Professional Documents
Culture Documents
YEAR 0 1 2
Production, MMSCFD 0 0 45
Production, BSCF 0 0 16.4
Heating capacity BTU/SCF 1000 1000 1000
Production, MMBTU 0 0 16,425,000
Gas Price, $/MMBTU 5 5 5
Gross Revenue, M$ 0 0 82,125
First Trance (20% Gross Revenue) 0 0 16,425
80% Gross Revenue 0 0 65,700
COST RECOVERY, M$ :
Non Capital Expenditure 20,000 30,000 41,063
Unrecovered Other Costs 0 25,100 58,500
Depreciation 0 0 6,000
Equity to be Split 0 0 0
Summmary
Net Contractor Share -30,000 -20,000 6,000
Cost RecoVery 0 0 65,700
Total Contractor Share -30,000 -20,000 71,700
Government Share 0 0 16,425
Total Share -30,000 -20,000 88,125
DMO Calculation
Production, MMBTU 0 0 16,425,000
Contractor Share 53.5714% 0 0 8,799,107
Gasl Price, $/MMBTU 5 5 5
DMO (25% Con Share) 25% 0 0 2,200
Price DMO 10% 0.5 0.5 0.5
Contractor Share 0 0 1,100
Contractor Loss for GOI 0 0 9,899
Yearly 0 1 2
CAPITAL EXPENDITURE
Exploration Drilling (Tangible) 0 0 0
Development Drilling (Tangible) 0 0 0
Artificial Lift 0 0 0
Production Facilities (Incl Pipeline) 0 0 0
Pipe line 0 0 0
Office & Housing Movables 0 0 0
PROFITABLITY ANALYSIS
YEAR 0 1 2
NET CASH FLOW -30,000 -20,000 6,000
CUMULATIVE NCF -30,000 -50,000 -44,000
1 1
1.0 1.0
PROFITABILITY ANALYSIS
PARAMETERS
Recoverable Gas, BSCF 148
Peak Rate, MMSCFD 45
Capital Investment, M$ 50,000
Expense Investment, M$ 50,000
TOTAL EXPENDITURE, M$ 100,000
YARDSTICKS:
Average Gas Price, $/MMBTU 5
Max Cash Impairement, M$ (50,000)
Net Cash Flow, M$ 42,482
NPV @ 15% Discount, M$ -5,918
IRR, % 12%
P/I Ratio 0.4
Payout , years 5.8
Cross Check
Gov.take+cost Rec+NC) 739,125
delta 0%
G CONTRACT
3 4 5 6 7 8
45 45 45 45 45 45
16.4 16.4 16.4 16.4 16.4 16.4
1000 1000 1000 1000 1000 1000
16,425,000 16,425,000 16,425,000 16,425,000 16,425,000 16,425,000
5 5 5 5 5 5
82,125 82,125 82,125 82,125 82,125 82,125
16,425 16,425 16,425 16,425 16,425 16,425
65,700 65,700 65,700 65,700 65,700 65,700
3 4 5 6 7 8
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
32,850 32,850 32,850 32,850 32,850 32,850
8,213 8,213 8,213 8,213 8,213 8,213
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
3 4 5 6 7 8
8,800 7,040 11,883 19,855 16,730 7,391
-35,200 -28,160 -16,277 3,578 20,308 27,700
1 1 1 0.0 0 0
60,000
1.0 1.0 1.0 0.8
40,000
-20,000
-40,000
-60,000
9 10 TOTAL
45 45
16.4 16.4 148
1000 1000
16,425,000 16,425,000
5 5
82,125 82,125 739,125
16,425 16,425 147,825
65,700 65,700 591,300
41,063 41,063
0 0 8,500
9 10
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0
0 0 50,000
0
0
0
0 0 0
0 0 0
0 0 50,000
0 0 0
0 0 0
32,850 32,850 295,650
8,213 8,213 73,913
0 0 0
0 0 0
0 0 0
0
41,063 41,063 419,563
9 10
7,391 7,391 42,482
35,091 42,482
0 0
5.8
Row 105
10
LONG TERM CASH FLOW FOR INDONESIA PRODUCTION SHARING CONTRACT OIL FIELD
YEAR 0 1 2
Production, BOPD 0 0 1,000
Production, MBO/YEAR 0 0 365
Oil prce, $/BO 50 50 50
Gross Revenue, M$ 0 0 18,250
