You are on page 1of 10

FORUM

Figure 1:  Computer generated image of the proposed Thermal Energy Storage Tank  (Source: James Cook University, 2007)

District cooling case study –


James Cook University, Townsville
Craig McClintock

ABSTRACT
James Cook University has built Australia’s largest central-energy chilled water plant incorporating stratified chilled water storage
to provide the cooling requirements to all 28 academic buildings within its Townsville campus. The project reduces electrical demand
and thus operating and transport costs, greenhouse gas emissions and maintenance, and provides the university with new refrigeration
plant that has a projected economic life of 30 years.

Keywords — Central Energy Plant, (CEP), chilled water, dynamic control system, maximum demand, Thermal Energy Storage, TES

OVERVIEW OF • 255 hectares of distributed campus incrementally, each with separate,


with 28 academic buildings. stand-alone air conditioning plant.
PROJECT LANDSCAPE
• Total air conditioned floor area The refrigeration chillers are in poor
James Cook of 69,000m2. condition (up to 35 years old) with the
University Site Topology • The earliest recorded building was majority requiring replacement in the
James Cook University (JCU) is located built in 1967 with the majority of next five years, at an estimated cost of
in tropical North Queensland, Townsville. the building stock built before 1990. $9M. The existing plant capacity totals
The University topography and facilities • The university grew in stages, with approximately 11.5MW of cooling in
comprise: additional buildings being added 29 locations around the site.

30 Eco l ibri u m  •  SE P TE M B E R 2 0 0 9


FORUM

• High Voltage (HV) electrical 40 per cent from 9.9MW to 5.4MW refrigerated air conditioning systems
reticulation on site is fragile and non- (2010 scenario) avoiding any high is high and represents a significant part
homogeneous with little spare capacity voltage feeder upgrades. It will also of the University’s operating costs.
to meet foreseeable load growth. provide a relatively ‘flat’ or consistent
Using available benchmark data, the
• There is no master plan for the site electrical demand, which frees up
University has identified that campus
services with poor ‘as-built’ drawing capacity on site, allowing capacity
electrical energy costs are significantly
records, thus making it difficult to for future campus expansion, and/or
higher than comparable facilities
locate or plan alterations to existing allows the utility provider to use this
including most notably the Cairns
underground services. capacity elsewhere.
Campus of the JCU and Charles Darwin
• Utility power bills are in the order • Reduced electricity operating costs University both of which are located
of $2.7M pa. by approximately 30 per cent from in similar climatic regions and both
$3,200,000 to $2,260,000, saving in incorporate stratified chilled water
• Site power maximum demand is the order of $940,000 pa (based on Thermal Energy Storage (TES) systems.
7.3MW (2007) with the utility feeders the current cost of electricity) by 2010.
(consumer mains) capable of 9MW. Due to the strategies adopted in the
• Reduced greenhouse gas emissions early development of the campus (1967)
attributable to the University from each building is served by its own small
Building Program 43,000 tonnes to 31,000 tonnes, cooling plant (water cooled and air
Expansion Drivers saving approximately 12,000 tonnes cooled) generating chilled water to satisfy
CO2 per year by 2010 (this is the the building’s cooling requirements. As a
JCU has an ambitious building equivalent to taking approximately
development program which will expand consequence, more than 28 small isolated
2650 cars off the road). chilled water plants currently exist on
the site to include an additional 25,200m2
of air-conditioned floor area by 2010 and a • Reduced maintenance costs and campus. The plants are of varying age
further 25,000m2 by 2015. The resolutions transport costs associated with (from 2 to 35 years old) and efficiency,
to the following identified drivers are servicing 28 different chillers, pump and many are air-cooled and highly
critical to the development program: groups, cooling towers and the like. inefficient during peak load periods.
The savings are categorised into new The large number of cooling plants also
• The 2010 building program results in high maintenance costs, as the
plant versus old plant maintenance
extrapolated maximum demand cost of maintenance for air conditioning
and central plant versus distributed
of 9.9MW would exceed the utility systems is strongly related to the number
plant. The combined benefit is
provider’s available capacity for the of system elements and travel distance.
anticipated to be more than half
site of 9MW. This would prompt an Many of the small plants have exceeded
the current maintenance costs.
expensive utility power upgrade and or are close to the end of their economic
site wide high voltage power upgrade • New refrigeration plant with a
life and major plant replacement costs
with a fourth ‘feeder’ or supply to the projected economic life of 30 years
will be incurred during the next five
site being required. and improved system reliability
years. The redundant equipment
(redundancy).
• The building program for 2015 will be recycled and sold off.
would also exceed the site high • Reduction in noise pollution
generated by multiple air conditioning The Douglas Campus is about to embark
voltage maximum feeder capacity
plant compared with the central plant on a major expansion program which
by approximately 3MW necessitating
and acoustic treatment. will result in the construction of 8 new
a fourth feeder and upgrades of the
buildings by 2010 and effectively increase
onsite high-voltage trunk cabling and • A building services master plan the air conditioned floor area by over
transformers network. that includes a central spine of 35 per cent.
underground service trenches
Engineered Solution throughout the campus, which
2.0 SITE EXPANSION
streamlines existing services, and
to the Project Drivers allows for future development DRIVERS
JCU Townsville is building Australia’s programs.
With an ambitious building program
largest Central Energy Chilled Water
increasing the academic air conditioning
Plant incorporating Stratified Chilled
Water Storage to provide the cooling
1.0  INTRODUCTION floor area from 69,000m2 (2007) to
The Townsville Douglas Campus of 94,200m2 (2010) and a further 25,000m2
requirements of all 28 existing academic
the JCU represents a typical medium (2015), the following drivers were
buildings. The project is due for
sized University Campus and comprises acknowledged:
completion by April 2009.
approximately 28 academic and service 1. Electrical infrastructure to the
Implementation of the proposed new buildings with a total air conditioned site has an upper limit of 9MW
system after completion of the current floor area in excess of 69,000m2 in 2007. maximum demand. The current
campus expansion projects planned for The campus is situated in the coastal site maximum demand (2007) was
2010 will yield the following benefits: tropics and therefore peak summer air recorded at 7.3MW. On a pro-rata
• Reduction of the instantaneous conditioning loads are high and there is basis future demand up to 2015 could
maximum electrical demand a year round requirement for cooling. be approximately 12MW, well above
for the site by approximately Consequently annual energy usage of the site infrastructure limitations.

