Professional Documents
Culture Documents
Orientation Schedule
TRAINING REPORT
Name of Mentor/Guide
Projects Period Days
at project level
Project 1
Project 2
Project 3
Project 4
Support Services
Name of Mentor/Guide
Projects Period Days
at project level
Scope of work
Construction of Coal Jetty of length 555m and 25m wide.
Port Craft Jetty of length 180m and 10m wide.
Port Operational Jetty of length 180m and 10m wide.
Breakwater of about 915m to protect jetty.
Approach Bridge of 10.10m wide for a distance of 7.90km
Conveyor Galleries at Jetty and Approach Bridge.
Junction Towers JNT1(On Shore) & JNT1A(On Jetty)
Grab Shore Unloaders – 2nos of 2000TPH each
Belt Conveyor System – 2nos of 555m each
Pipe Conveyor System – 2nos of 9.6km
Building – Administrative, Control and Substation
Electrical System and other services.
Major Construction Activities
Properties
Materials Permissible Limit Test Frequency Remarks
(Physical/Chemical)
Tuticorin
OPC53 Sikaplast 175(+/
M50 PSC Girder power - - 0.32 430 50 - - - 154 3.84 563 561 758 - 28 - 2521.84
Dalmia 5201NS -25)
plant
Tuticorin
OPC53 Sikaplast 175(+/
M40 Piling power - - 0.33 365 110 - - - 157 3.80 632 515 712 - 28 - 2454.8
Dalmia 5201NS -25)
plant
Tuticorin
Precast/In OPC53 Sikaplast 150(+/
M40 power - - 0.32 370 100 - - - 150 3.76 642 524 724 - 28 - 2515.75
-situ Dalmia 5201NS -25)
plant
Piling :
1. Approach Pile Details :
Pile Diameter = 1200 mm
Liner thickness = 8mm
C/C Distance of Pile = 9m and 7m in cross direction up to 39
and 234 pile grid respectively, 34m in long direction.
Pile Cut off level = (+) 5.975m MCD & (+) 6.725m MCD for
Expansion joint & Non-expansion joint respectively.
Pile Founding level = pile founding level shall be a minimum
of 7.35m depth below the existing seabed level subjected
to a minimum Rock Socketing of 4d and 5d for grid A and C
respectively. Founding level for piles at subsequent grids
shall be verified by consultant based on the boring data at
completed pile location.
Dummy Liner Thickness = 16mm
Founding level = Founding level of the dummy pile depends
upon the soil strata and there is a specified criteria for
fulfilment of the requirement.
2. Pile Boring :
Method = Conventional
Boring done by the Chisel & Bailer.
SPT = this test is performed to fix the rock top level.
(Criteria – Start of rock socket shall be considered where
SPT ‘N’ values is >120)
PPR = Aim is to fix the founding level of the pile. (Criteria –
Pile penetration is less than equal to 10cm for 277 blows
using 3.5T weight of chisel)
4. Pile Concreting :
Grade of Concrete = M40
Concreting Process = Tremie Method
Test conducted after the concreting = Pile Integrity Test (PIT)
2. Erection Activities :
Precast members are transported by the trailer with proper
arrangement from the precast yard to the unloading point.
Trolley positioning.
Lifting.
Placing.
Fixing of temporary bracing
Shifting
Locking
Accropode Casting :
Volume = 4cum
Grade of Concrete = M30
Total no. of accropode required = 5530nos
Casting Completed = 695nos (As on 12.04.2019)
Production = 10nos/day
Curing Compound = BASF Master Cure
Mr Bindeshwar Prasad 5
Project Manager Division
Land No.:119-120, Ph-20, Vill.-Mouja Asoli, Tehsil-Kamptee, Near Bhushan Steel
Address/Location Godown, Bhandara Road (Nh-6), Nagpur-440035, India
Scope of work
Piling work (1200 dia 1284nos)
Construction of Pile Cap (250nos)
Construction of Pier (276nos)
Construction of Pier cap/Cantilever (242nos)
Construction of Pier Arm (45nos)
Construction of Track Arm (44nos)
Construction of Portal (17nos)
Segment Casting (2383nos)
Segment Erection (2383nos)
Piling work.
Precast Structures.
Pre-stressing work.
Launching work.
RCC-Cast-in-situ
Segment Casting For Viaduct Work.
Properties
Materials Permissible Limit Test Frequency Remarks
(Physical/Chemical)
SIKA
Ultratech 175(+/
M35 Pile viscocret - - - 0.38 320 125 - - - 150 4.0 717 425 213 581 28 - 2535.00
OPC53 -25)
e 5138
SIKA
Ultratech 175(+/
M35 T-Girder viscocret - - - 0.39 380 61 - - - 148 3.8 730 424 592 227 28 - 2565.80
OPC53 -25)
e 5138
SIKA
Ultratech 150(+/
M50 Segment viscocret - - - 0.33 450 75 - 0.91 - 150 4.5 734 414 548 188 28 - 2564.41
OPC53 -25)
e 5138
Segment Casting :
1. Dimensional Details Of Segment:
Length – Depend upon the span geometry of Piers.
