST/KM. (PESOS)
LEVEL OF
SCOPE OF WORK FLAT TERRAIN
IMPROVEMENT
NCR CAR REGION I REGION II REGION III REGION IV-A
AC 50mm     13,686,063.13     15,749,540.17     12,794,124.37     14,343,142.60     13,097,658.53     13,596,036.71
GRAVEL TO ASPHALT AC 80mm     18,565,472.78     21,773,715.72     18,118,886.51     20,067,225.88     17,967,356.36     18,420,965.82
AC 100mm     21,583,247.31     25,651,395.13     21,470,225.82     23,686,153.28     20,950,474.10     21,406,478.00
               
PCC 230mm     15,050,035.46     16,327,619.02     14,422,195.43     16,425,480.35     14,801,922.29     15,748,434.34
GRAVEL TO CONCRETE PCC 280mm     17,288,827.48     18,897,725.70     16,755,146.78     19,088,757.10     17,102,865.37     18,242,580.30
PCC 300mm     18,201,597.58     19,944,263.74     17,704,795.18     20,171,133.58     18,041,442.61     19,255,631.12
               
UNIT COST/KM. (PESOS)
LEVEL OF
SCOPE OF WORK FLAT TERRAIN
IMPROVEMENT
REGION IV-B REGION V REGION VI REGION VII REGION VIII REGION IX
AC 50mm     17,993,467.01     19,249,239.17     15,985,604.04     15,363,532.47     16,373,088.18     19,004,433.90
GRAVEL TO ASPHALT AC 80mm     25,312,530.02     27,475,989.40     22,072,611.49     21,386,381.63     22,798,674.63     26,620,023.45
AC 100mm     30,020,156.03     32,771,690.26     25,970,003.25     25,162,603.60     26,881,532.67     31,504,062.18
               
PCC 230mm     19,338,371.35     15,958,942.49     18,367,973.41     17,504,911.20     19,412,347.80     19,422,320.72
GRAVEL TO CONCRETE PCC 280mm     22,350,290.21     18,482,030.30     21,189,626.23     20,281,692.82     22,472,411.23     22,424,007.59
PCC 300mm     23,575,341.71     19,509,909.27     22,337,062.24     21,412,390.28     23,714,109.56     23,643,944.72
               
UNIT COST/KM. (PESOS)  
LEVEL OF
SCOPE OF WORK FLAT TERRAIN  
IMPROVEMENT
REGION X REGION XI REGION XII REGION XIII AVERAGE  
AC 50mm     18,435,707.95     16,842,369.10     16,354,381.07     23,161,594.21     16,376,873.91  
GRAVEL TO ASPHALT AC 80mm     25,340,772.62     24,040,943.62     22,859,676.14     33,303,633.17     22,882,803.70  
AC 100mm     29,751,775.43     28,709,159.66     26,999,565.09     39,829,949.86     27,021,779.48  
               
PCC 230mm     18,918,303.48     15,444,398.30     16,717,092.37     18,843,212.31     17,043,972.52  
GRAVEL TO CONCRETE PCC 280mm     21,705,303.72     17,925,371.00     19,293,478.95     21,709,339.78     19,700,590.91  
PCC 300mm     22,841,446.82     18,934,205.24     20,344,092.78     22,875,322.45     20,781,668.06  
D. Flooded Sections (Raising of Grade and Drainage)         
               
UNIT COST/KM. (PESOS)
SURFACE TYPE SCOPE OF WORK
NCR CAR REGION I REGION II REGION III REGION IV-A
ASPHALT AC 50mm     41,816,759.73     42,749,601.75     36,831,379.98     39,834,631.73     40,669,988.61     45,113,041.89
(Assumption : raising of grade by 1.00 AC 80mm     46,745,328.53     48,800,338.71     42,168,834.17     45,576,222.99     45,577,994.14     49,969,654.58
meter & removal/ replacement of RCPC at
both sides)
AC 100mm     49,804,265.94     52,704,518.52     45,537,413.02     49,215,799.12     48,596,187.20     52,985,167.66
               
CONCRETE PCC 230mm     43,504,303.58     43,517,736.56     38,566,215.70     42,053,650.93     42,638,612.66     47,486,669.41
(Assumption : raising of grade by 1.00 PCC 280mm     45,842,884.24     46,150,889.37     40,939,064.20     44,765,305.24     45,023,879.72     50,052,594.41
meter & removal/ replacement of RCPC at
both sides)
PCC 300mm     46,796,662.59     47,223,773.18     41,905,797.51     45,868,175.81     45,997,377.64     51,095,491.50
               