First Trance (20% Gross Revenue) 0 0 3,650
80% Gross Revenue 0 0 14,600
COST RECOVERY, M$ :
Non Capital Expenditure 14,000 21,000 5,931
Unrecovered Other Costs 0 14,000 35,000
Depreciation 0 0 4,750
Equity to be Split 0 0 0
Summmary
Net Cash Flow -33,000 -92,000 8,669
Cost RecoVery 0 0 14,600
Total Contractor Share -33,000 -92,000 23,269
Government Share 0 0 3,650
Total Share -33,000 -92,000 26,919
DMO Calculation Without DMO 0
Production, MBO 0 0 365
Contractor Share 26.7857% 0 0 98
Gasl Price, $/MMBTU 50 50 50
DMO (25% Con Share) 25% 0 0 24
Price DMO 10% 5.0 5.0 5.0
Contractor Share 0 0 122
Contractor Loss for GOI 0 0 1,100
EXPENDITURE BUDGET - S
Yearly 0 1 2
10000
2 3
CAPITAL EXPENDITURE
Exploration Drilling (Tangible) 3,000 0 0
Development Drilling (Tangible) 3,000 9,000 0
Artificial Lift 2,000 2,000 0
Production Facilities (Incl Pipeline) 4,000 50,000 0
Pipe line 5,000 10,000 0
Office & Housing Movables 2,000 0 0
PROFITABLITY ANALYSIS
YEAR 0 1 2
NET CASH FLOW -33,000 -92,000 8,669
CUMULATIVE NCF -33,000 -125,000 -116,331
1 1
1.0 1.0
PROFITABILITY ANALYSIS
PARAMETERS
Recoverable Oil, MBO 18,676
Peak Rate, MBOPD 10,000
Capital Investment, M$ 90,000
Expense Investment, M$ 35,000
TOTAL EXPENDITURE, M$ 125,000
YARDSTICKS:
Average Oil Price, $/bbl 50
Max Cash Impairement, M$ (125,000)
Net Cash Flow, M$ 71,893
NPV @ 15% Discount, M$ -9,077
IRR, % 12%
P/I Ratio 0.6
Payout , years 4.9
Cross Check
Gov.take+cost Rec+NC) 933,823
ONTRACT OIL FIELD
3 4 5 6 7 8 9
10,000 8,607 7,408 6,376 5,488 4,724 4,066
3,650 3,142 2,704 2,327 2,003 1,724 1,484
50 50 50 50 50 50 50
182,500 157,079 135,199 116,367 100,158 86,207 74,199
36,500 31,416 27,040 23,273 20,032 17,241 14,840
146,000 125,663 108,159 93,094 80,126 68,966 59,359
3 4 5 6 7 8 9
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
47,450 40,841 35,152 30,255 26,041 22,414 19,292
11,863 10,210 8,788 7,564 6,510 5,603 4,823
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
2005 6012 0
9983 7491 22464 0
0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0
0 0 0 0
0 0 0
0 0
0
11987.1 13502.1 22464.4 0 0 0 0
3 4 5 6 7 8 9
61,580 31,688 25,096 24,691 29,190 6,142 5,287
-54,752 -23,064 2,033 26,724 55,914 62,056 67,343
1 1 0 0.0 0 0 0
1.0 1.0 0.9
100,000
50,000
0
0 1 2 3 4 5 6 7 8 9 10
Row 113
-50,000
-100,000
0
0 1 2 3 4 5 6 7 8 9 10
Row 113
-50,000
-100,000
-150,000
10 TOTAL
3,499
1,277 18,676
50
63,864 933,823
12,773 186,765
51,091 747,059
20,756 338,493
0
0 90,000 428,493
20,756 508,574
0 9,180
Total cost delta
20,756 428,493 428,493 0
30,335 318,566
9,351 136,738
22,210 233,236
3,849 56,280
-428 -6,253
3,575 13,437
38,558 433,437
3,421 50,026
8,126 85,330
-3,849 -56,280
428 6,253
8,126 85,330
0 90,000
9,180
8,126 -13,850
3,575 13,437
4,550 -27,287
4,550 71,893
4,550 71,893
20,756 428,493
25,306 500,386
38,558 433,437
63,864 933,823
the value have to equal GR 933,823