SE P TE M B E R 2 0 0 9   • Eco l ibri u m 31
FORUM

The University required an engineered


design solution that offered the lowest
Net Present Value (NPV) solution to
Entry the electrical and mechanical services
Gate-house
infrastructure to support the above
drivers and to lessen the environmental
footprint of the campus. Net Present
Future Value is an accounting term that
development considers the life-cycle costing of
a facility of 25 years (calculated in
today’s money terms), and combines
operating, maintenance, capital and
replacement costs. The NPV allows the
Roadway
facility owners/managers to compare the
Existing
buildings
efficiency of different design solutions,
and plan for future cash flow.

2.1 Basic Concept of the


Central Energy Plant Utilising
Thermal Energy Storage
Location of service In commercial buildings today, air
trenches which carry
chilled water to each conditioning systems can be broadly
building on campus
categorised into two technologies based
on the refrigerant adopted, being Direct
Expansion (DX) and Chilled Water (CW).
DX systems employ the use of a gas
refrigerant which is compressed to a
liquid within a condensing unit, and
gives off waste heat in the process. This
gas is allowed to re-expand back to a
Future gas at a controlled rate within a cooling
development
coil, and thus absorbs heat, or creates a
Thermal energy cooling effect as it does so. Within a fan
storage tank coil unit the air that is to be cooled is
blown over the cooling coils, and then
passed into the desired room. While DX
Central
Energy Plant systems are widely used in commercial
applications, they have a number of
Not to scale
disadvantages including limitations
on maximum pipe runs between the
Figure 2:  Site Plan of James Cook University, Townsville Campus.  (Source: MGF, 2008) condenser and fan coil units, the space
required to accommodate multiple
outdoor condensing units, limitations in
2. A significant electrical upgrade will campuses and similar facilities
systems capacity and reduced operating
be required by the University and ($2.6M pa).
efficiency at partial load conditions.
utility provider if the current building 5. Maintenance cost of chillers (and
services design philosophy air conditioning system) is high In contrast, chilled water systems adopt a
is maintained. compared to central energy plant single central chiller plant which uses water
3. Existing air conditioning system facilities. heat transfer fluid in the buildings, of which
philosophy of stand alone chiller the temperature is typically lowered to 6°C,
6. JCU recognised a need for a site master and supplies water at this temperature to all
plants is not suitable for a large plan that combined electrical and fan coil units. The flow of water is regulated
facility. Economies of scale provide mechanical services infrastructure through the various cooling coils using
greater opportunities for efficiency in centralised services trenches for modulating valves to maintain precise
the larger the plant, and therefore all existing and future services. control over the cooling coil and therefore
reduced running cost, maintenance
7. The design philosophy is the supply air-stream temperature. This
costs, and simpler upgrades as
commensurate with Ergon’s (local system allows much more accurate control
technology improves. Replacement
electricity supply authority) objective over temperature and humidity than DX
cost of chillers over the next five
to manage peak demand with a view systems. Water leaving the cooling coil
years is estimated at $9M. to reducing infrastructure capital absorbs the heat energy from the air-stream
4. University utility operating costs are expenditure and improving utilisation and is raised to approximately 15°C before
high compared with other university of their network assets. being returned to the chiller plant.