UNIT COST/KM. (PESOS)
SURFACE TYPE SCOPE OF WORK
REGION IV-B REGION V REGION VI REGION VII REGION VIII REGION IX
ASPHALT AC 50mm     49,656,810.71     51,342,708.23     47,831,591.18     48,129,133.42     50,125,253.42     46,482,464.35
(Assumption : raising of grade by 1.00 AC 80mm     57,028,110.09     59,612,641.30     53,981,519.39     54,202,380.46     56,595,375.07     54,135,561.12
meter & removal/ replacement of RCPC at
both sides)
AC 100mm     61,779,139.75     64,945,606.83     57,930,185.81     58,021,229.63     60,716,553.25     59,053,142.79
               
CONCRETE PCC 230mm     51,344,723.43     48,340,567.45     50,624,922.49     50,604,799.72     53,461,574.57     47,154,772.35
(Assumption : raising of grade by 1.00 PCC 280mm     54,461,992.32     50,953,679.95     53,571,442.54     53,484,893.94     56,614,268.37     50,237,166.32
meter & removal/ replacement of RCPC at
both sides) PCC 300mm     55,730,292.85     52,018,668.96     54,769,998.58     54,658,063.96     57,894,132.21     51,490,491.77
               
UNIT COST/KM. (PESOS)  
SURFACE TYPE SCOPE OF WORK
REGION X REGION XI REGION XII REGION XIII AVERAGE  
ASPHALT AC 50mm     50,979,842.59     46,237,699.11     49,359,844.84     57,246,731.81     46,525,467.71  
(Assumption : raising of grade by 1.00 AC 80mm     57,932,929.82     53,480,510.53     55,918,923.28     67,439,490.48     53,072,863.42  
meter & removal/ replacement of RCPC at
both sides)
AC 100mm     62,384,799.93     58,187,554.63     60,103,153.23     74,008,199.72     57,248,307.31  
               
CONCRETE PCC 230mm     51,781,566.90     45,138,634.99     50,074,363.13     53,262,258.31     47,472,210.76  

https://www.dpwh.gov.ph/dpwh/2019 DPWH ATLAS/Tables & Graphs (Roads)/Road Data 2016/ATLAS 2016/Table 1.4.htm 3/5
6/17/2021 Table 10

(Assumption : raising of grade by 1.00 PCC 280mm     54,667,517.81     47,713,356.44     52,758,463.24     56,231,208.04     50,216,787.89  
meter & removal/ replacement of RCPC at
both sides) PCC 300mm     55,844,373.59     48,760,864.11     53,853,263.43     57,439,428.63     51,334,178.52  
E. Drainage and Slope Protection           
               
UNIT COST/L.M. (PESOS)
SURFACE TYPE SCOPE OF WORK
NCR CAR REGION I REGION II REGION III REGION IV-A
Grouted Riprap (H=3.00)             6,107.31             5,135.22             4,960.20             5,495.03             5,339.45             5,563.00
SLOPE PROTECTION
(Per Linear Meter)
Stone Masonry (H=3.00)           13,907.22           12,741.01           12,251.73           13,488.90           12,711.14           13,282.67
               
Grouted Line Canal
            2,209.10             2,016.89             1,870.12             2,039.21             2,054.29             2,118.03
(2.01x.57), v-shaped
DRAINAGE                        Concrete Lined Canal
          10,576.84           10,304.80           10,219.52           10,786.33           10,307.87           10,860.57
(Per Linear Meter) (H=1.00x0.60)
RCPC (910mm.
            8,504.74             9,197.31             8,529.54             8,929.64             8,675.11           11,120.67
Dia.)/Manhole
             
UNIT COST/L.M. (PESOS)
SURFACE TYPE SCOPE OF WORK
REGION IV-B REGION V REGION VI REGION VII REGION VIII REGION IX
Grouted Riprap (H=3.00)             6,001.75             5,263.21             6,320.62             6,516.31             6,133.72             6,463.41
SLOPE PROTECTION
(Per Linear Meter)
Stone Masonry (H=3.00)           14,586.45           12,928.09           15,013.84           15,245.39           14,834.55           15,607.17
               
Grouted Line Canal
            2,193.38             1,981.73             2,340.24             2,355.11             2,370.18             2,388.83
(2.01x.57), v-shaped
DRAINAGE                        Concrete Lined Canal
          11,175.99           10,857.12           10,517.48           11,149.26           12,138.33           10,913.22
(Per Linear Meter) (H=1.00x0.60)
RCPC (910mm.
          10,054.76           10,839.01             9,406.95           10,648.30           11,523.92             8,819.99
Dia.)/Manhole
             
UNIT COST/L.M. (PESOS)  
SURFACE TYPE SCOPE OF WORK
REGION X REGION XI REGION XII REGION XIII AVERAGE  
Grouted Riprap (H=3.00)             6,010.84             5,508.99             6,446.93             5,786.54             5,815.78  
SLOPE PROTECTION
(Per Linear Meter)
Stone Masonry (H=3.00)           14,353.87           13,371.31           15,192.48           14,143.27           13,978.69  
               