Delta 0 OK
1,277 18,676
342 5,003
50
86 1,251
5.0
428 6,253
3,849 56,280
10
0 3,000
0 12,000
0 4,000
0 54,000
0 15,000
0 2,000
0
0 90,000
0
0
0
0 0
0 0
0 7,000
0 28,000
0 0
16,605 242,794
4,151 60,699
0 0
0 0
0 0
20,756 338,493
20,756 428,493 0
10
0 90,000
0
19,000
71,000
0
0
0
0
0 0
0 0
0 0
0 0
0 90,000
10
4,550 71,893
71,893
0
4.9
CONCESSIONARY CALCULATION PR
Production, BO 750,000 900000 5000
Oil Price, $/B 50 53
Revenue, $ 37,500,000
Royalty, $ 20% 7,500,000
Net Revenue, $ 30,000,000
Deductions, $ 40.0% 15,000,000 45%
Taxable Income, $ 15,000,000
Provincial Tax 10%, $ 10% 1,500,000
Net of Prov Tax, $ 13,500,000
Federation Tax 40%, $ 40% 5,400,000
Net after tax, $ 8,100,000
PSC CALCULATION
Summmary
Net Contractor Share 2,249,999 450
Recoverable 15,000,000 2,000
Total Contractor Share 17,249,999 2,450
Government Share 20,250,001 2,550
Total Share 37,500,000 5,000
-300
DMO Calculation
Production, bo 750,000
Contractor Share 26.7857% 200,893
Oil Price, $/b 50
DMO (25% Con Share) 25% 50,223
Price DMO 10% 5
Contractor Share 251,116
Contractor Loss for GOI 2,260,043
PSC YEMEN
Production, BO 1
Price, $/B 100
Revenue, $ 100
Royalty 10% 10
Net Revenue 90
Cost Recovery 17% 15 15
Profit oil 75
Contractor Profit OIL 25% 19
Government Profit oil 71% 53
YOGC Profit oil 4% 3
Government share
Royalty 10
Profit oil 53
YOGC Share 3
Sub Total 66
Contractor share
Profit oil 19
Cost recovery 15
Sub Total 34
PSC OMAN
Production, BO 1
Price, $/B 100
Revenue, $ 100
Royalty 0% 0
Net Revenue 100
Cost Recovery 15% 15
Profit oil 85
Contractor Profit OIL 20% 17
Government Profit oil 80% 68
(Assumption prod < 10 MBOPD) 0
Government share
Royalty 0
Profit oil 68
Sub Total 68
Contractor share
Profit oil 17
Cost recovery 15
Sub Total 32
KSO CONTRACT
Production 20
Crude Price 50
Gross Revenu 1,000
Cost Recovery 30% 300
Equity to be split 700
Government Share
Equity share 32.7731% 229
DMO 168
DMO fee -168
Income tax from PN 138
Income tax from Con 52
Total Government Share 420
Pertamina share
Equity share 42.0169% 294
DMO 63
DMO fee -16
Taxable income 341
Tax 40.50% 138
Total Pertamina Share 203
Contractor share
Equity share 25.2100% 176
DMO loss -63
DMO fee 16
Taxable income 129
Tax 40.50% 52
Total Contractor Share 77
CROSS CHECK
Revenue 79
Investment 20
Expense 31
Tax 14
Input 79
Output 65
Total NCF 14 This number have to equal with NCF on the table
YEAR 0 1 2 3
1 Revenue 100 1000
2 Investment 1000 100
3 Expense 200 400
4 Depreciation 200 220
5 TAX 0 0 152
Net Cash Flow (NCF) -1000 -100 -100 448
CROSS CHECK
Revenue 4400
Investment 1100
Expense 1840
Tax 704 Inv. yr-1 1000 200 200
Inv. yr-2 100 20
Input 4400 200 220
Output 3644
Total NCF 756 This number have to equal with NCF on the table
4 5 6 7 8 9 10 TOTAL
800 700 600 500 400 200 100 4400
1100
400 300 200 100 100 100 40 1840
220 220 220 20 1100
72 72 72 152 120 40 24 704
328 328 328 248 180 60 36 756