32 Eco l ibri u m  •  SE P TE M B E R 2 0 0 9


Announcing the launch of FansSelect Australia’s newest fan
and blower selection software.
Designed by engineers for engineers, FansSelect offers features and
improvements that makes the job of selecting the right fan easier
than it’s ever been before.

FAN
Simple and intuitive to use, no training required.
A single screen interface allows all information to be accessed and
viewed quickly.
Simple to use selection filters allow you to short list your options

SELECTION
quickly and easily.
Dynamic simulation of fan performance under variable speed control
shows adjusted power, sound and flow characteristics.
Selection results table can be tailored to return only your chosen

AT YOUR
performance criteria.
Click headings to sort on any column in the results table,
e.g. sound, absorbed power, BCA compliance etc.
Web based for online updates; data and specifications always

FINGERTIPS.
up to date.
Includes fan sound attenuation options.
BCA Section J5.2 2009 compliance instantly visible for all selections.
Broader selection options including Chicago Blower centrifugal fans.
Full project schedule and datasheet functions.
Easy export of all data to clipboard and auto save functions to
protect your work.

FansSelect represents over 3 years of engineering development


and over a quarter of a million dollars invested to make the task
of selecting fans truly a breeze.
Go to our website and instantly download FansSelect, it’s free!

DESIGNED BY ENGINEERS FOR ENGINEERS

TM

1300 733 833


www.fansdirect.com.au
FORUM

WARM WATER

PRIMARY CHILLED
WATER PUMP INDIVIDUAL BUILDINGS
DAY TIME TANK MASS THERMAL SECONDARY CHILLED
CHARGE CYCLE ENERGY STORAGE WATER PUMP

CHILLER
COOL WATER
TERTIARY CHILLED WATER PUMPS

WATER TANK CENTRAL ENERGY PLANT SITE RETICULATION

Day-time operation

WARM WATER

PRIMARY CHILLED
WATER PUMP INDIVIDUAL BUILDINGS
NIGHT TIME TANK MASS THERMAL SECONDARY CHILLED
CHARGE CYCLE ENERGY STORAGE WATER PUMP

CHILLER
COOL WATER
TERTIARY CHILLED WATER PUMPS

WATER TANK CENTRAL ENERGY PLANT SITE RETICULATION

Night-time operation

Figure 3:  Process Flow Chart  (Source: MGF, 2007)