Grouted Line Canal
            2,341.92             2,121.49             2,311.95             2,232.84             2,184.08  
(2.01x.57),v-shaped
DRAINAGE                        Concrete Lined Canal
          10,475.51             9,918.27           10,464.52           10,741.79           10,712.96  
(Per Linear Meter) (H=1.00x0.60)
RCPC (910mm.
          10,666.82             9,292.71           10,672.39           11,342.47             9,889.02  
Dia.)/Manhole
             
F. New Road Construction            
               
UNIT COST/KM. (PESOS)
SURFACE TYPE SCOPE OF WORK
NCR CAR REGION I REGION II REGION III REGION IV-A
PCC 230mm     25,096,334.56     23,153,202.60     19,695,799.94     22,303,494.45     23,787,235.44     23,639,000.29
CONCRETE PCC 230mm, w/ slope
    31,487,498.94     29,738,339.27     26,991,694.51     30,012,659.40     29,735,349.35     30,536,997.84
protection
               
AC 50mm     26,525,001.16     24,934,593.77     20,067,046.59     22,519,616.34     24,519,392.43     24,046,942.92
ASPHALT AC 50mm, w/ slope
    33,105,304.44     31,716,476.45     27,559,128.92     30,436,573.86     30,656,518.95     31,139,989.09
protection
             
UNIT COST/KM. (PESOS)
SURFACE TYPE SCOPE OF WORK
REGION IV-B REGION V REGION VI REGION VII REGION VIII REGION IX
PCC 230mm     30,030,116.10     25,022,584.33     30,708,892.06     27,989,488.16     29,024,940.63     28,158,981.66
CONCRETE PCC 230mm, w/ slope
    36,309,741.76     30,828,729.24     36,734,888.75     35,260,200.48     36,059,649.01     35,857,882.46
protection
               
AC 50mm     32,168,098.27     30,670,171.08     31,667,600.30     28,553,483.60     29,205,198.17     31,297,475.27
ASPHALT AC 50mm, w/ slope
    38,638,488.21     36,661,534.44     37,886,777.89     36,027,500.27     36,439,178.05     39,205,604.28
protection
             
UNIT COST/KM. (PESOS)  
SURFACE TYPE SCOPE OF WORK
REGION X REGION XI REGION XII REGION XIII AVERAGE  
PCC 230mm     29,113,757.27     24,901,934.54     27,479,357.58     29,231,549.11     26,208,541.80  
CONCRETE PCC 230mm, w/ slope
    35,246,073.85     31,187,651.98     34,459,213.25     35,128,921.39     32,848,468.22  
protection
               
AC 50mm     32,422,751.60     28,385,780.86     29,958,520.28     36,947,248.98     28,368,057.60  
ASPHALT AC 50mm, w/ slope
    38,748,294.74     34,865,523.42     37,136,024.37     43,033,354.19     35,203,516.97  
protection
             
Note :              
1. The price of construction materials are based on the regional average prices plus 15% mark-up for the hauling cost (3rd Quarter 2019 or latest CMPD
value), equipment rates are based from the latest ACEL Rates (25th Edition) and labor rates are based on regional labor average (January 2020).
2. Item A to C, the Estimated Cost excludes cost for Drainage and Slope Protection Works.

https://www.dpwh.gov.ph/dpwh/2019 DPWH ATLAS/Tables & Graphs (Roads)/Road Data 2016/ATLAS 2016/Table 1.4.htm 4/5
6/17/2021 Table 10

3. The Estimated Cost was assumed for a flat terrain condition. A cost factor of 10% for rolling mountainous terrain condition may be applied.

Notes:
 

1.) Road data provided are as of  15 October 2019.

2.) The unit of measure for Road Data is kilometers.

3.) National Roads are classified into:


        Primary Roads - A contiguous length of significant road sections extending linearly without any breaks or forks that connect

major cities (At least around 100,000 population) comprising the main trunk line or the backbone of the National Road System.   
        Secondary Roads - Directly connect cities to national primary roads (except in metropolitan areas) or those not included in the

category of major cities.


Likewise, said roads directly connect major ports, major ferry terminals, major airports, tourist service

centers, major government infrastructure to national primary roads. They also directly connect provincial capitals within the same
region.

        Tertiary Roads - Other existing roads under DPWH which perform a local function. (In the map, these roads are represented

only by letters.)

4.) No Assessment refers to Road Sections that are either under construction and/or segments with length below the 50-meter

gauging length.

For questions regarding this website contact feedback@dpwh.gov.ph