Declining balance
n 5 20 16 12.8 10.24 40.96
n 4 25 18.75 14.06 10.55 31.64 for depreciation distribu
n 8 12.50 10.94 9.57 8.37 7.33 6.41 5.61 39.27
Double DB
n 5 40 24 14.4 8.64 12.96
YEAR 0 1 2 3 4 5 6
1 Revenue 100 1000 800 700 600
2 Capital Investment 1000 100
3 Expense 200 400 400 300 200
4 Depreciation 200 180 144 115.2 419.84
Taxable income -300 420 256 284.8 -19.84
5 TAX 40% 0 168 102.4 113.92 0
Net Cash Flow (NCF) -1000 -100 -100 432 297.6 286.08 400
PROBLEM-2 Calculate NCF based on double declining balance depreciation for 5 years
YEAR 0 1 2 3 4 5 6
1 Revenue 100 1000 800 700 600
2 Capital Investment 1000 100
3 Expense 200 400 400 300 200
4 Depreciation
Taxable income
5 TAX 40%
Net Cash Flow (NCF)
C1
C2
Total
Total
100
100
100 Medco oil
100 Medco gas
100
7 8 9 10 TOTAL
500 400 200 100 4400
1100
100 100 100 40 1840
40.96 1100
359.04 300 100 60
143.62 120 40 24
256.38 180 60 36 748.06
0
7 8 9 10 TOTAL
500 400 200 100 4400
1100
100 100 100 40 1840
Contoh Perhitungan Discounted Net Cash Flow
Tentukan discount rate agar cumulative NCF = 0
Cumul.
Year 0 1 2 3 4 5 NCF
Net Cash Flow (NCF)
0% -20.0 5.0 12.0 15.0 10.0 10.0 32.0 IRR=
i= 5% -20.0 4.8 10.9 13.0 8.2 7.8 24.7
i= 10% -20.0 4.5 9.9 11.3 6.8 6.2 18.8
i= 15% -20.0 4.3 9.1 9.9 5.7 5.0 14.0
i= 20% -20.0 4.2 8.3 8.7 4.8 4.0 10.0
i= 25% -20.0 4.0 7.7 7.7 4.1 3.3 6.7
i= 30% -20.0 3.8 7.1 6.8 3.5 2.7 4.0
i= 35% -20.0 3.7 6.6 6.1 3.0 2.2 1.6
i= 40% -20.0 3.6 6.1 5.5 2.6 1.9 -0.4
IRR yaitu sekitar 39% karena cumulative discount NCF = 0
YEAR 0 1 2 3 4 5
1 Revenue 100 1000 800 700
2 Capital Investment 1000 100
3 Expense 200 400 400 300
4 Depreciation 200 180 144 115.2
Taxable income -300 420 256 284.8
5 TAX 40% 0 168 102.4 113.92
Net Cash Flow (NCF) -1000 -100 -100 432 297.6 286.08
IRR= 10%
NPV= 13
C1 200 160 128 102.4 409.6
C2 20 16 12.8 10.24 40.96
Total 200 180 144 115.2 419.84 40.96
NPV 18.8
YEAR 0 1 2 3 4 5
1 Revenue 100 1000 800 700
2 Capital Investment 1000 100
3 Expense 200 400 400 300
4 Depreciation 200 180 144 115.2
Taxable income -300 420 256 284.8
5 TAX 40% 0 168 102.4 113.92
Net Cash Flow (NCF) -1000 -100 -100 432 297.6 286.08
Cumulative NCF -1000 -1100 -1200 -768 -470.4 -184.32
IRR= 10%
NPV= 13
C1 200 160 128 102.4 409.6
C2 20 16 12.8 10.24 40.96
Total 200 180 144 115.2 419.84 40.96
NPV 18.8
YEAR 0 1 2 3 4 5
1 Revenue 100 1000 1000 2000
2 Capital Investment 1000 500
3 Expense 200 400 400 300
4 Depreciation 200 260 208 166.4
Taxable income -300 340 392 1533.6
5 TAX 40% 0 136 156.8 613.44
Net Cash Flow (NCF) -1000 -500 -100 464 443.2 1086.56
Cumulative NCF -1000 -1500 -1600 -1136 -692.8 393.76
IRR= 22%
NPV= 788
C1 200 160 128 102.4 409.6
C2 100 80 64 51.2 204.8
Total 200 260 208 166.4 460.8 204.8
Chart Title
4000
3000
2000
1000
NCF
Row 111
0
0 1 2 3 4 5 6 7 8 9 10 11
-1000
-2000
Time, years
payout= 4.6 years
39%
6 7 8 9 10 TOTAL
600 500 400 200 100 4400
1100
200 100 100 100 40 1840