Central Energy Plant (CEP) is the chilled water system, except that the of the water. This head thus improves
centralised plant for the district cooling. chiller plant takes the form of one efficient the efficiency of the CEP/TES interface.
It contains the chillers, cooling towers, centralised plant rather than 28 different
The CEP building houses:
pumps and thermal energy (chilled cooling plants. The central energy plant
water) storage tank. It offers the benefits has a design Coefficient Of Performance • three 4.2MW centrifugal high
of high efficiency, central plant, reduced (COP is a measure of efficiency) of 6 efficiency chillers, with provision for
maintenance, ease of expansion and at summer conditions of 33°C dry bulb an additional two chillers in the future
technological upgrades as technology and 27°C wet bulb. • primary and secondary chilled water
advances. On large centralised plant such pumps (with variable speed drives)
as this, ‘redundancy’ or back-up systems
are included in the system architecture,
3.0 ENGINEERING • condenser water pumps (with variable
speed drives)
which allows for continuous supply in DESIGN RESPONSE
• four 5.1MW cooling towers
the event of a component failure. The design solution proposed a new (with variable speed drives on the
Thermal Energy Storage (TES) makes use Central Energy Plant (CEP) integrated fans) with provision for a 5th tower
of periods of the day or night when the site with a Thermal Energy Storage (TES)
• CEP office
demand for cooling is less than the average element. The final engineering design
response was determined by comparing • low voltage and high voltage
demand, by running central chilled water switch room
plant during these times to chill return several computerised energy models of
the site. (Refer to section 4.1.) • the building is air conditioned
water (from 15°C) back to chilled water (at
rather than mechanically ventilated
6°C). During times when the site demand The chiller and water storage facility
to prolong plant life and prevent
exceeds the average demand (typically is located in the southeast part of the
condensation (corrosion) issues.
in the afternoon), the chilled water is campus at sufficient elevation to ensure
drawn from the storage tank. From here, that water level in the thermal storage The 12 mega litre TES tank contains
the pre-cooled water is then reticulated tank represents the highest point in the specially engineered top and bottom
throughout the campus and delivered to chilled water network, thus ensuring water diffusers to allow the water leaving
fan coil units within each building. The the ‘static head’ or pressure floods all or entering the tank to do so without
installation of air-conditioning systems the chilled water pipework, preventing turbulence. This allows the chilled and
within the buildings themselves remains air pockets from being trapped in the returning warm water to stratify within
essentially the same as any conventional pipework, and thus affecting flow the one single tank.

34 Eco l ibri u m  •  SE P TE M B E R 2 0 0 9


FORUM

Site Power Profile 2007 & 2010 (20th Feb)–Status Quo Approach
tank. The secondary pumps pressurise
12000 the main water spine throughout the
campus, and the tertiary pumping
systems control the flow of chilled water
10000
in each building. They are controlled to
deliver a variable water flow to match
8000 the instantaneous cooling demand with
a fixed pressure setting throughout the
Power (kWe)

building. The variable speed drives on


6000 these pumps allow them to ramp back
their speed as demand for chilled water
4000
declines, and as they do this, the pump
power demand reduces significantly, thus
delivering energy savings.
2000
The heat in each building is carried
via the water medium back to the top
0 of the TES tank for storage and night
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (24 Hr)
time cooling.

SITE POWER PROFILE 2007 SITE POWER PROFILE 2010


3.1  Computerised Energy Model
CHILLER PROFILE 2007 CHILLER PROFILE 2010

Figure 4:  Chiller Plant Contribution to Maximum Demand  (Source: MGF, 2006) A detailed computer model of the
electrical and refrigeration demand
The water is pumped out of the bottom 7.8kM of underground uninsulated of the campus was developed during
of the TES tank with a variable speed piping which is fed to each building. The the feasibility study to determine the
pumping system to match the site cooling primary pumping system pumps water impact of the proposals on energy usage
demand. The water is distributed to through the chillers and into the TES profiles and energy costs. The model was

DEMAND THE BEST


COPPER FLANGES WITH
GALVANISED PROTECTION

Same price as Powder


Coated Flanges
100% Electrolysis Protection
Suitable for corrosive and
salt environments
100% UV Protection,
will not fade, crack or
deteriorate after installation

KEEP JOBS IN AUSTRALIA.


Copper BUY AUSTRALIAN MADE.
Electrolysis Adapter
Insulator
Galvanised
Backing Flange WaterMark
AS 3688 Lic 1344
SAI Global

Phone: +61 3 9484 4155 ctsfab.com.au SE P TE M B E R 2 0 0 9   • Eco l ibri u m 35


FORUM

Site Power Profile 2007 & 2010 (20th Feb) – CEP/TES Solution
cooled machines proposed
10000 for incorporation in the CEP.
9000
• It will allow chilled water to be
generated at night during off-peak
8000 tariff periods when electricity costs are
7000
lower and ambient air temperatures are
lower are more favourable, and stored
6000 in the TES tank for use the next day.
Power (kWe)

