RATE ASPHALT WORK

SR. NO ITEM UNIT RATE


1 Prime Coat Sqm 21
2 Tack Coat Sqm 15
3 DBM Cum 3969
4 BC Cum 4711
5 CRMB 55 Cum 4943
6 MASTIC ASPHALT 40 mm Cum 614
7 MASTIC ASPHALT 25 mm Cum 384
Rate anlysis for CRMB 55
Unit for calculation : Per CM

S.No Item description Unit Qty Rate Amount Remarks


1 CRMB 55 grade Kg 155 24.97 3870.4

2 Aggregate CM 1.2 434 520.8

3 Operating cost CM 1 150 150

4 Laying CM 1 402 402

4943 Per CM
Rate anlysis for BC
Unit for calculation : Per CM

S.No Item description Unit Qty Rate Amount Remarks


1 Bitumin 30/40 grade Kg 145.7 24.97 3638.13

2 Aggregate CM 1.2 434 520.8

3 Operating cost CM 1 150 150


Output 200 MT
4 Laying CM 1 402 402 9000+2*7200+12000+2500

4711 Per CM
Rate anlysis for DBM
Unit for calculation : Per CM

S.No Item description Unit Qty Rate Amount Remarks


1 Bitumin 60/70 grade Kg 112.8 24.97 2816.6

2 Aggregate CM 1.2 500 600

3 Operating cost CM 1 150 150

4 Laying CM 1 402 402

3969 Per CM
Rate anlysis for Tack coat
Unit for calculation : Per SM

S.No Item description Unit Qty Rate Amount Remarks


1 Bitumin emulsion Kg 0.5 22 11

2 Cleaning SM 1 1 1

3 Labour component SM 1 3 3

Rate Per SM 15
Rate anlysis for Primer coat
Unit for calculation : Per SM

S.No Item description Unit Qty Rate Amount Remarks


1 Bitumin emulsion Kg 0.6 22 13.2

2 Cleaning SM 1 1 1

3 Labour component SM 1 4 4

18
Say 21
Rate anlysis for 40 mm thick Mastic
Unit for calculation : Per CM

S.No Item description Unit Qty Rate Amount Remarks


1 Bitumin 30/40 Grad Kg 328 24.97 8190.16

2 CA and FA CM 0.8 600 480

3 Fillar material Kg 750 6 4500

4 Operating cost 1500

5 Labour component 1300


15970 Per CM

Rate per SM for 40mm thickness 614


Rate per SM for 25mm thickness 384