Width – 8.5m
Web thickness – Varies from 600mm to 360mm (for
34m span)
Soffit thickness – Varies from 450mm to 270mm (for
34m span)
Height – 2.0m from soffit to deck
Parapet – Height 0.9m and width 0.150m
OHE – Height 0.9m, width 0.660m and length 0.950m
2. Concreting Activities:
Bed alignment
Side Shutter alignment & fixing
Surface cleaning and apply of shutter oil
Reinforcement placing with proper cover block
Inner shutter alignment & fixing after the surface
cleaning and apply of shutter oil
Bulk head fixing
Shutter vibrator fixing
Concreting
3. Concreting Sequence:
Soffit Slab
Half height of web – 1
Half height of web – 2
Remaining half of the web – 1
Remaining half of the web – 2
Deck slab including parapet & OHE
Grade of Concrete – M45 & M50
4. Time Cycle:
Bar cutting & bending – 2 to 4 hrs.
Bar binding – 4 to 5 hrs.
Profiling – 2hrs.
Final checking – 2hrs
Concreting – 2 hrs.
1. Casting Bed:
T-Girder – 14 Nos.
R-Girder – 3 Nos.
2. Girder Shutter:
Typical girder – 4 set
Nagpur girder – 2 set
Rectangular girder – 2 set
3. Concreting Activities:
Casting bed cleaning and applying of shutter oil
Reinforcement placing with proper cover blocks
Side shutter fixing and applying of shutter oil
Stopper fining and applying of shutter oil
Concreting
Grade of concrete – M35
4. Dimensional Details:
Length – Varies (max 15.55m)
Width – Soffit 400mm and deck 1495mm (T-Girder)
Web thickness – 225mm (T-Girder)
Height – 1250mm (T-Girder)
Width – 600mm (R-Girder)
Height – 1175mm (R-Girder)
Scope of work
1. Elevated Parking –
Piling
Pile Cap
Beam
Column
Roof
2. AT Grade Road –
Piling
Retaining Wall
Deck slab
3. Storm Water Drain
4. Ballah piling for temporary land filling
Piling work.
5. Superstructure work.
6. Storm water drainage work
7. Filling work.
8. RCC-Cast-in-situ
9. Temporary ballah piling work.
DMC Piling :
3. DETAILS OF PILE: (KHARAGPUR END)
Length – -34.00m RL (P119-P200)
Cut off level – varies
Diameter – 0.750m
Grade of concrete – M30
Liner length – 10.08m (6mm thick)
Reinforcement – 16mm, 25mm & 32mm as longitudinal
bars. 16mm bar used as spacer and 10mm bar used as
tie. Lap length considered as 46D
No. of piles – Elevated parking (76nos), AT Grade road
(200nos), Howrah side (52nos)
4. FIELD PROCEDURE:
For executing DMC piling method which is approved as
per IS 2911 under specification of bored cast-in-situ
piles. The positioning of points where the piles are
proposed to set up, are checked by the surveyor.
After the point for boring operation is set out by the
surveyor, the tripod is spaced such a manner that each
side legs at least 1.5m away from the point, keeping the
centre of bore hole exactly in the centre.
The bailer is then attached with the winch rope for
pitching and driving the liners, after driving the first
liner other liners are welded properly and driven
accordingly.
After driving the liners chiselling takes place.
Chisel attached with the DMC pipes and the pipes are
attached with the mud circulating pipes for boring.
Chisel boring and mud circulation process done
simultaneously for smooth & easy boring process.
Wash vat should clean time to time for better pumping.
After boring the cage lowering process take place.
25T tyre mounted crane lift the cage and then the cage
aligned properly and gradually lowered the cage, after
the first cage lowering the cage rested on the bars at
the top of the liner, after that 2nd cage lapped properly
with the 1st one and again lowered gradually, in this
process pile cages are lowered.
After the cage lowering tremmie pipes are fixed
properly for concreting.
3. CONCRETING SEQUENCE:
For example if the pile requires 18cum concrete then
after every TM (i.e. 6cum conc.) tremmie pipes should
be removed as specified (i.e. 1.5m tremmie pipe should
always embedded into the concrete)
4. TIME CYCLE:
Rig shifting vat shifting and Boring – 36hrs
Cage lowering – 2hrs
Tremmie pipe fixing – 1hrs
Concreting – 2hrs
Miscellaneous activities – 1hrs
Total = 42hrs
Survey Works:
Scope of work
1. Earthwork
2. Ground Improvement
3. Dewatering
4. Confirmatory Sub Soil Investigations
5. Pile Qualification
1. Multi Staging Dewatering system to lower the existing Ground Water Table.
2. Excavation work in the main plant area having maximum depth of 16.6m from the EGL
3. Ground Improvement with Soil-Cement mix up to various elevations having quantity of
8,00,000 Cum approximately
4. Confirmatory Sub Soil Investigations,
SPT (Standard Penetration Test)
PMT (Pressure Meter Test)
SPLT (Static Plate Load Test)
CHST (Cross Hole Seismic Test)
5. Pile Qualification
Vertical Test Pile – 3nos @1200mm dia.