5000 Figures 5 and 6 show the impact of the


proposed higher efficiency CEP and TES
4000
system combination on site electrical
3000 load profiles for year 2007 and year 2010
scenarios.
2000
Figures 5 and 6 show that implementation
1000
of the CEP/TES system will immediately
0 reduce the current maximum demand
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 from 7.3 MW to 5.3 MW and shift a
Time (24 Hr)
significant part of the University’s power
SITE POWER PROFILE 2007 SITE POWER PROFILE 2010 usage to off-peak tariff periods.
CHILLER PROFILE 2007 CHILLER PROFILE 2010 A significant part of the energy
SITE POWER PROFILE 2010 reduction is due to better chiller
–STATUS QUO
efficiencies. More significantly it will
Figure 5:  Impact of CEP/TES on Site Maximum Demand  (Source: MGF, 2006) permit the current expansion planned
by the University to be undertaken
based on exhaustive analysis of existing The model was tested against actual 2007
without any increase in the electrical
campus electrical and cooling loads maximum demand and electricity usage
maximum demand of the campus.
and was derived by empirical methods data and demonstrated close correlation.
and supported by data furnished by
Figure 4 shows the derived load profiles 3.3 Energy Efficiency Inclusions
the University’s facility management
for a November peak load day for year
personnel. In order to achieve best engineering
2007 and year 2010 scenarios respectively.
The year 2010 scenario is based on a practices, several computerised energy
Using the data the following profiles were
continuation of the distributed plant models were created for different plant
derived for 2007, and extrapolated for
arrangement currently employed configurations and manufacturers. Three
2010 and 2015 scenarios:
at the University. chiller manufacturers were compared
• Separate average and peak chiller with performance data provided. The
electrical load profiles incorporating The graphs show the following. governing equation for each chiller was
chillers, chiller water pumps, condenser • Over 50 per cent of the peak site derived and run through the energy
water pumps and cooling tower fans for electrical demand is created by model as a function of weather data
each hour of each day of a typical year. chiller plant operation and “Chiller” (dry bulb and wet bulb), load seasonal
This load element can be modified by and “Other” peaks are generally profiles and time. The control strategy
the implementation of TES. coincident. implemented will take advantage of the
• Other profiles incorporating general selected chiller optimum performance
• Maximum demand and energy ’sweet spot’ which is at 80 per cent load.
light and power electrical loads and loads consumption is highest during the
associated with air handling fans and on-peak periods when the cost of The chilled water flow rate is varied
the like. This load is relatively constant electricity is highest. pending on inventory levels of the tank
and unaffected by seasonal cooling to take advantage of the pumping energy
• Site maximum demand will increase
variations. Although these loads remain savings and chiller performance. The
from the current 7.3MW to 9.8 MW
modified by use of thermal storage, condenser water flow rate to the cooling
by year 2010
they do influence the analysis when towers is also varied to maintain a fixed
alternative tariff structures are being temperature difference with a minimum
considered. The electrical loads from 3.2 Impact of Proposed CEP/ water flow rate setting taking advantage
lighting and general power usage are TES System on Site Electricity of the pump energy savings.
unavoidable during daytime with its Usage
more expensive electrical tariff. However By also employing variable speed pumps
The proposed CEP/TES system will for condenser water flow, coupled to
the TES system allows for some of the significantly alter the campus electrical
electrical load to be transferred to night, a floating set point condenser water
load profiles as follows. temperature adjustment, further
incurring lower tariffs.
• It will reduce the energy required efficiencies are gained. Traditionally
Profiles were further adjusted to reflect to generate chilled water as a the control systems in most commercial
the impact of weekend and holiday consequence of the superior efficiency buildings have static set points which
periods on chiller and other load profiles. of the large high efficiency water do not reflect the seasonal climatic