419.84 40.96 1100
-19.84 359.04 300 100 60
0 143.616 120 40 24
400 256.384 180 60 36 748.064
0.10243
1000
100
Chart Title
1000
Chart Title
1000
500
0 Row 72
0 1 2 3 4 5 6 7 8 9 10 11
-500
-1000
-1500
6 7 8 9 10 TOTAL
600 500 400 200 100 4400
1100
200 100 100 100 40 1840
419.84 40.96 1100
-19.84 359.04 300 100 60
0 143.616 120 40 24
400 256.384 180 60 36 748.064
215.68 472.064 652.064 712.064 748.064
0.10243
Payout 4.6 Years lihat gambar
1000
100
P/I Ratio discounted 10% 0.011517 < 0.75 investasi tidak menarik
UNIR 0.623387
Assumption Hurdle rate = 20% Proyek ini tidak menarik atau tidak diterima oleh investor
6 7 8 9 10 TOTAL
1500 1000 1000 500 100 8200
1500
200 100 100 100 40 1840
460.8 204.8 1500
839.2 695.2 900 400 60 4860
335.68 278.08 360 160 24 2064
964.32 621.92 540 240 36 2796
1358.08 1980 2520 2760 2796
0.21708
Payout 4.6 Years menarik
1000
500
P/I Ratio discounted 10% 0.545092 < 0.75 investasi tidak menarik
UNIR 1.7475
Assumption Hurdle rate = 20% Proyek ini menarik atau diterima oleh investor
Parameter
Investment 1500
Yardsticks
Payout 4.6 years < 5 years
IRR 22% > hurdle rate 20%
P/I Ratio UD 1.86 > 1
P/I Ratio dict 0.545092
UNIR 1.7475 >1
Row 111
Kesimpulan
1
This proyect is profiatable
OPERATOR : PT. MEDCO E&P INDONESIAA
Contract Area : Rimau Extention Block
Budget Year : Long Range Forecast
(In Thousand of US. Dollars) NET CASH FLOW
Yearly 1 2
Forecast Forecast
INDONESIA SHARE :
Pertamina Equity Share 0 0
Lifting Price Variance / FTP 0 1,279
Domestic Requirement 0 0
Government Tax Entitlement 0 313
CONTRACTOR SHARE :
Contractor Equity Share 0 0
Lifting Price Variance / FTP 0 468
DMO LOSS (Table - 19) 0 0
Yearly 1 2
Forecast Forecast
CAPITAL EXPENDITURE
Exploration Drilling (Tangible) 0 0
Development Drilling (Tangible) 292 3,796
Artificial Lift 0 0
Production Facilities (Incl Pipeline) 0 1,538
Pipe line 0 0
Office & Housing Movables 0 0
DOMESTIC REQUIREMENT
1 2
Forecast Forecast
DEPRECIATION
1 2
Forecast Forecast
1 2
Forecast Forecast
PRODUCTION
KAJI+SEMOGA 0.000 0.598
OTHER RIMAU 0.00 0.00
Total 0 1
Production
Proration
PL Pengabuan 0.6 0 0
PL Tempino 0.1 0 0
Export 0.3 0 0
P/L Fee P/L Toll Fee
PL Pengabuan 0.13 0 17
PL Tempino 0.62 0 14
Export 1.00 0 66
Total P/L fee 0 96
Table - 1
NET CASH FLOW ANALYSIS
3 4 5 6 7 8 9 10
Forecast Forecast Forecast Forecast Forecast Forecast Forecast Forecast
3 4 5 6 7 8 9 10
Forecast Forecast Forecast Forecast Forecast Forecast Forecast Forecast
0 0 0 0 0 0 0 0
3,358 292 0 0 0 0 0 0
0 0 0 0 0 0 0 0
15,479 8,828 1,116 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
8,832 768 0 0 0 0 0 0
0 0 0 0 0 0 0 0
11,165 45,489 45,569 40,129 35,249 30,963 27,197 23,890
2,791 11,372 11,392 10,032 8,812 7,741 6,799 5,972
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
913 2,235 2,620 2,240 1,910 1,629 1,389 1,185
3 4 5 6 7 8 9 10
Forecast Forecast Forecast Forecast Forecast Forecast Forecast Forecast