36 Eco l ibri u m  •  SE P TE M B E R 2 0 0 9


FORUM

conditions as a function of time. directly on high voltage were able to be steel roof members proved a cost saving
The focus of the energy modelling and used. The chillers comprise an11kV motor of approximately $40,000 in capital cost.
building management control system and high voltage soft starter kit to enable
the site high voltage reticulation to be Avoided insulation: Medium Density
was to create an innovative solution that
directly coupled to the chillers without the Polyethylene (MDPE) piping has been
is dynamic (alive) and which constantly
need to reduce the 11kV to 415V power used for irrigation and water reticulation
changes its operating parameters to
supply (industry standard). Conventional for some time. Chilled water distribution
reflect the seasonal variance. The plant
practice would be to use motors that in buildings is generally constructed
operation is governed by an algorithm
operate on low voltage, which incur in metal pipes that require thermal
which is based on seasonal ambient
transformer efficiency losses, transformer insulation, normally 50mm polystyrene.
conditions, and also considers the input
capital cost, switchgear and switchboard By using MDPE pipework to reticulate
from temperature and humidity sensors.
capital cost; increased building floor area the chilled water throughout the campus,
to house additional indoor transformers insulation was avoided, and the greater
3.4  Further System Efficiencies 12M pipe lengths available reduced
and savings in long term maintenance.
Value adding to this project over and The estimated savings in avoiding these the number of joints, flexibility in the
above the CEP/TES design, included was $800,000 in capital cost. installation, and flexibility for future
the control strategy of the central plant; branch take offs, thus providing savings.
the selection of the high voltage chiller Reduced plant-room structure: Typically The wall thickness of the 500mm diameter
motors; the CEP piping arrangement to plant pipe work is suspended from the MDPE is 29.6mm which is directly
reduce the roof steel member sizes and roof structure, thus increasing the size buried in a compact sand fill, offering
selection of the underground reticulated of these structural elements. By using an high thermal performance, and inherent
chilled water piping (7.8kM). innovative chilled water pipe manifold vapour barrier and mechanical protection
arrangement where five headers were with the MDPE outer surface of the pipe.
Using high voltage equipment: The chiller stacked above each other on support
selected is a result of further energy frames, the weight of the headers High water temperature differential:
modelling with a three stage compression (majority of piping weight) was carried The chilled water on site has a fixed
centrifugal chiller selected. Due to the directly by the floor slab and not the steel supply temperature of 6°C and return
size of the plant, motors that operate roof framing. The reduction in size of the temperature of 15°C, which gives

GO the complete solution


GREEN
YOUR
GREEN BUILDING
PARTNER

• # 1 in performance …worldwide
• Largest global producer of Enthalpy Wheels
• The first choice of engineers /consultants …
worldwide
• Received AHRI Performance Award for
100% Success Rate for 7 consecutive years

Energy Recovery Heat Recovery Evaporative


Ventilators Wheels Cooling Pads

Members of
green building council australia
member
CERTIFIED PERFORMANCE

www.bigfootsystems.com.au
BA/DRI/944C

www.drirotors.com
Contact our Australian Rep. Office Tel.: 08 92762307• Fax: 08 9375 7989
Mob. 0412932317• Email: sundermalkani@bigpond.com
Or, for QLD, NSW & ACT, Contact our Agent: Automatic Control Co. Pty Ltd., Brisbane
Tel: 07 3808 9400 • Fax: 07 3808 6955 • Mob. 0413 051 590 Pro Pipe Supplies Pty Ltd, 13-15 Main Street, Beverly, SA5009
Email: dfroes@automaticcontrol.com.au t: +61 8 8268 8633 enquiries@propipesupplies.com.au
USA | Brazil | Europe | Turkey | Malaysia | Thailand | Philippines | China | Korea | Japan | Australia

SE P TE M B E R 2 0 0 9   • Eco l ibri u m 37
FORUM

Caution tape

COMPACT FILL
Electrical and
data trunk cabling

MDPE branch
pipe for chilled water

Potable water RETURN SUPPLY


supply pipes Trunk pipes for
chilled water
reticulation
SAND FILL

Figure 6:  Typical Section through Trench  (Source: MGF, 2007)

a 9° temperature differential. electrical and mechanical services for the 3. Services corridor and common
Conventional systems tend to operate site was conceived. This enabled future trench arrangement.
on a 6–7° differential. Using a greater designers and building expansions to
differential requires 25 per cent lower utilise the parameters set for consistence As part of the high voltage study it was
flow rate, and thus requires less pumping and simplicity across the site. The Master revealed that the existing site network
energy and smaller pipes, 160mm to planning for the university comprises was frail and exposed to failure with
560mm ø. However this also required three key areas: non-homogenous conductors and three
the air-handing units within the building independent feeds. As part of the high
1. Standard for site wide chilled water
to be calibrated for these less common voltage upgrade, all conductors are
supply temperatures and pressures
parameters and the chillers to work for future building connections as upgraded to a homogenous size and ring
harder to restore the 6°C water during detailed above. main units were installed to enable back
the night time cooling cycle. feeding and system backup / redundancy.
2. High voltage (HV) site upgrade and
Services Master Plan: During the course rationalisation for future building The civil works created known service
of the design, a master plan of the program. corridors on site with a common trench

Year 2007 Scenario Year 2010 Scenario


Location
Distributed Plant With CEP/TES Distributed Plant With CEP/TES

Site Maximum Demand 7.3 MW 5.3 MW 9.8 MW 5.4 MW

Energy Usage per year


32,000,000 23,000,000 41,228,077 30,360,806
[KWH]

Electricity Costs per year


$ 2,651,346.00 $ 1,786,908 $ 3,200,000 $ 2,260,000
(2007 rate)*

Greenhouse Gas
33,643 Tonnes CO2 24,729 Tonnes CO2 43,000 Tonnes CO2 31,000 Tonnes CO2
Generation per year

* Detailed tariff prices based on March 07 Utility rates.

Table 1:  Model Predictions for proposed and business-as-usual systems  (Source: MGF, 2006)

38 Eco l ibri u m  •  SE P TE M B E R 2 0 0 9


FORUM

Location Tank Capacity TES Capacity PROJECT DETAILS


Client:  James Cook University,
State Archives Centre Runcorn, Qld 1.5 Ml 13,000 KWH Facility Maintenance.
Sponsors / Partners:  
Ergon Limited
William McCormack Place Cairns Principal Design, Mechanical and
1.5 Ml 13,000 KWH
(proposed), Qld Electrical Design Consultant:  MGF
Consultants (NQ) P/L and MGF
Consultants P/L
Telfer Mine (Mine Cooling), NT? 1.8 Ml 15,000 KWH
Building Design Consultant: 
MGF Consultants (NQ) P/L and
JCU Cairns Campus 3.3 Ml 22,000 KWH Power Graham and Dempsey
Architects P/L
Civil Design Consultant: 
Curtin University WA 3.8 Ml 30,000 KWH Maunsell Australia P/L
and MGF Consultants (NQ) P/L.

Charles Darwin University, NT 8.6 Ml 72,000 KWH Builder:  Dave Harney


Constructions P/L
Mechanical Contractor (CEP): 
JCU Townsville Douglas Campus AE Smith P/L
12 ML 106,000 KWH
(under construction) Mechanical Contractor (Building
Connections):  Green APS
Table 2:  Current Australian large chilled water TES systems  (Source: MGF, 2009) Electrical High Voltage
Contractor:  Protech P/L
TES Tank Contractor:  Acqacon P/L
housing chilled water supply and return BIOGRAPHY Civil Contractor: 
piping, high voltage conduits and BMD Constructions P/L
communications conduits. Figure 6 is Craig McClintock (BE Mech Hons C1;
a typical section through the service RPEQ, MIEAust, MAIRAH) is the
corridor trench. Townsville branch manager of MGF
Consultants, and is a JCU alumni.
Since starting in the building services This paper was first published
4.0  CONCLUSION engineering industry in 1992, Craig as “CAS 54 District Cooling Case
Study – James Cook University,
JCU Townsville Douglas Campus has has worked extensively in contracting, Townsville” in the Environment
embarked on the largest CEP/TES system consulting and the state government Design Guide in 2009.
in Australia with completion expected engineering department to service the
in April 2009 followed by 12 months of commercial and institutional buildings
verification. Outcomes predicted by the in the tropics of North Queensland. He
model are summarised in tabular form was the principal mechanical services
engineer on the JCU project. Craig McClintock was
below.
This paper was presented at AIRAH’s
the winner of AIRAH’S 2007
Accordingly the CEP/TES proposal will
Achieving the Green Dream Conference. Future Leaders Award.
in year 2010 effectively reduce the site
Maximum Demand by 4.5 MW, save the Contact: craig@mgfnq.com.au  ❚
University $990,000 in energy costs and
reduce greenhouse gas impact by 12,000
tonnes CO2-e p.a. Project Awards
The project has received
Currently the following large scale the following awards:
stratified chilled water TES systems are
operating in Australia. • Engineers Australia
Queensland Division
On completion of the project, JCU 2008 Excellence Award,
Townsville will have constructed Reports, Procedures
Australia’s largest district cooling system and Systems category
with high efficiency central energy plant • Engineers Australia
incorporating large scale thermal energy 2008 Australia Excellence
water storage. The author believes this Awards finalist.
type of system should be more commonly • Townsville City Council 2008
used and could provide an important Excellence in Sustainability
tool for demand side management, and Innovation Business
energy reduction strategies and future Award.
infrastructure master planning.

SE P TE M B E R 2 0 0 9   • Eco l ibri u m 39

You might also like