Table - 4
DEPRECIATION
3 4 5 6 7 8 9 10
Forecast Forecast Forecast Forecast Forecast Forecast Forecast Forecast
Table - 5
PIPE LINE FEE
3 4 5 6 7 8 9 10
Forecast Forecast Forecast Forecast Forecast Forecast Forecast Forecast
3 10 10 8 7 6 5 4
0 2 2 1 1 1 1 1
1 5 5 4 4 3 3 2
33,854 510,066
13,450 205,717
5228 36,861
5,314 100,876 Cross Check
Gov.take+cost Rec+NC) 1,404,889 1,404,889
57,846 853,520 delta 0% 0%
12,385 186,607
4,920 75,261
(5,228) (36,861)
0 4,254
12,077 229,262
(5,314) (100,876)
6,763 128,385
27,241 431,227
34,004 559,612
0
6,763 128,385 0
128,385
0 3
6,763 128,385
128,385
0 3
0
11 TOTAL
Forecast Forecast
0 0
0 7,738
0 0
0 26,960
0 0
0 0
0 34,698
0 0
0 0
0 0
0 20,352
0 0
20,985 282,166
5,246 70,541
0 0
0 0
1,010 15,227
27,241 388,286
27,241 422,984
9.14 7.44
11
Forecast Forecast
6.29
0.00
40.0
39.5
5228 79,966
0 0
5228 79,966
11 0
Forecast Forecast
0 34,698
292
5,334
18,837
9,120
1,116
0 31,342
0 34,698
11 0
Forecast Forecast
6.291
0.00
6
4
1
2
179 2,740
142 2,178
689 10,310
1010 15227
OPERATOR : P.T. MEDCO E&P INDONESIA Lapangan Y
Contract Area : PSC - South Sumatra Extension
Budget Year : Long Range Forecast 1
NET CASH FLOW ANALYSIS - GAS PROD
1 SCF=1150 BTU 1 2
SCF to BTU 1.15 Forecast Forecast
INDONESIA SHARE :
Government Equity Share 0 0
Lifting Price Variance / FTP 0 101
Domestic Requirement 0 0
Government Tax Entitlement 0 159
CONTRACTOR SHARE :
Contractor Equity Share 0 0
Lifting Price Variance / FTP 0 168
DMO LOSS (Table - 19) 0 0
Table - 2 ASSUMPTION
EXPENDITURE BUDGET - SUMMARY,
1 2
Forecast Forecast
Table -3
DOMESTIC REQUIREMENT
1 2
Forecast Forecast
Table - 3
DEPRECIATION
1 2
Forecast Forecast
CAPITAL
1400 0
1 2
Forecast Forecast
0.0 2.3
Total 0.0 2.3
Table-5 Gas Price, $/MMBTU
1 2
Forecast Forecast
Table-6 Revenue, M$
1 2
Forecast Forecast
MMB 0 1,343
Total Revenue 0 1,343
P/L 1 2
Toll Fee Forecast Forecast
$/MMBTU
MMB 0.47 0 395
Total Revenue 0 395
#DIV/0! 0.47
Lapangan Y
Coy
1 1 1 242
3 4 5 6 7 TOTAL
Forecast Forecast Forecast Forecast Forecast Forecast
0 0 0 0 0 0 GOVERNMENT TAKE, M$
COST RECOVERY, M$
NET CONTRACTOR SHARE, M$
0 0 0 0 0 0 GROSS REVENUE, M$
101 101 101 101 101 604
0 0 0 0 0 0
75 75 75 75 75 534 Cross check: GR=GT+CR+NCS
0 0 0 0 0 0
168 168 168 168 168 1,007
0 0 0 0 0 0
0 0 0 0 0 187
168 168 168 168 168 1,194
(75) (75) (75) (75) (75) (534)
93 93 93 93 93 660
1,075 1,075 1,075 1,075 1,075 6,447
1,167 1,167 1,167 1,167 1,167 7,107
3 4 5 6 7 TOTAL
Forecast Forecast Forecast Forecast Forecast Forecast
0 0 0 0 0 0
0 0 0 0 0 1,400
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 700
265 271 278 285 292 1,649
66 68 69 71 73 412
0 0 0 0 0 0
0 0 0 0 0 150
395 395 395 395 395 2,367
UIREMENT
3 4 5 6 7 TOTAL
Forecast Forecast Forecast Forecast Forecast Forecast
3 4 5 6 7 TOTAL
Forecast Forecast Forecast Forecast Forecast Forecast
0 0 0 0 0 1,400
3 4 5 6 7 #REF!
Forecast Forecast Forecast Forecast Forecast Forecast
2.3 2.3 2.3 2.3 2.3
2.3 2.3 2.3 2.3 2.3
3 4 5 6 7 #REF!
Forecast Forecast Forecast Forecast Forecast Forecast
3 4 5 6 7 1400
Forecast Forecast Forecast Forecast Forecast Forecast
3 4 5 6 7 TOTAL
Forecast Forecast Forecast Forecast Forecast Forecast
0.0 0.0
e, MMSCFD 2.00 2.00
1,100 1,100
Investment 850 850
1,950 1,950
0 1 2 3 4
Production, bo 100 1,000 861 741 638
Crude Price 50 50 50 50 50
Gross Revenue, $ 5,000 50,000 43,035 37,041 31,881
First Trance 20% 1,000 10,000 8,607 7,408 6,376
Revenue after FTP 4,000 40,000 34,428 29,633 25,505
Cost Recov 40% 2,000 20,000 17,214 14,816 12,753
Equity to be Split 2,000 20,000 17,214 14,816 12,753
Gavernment 73.2143%
FTP Share 732 7,321 6,302 5,424 4,668
Equity share 1,464 14,643 12,603 10,848 9,337
Domestic Requiremet (DMO) 301 3,013 2,594 2,232 1,921
Adjustment of DMO -33 -335 -288 -248 -213
Tax 236 2,357 2,029 1,746 1,503
Total Government Share 2,700 27,000 23,239 20,002 17,216
Contractor 26.7857%
FTP Share 268 2,679 2,305 1,984 1,708
Equity share 536 5,357 4,611 3,969 3,416
Domestic Requiremet -301 -3,013 -2,594 -2,232 -1,921
Adjustment of DMO 33 335 288 248 213
Taxable Contractor Share 536 5,357 4,611 3,969 3,416
Tax 44% -236 -2,357 -2,029 -1,746 -1,503
Net Contractor Share 300 3,000 2,582 2,222 1,913
Summmary
Net Contractor Share 300 3,000 2,582 2,222 1,913
Recoverable 2,000 20,000 17,214 14,816 12,753
Total Contractor Share 2,300 23,000 19,796 17,039 14,665
Government Share 2,700 27,000 23,239 20,002 17,216
Total Share 5,000 50,000 43,035 37,041 31,881
DMO Calculation
Production, bo 100 1,000 861 741 638
Contractor 26.7857% 27 268 231 198 171
Oil Price, $/b 50 50 50 50 50
DMO (25% C 25% 7 67 58 50 43
Price DMO 10% 5 5 5 5 5
Contractor Share 33 335 288 248 213
Contractor Loss for GOI 301 3,013 2,594 2,232 1,921
5 6 7 8 9 10
549 472 407 350 301 259
50 50 50 50 50 50
27,441 23,618 20,328 17,497 15,060 12,962
5,488 4,724 4,066 3,499 3,012 2,592
21,952 18,895 16,263 13,998 12,048 10,370
10,976 9,447 8,131 6,999 6,024 5,185
10,976 9,447 8,131 6,999 6,024 5,185