Lateral Test Pile – 3nos @1200mm dia.
High Strain Test Pile – 2nos @1200mm dia.
Anchor Pile – 16nos @1200mm dia.
Properties
Materials Permissible Limit Test Frequency Remarks
(Physical/Chemical)
Physical: - 90micron max.
Physical:- Fineness, Standard
10% retained, Initial
Consistency, Initial & Final
setting time min. 30min & Physical:- Every change of week
Setting Time, Compressive
Cement final setting time max. Chemical:- Every 12
Strength, Soundness
10hrs, le Chatelier max. months/Change of source
Chemical(third party):- Chloride
10mm
Content, Unburned Lime
Chemical:- >0.1% Cl Value
Physical:- Fineness Physical:- >34% with
Physical:- once for each
Fly ash Chemical(third party):- 45micron Sieve
source/monthly
Insoluble Residue Chemical:- >2%
Physical: - Gradation,
Physical:- Gradation, Flakiness Physical:- Gradation(Daily), Impact
Flakiness index (<35%),
index, Elongation index, Impact Value(Monthly), Specific Gravity &
Elongation index (<35%),
Value, Crushing value, Specific Water Absorption(once for each
C.A. Impact Value (<45%),
Gravity & Water Absorption source)
Crushing value (<45%)
Chemical(third party):- Chloride Chemical(third party):- Chloride
Chemical(third party):-
Content Content(Once for each source)
Chloride Content
Physical:- Sieve analysis(as Physical:- Sieve analysis(Daily),
Physical:- Sieve analysis, Moisture Content(before concrete
per is 383), Moisture
Moisture Content, Silt Content, batching & mixing), Silt
Content, Silt Content(as
Specific Gravity & Water Content(Daily), Specific Gravity &
F.A. per cpwd specification),
Absorption Water Absorption(once for each
Specific Gravity & Water
Chemical(third party):- Chloride source/monthly)
Absorption
Content
Ground Improvement :
The project involves Ground Improvement using Soil-Cement
mix for main plant area having plan dimensions of 510m X
370m which includes Excavation for various areas having
maximum excavation depth up to16.6m depth from EGL, having
quantity of 19, 00,000 Cum approximately, Ground
Improvement with Soil-Cement mix up to various elevations
having quantity of 8,00,000 Cum approximately.
The site falls under zone III as
per the seismic zoning map of India and it had been learnt that
the area is prone to liquefaction under influence of seismic
activity. Therefore, to mitigate the liquefaction potential of
ground sub-strata, improvement of soil by compacted soil-
cement mix by mixing cement in soil at OMC corresponding to
modified proctor density test and application of suitable roller
compaction to achieve the maximum density at site(at least
95% of lab value).
1. Sequence of Activities :
Stacking of Excavated Soil:
During Excavation the excavated soil stacked properly for
backfill or GI purpose. Top 1m soil from existing ground
level of excavated area will be stacked separately and will
not be used in ground improvement works. Further 1-3m
soil from existing ground level of excavated area will be
stacked separately and checked for permissible organic
content for ground improvement works before use.
Sr. Calibration
Name of Equipment Purpose Ref Standard
No. Frequency
For Gradation or
2. IS Sieves 200mm Dia. IS 460
Sieve Analysis
For Sieving
3. Sieves Shaker 200mm Dia. IS 2386
Persons must have a valid gate pass to enter into the Project premises.
Vehicle & Construction machineries must have a valid Project pass.
Only authorized personnel are permitted to drive Vehicle.
Project Smoking Policy
The Entire Site is a No-Smoking Area, including office, corridors, toilets and car park.
Inside Site Cigarette/match box, lighter is strictly prohibited.
What are your Responsibilities??
Positive Attitude for EHS.
Follow Approved Method / Procedure for work.
Mitigate all Hazards & Risks.
Report all Incident, Accident & Near-miss
If you see something that is unsafe fix it or Make it Safe or Report It
Permit to Work (PTW)
PTW applies to hazardous activity:
Excavations and Trenching.
Height Work permit
Hot Work - Demolishing/Dismantling
Confined Space.
LOTO- Lock out Tag Out
Use of Man Lifting Basket.
Radiography.
Road Closure.
Lifting/Rigging/Erection
Personal Protective Equipment (PPE)
Safety Helmet.
Safety Footwear
Other PPEs as per job requirement
All PPES must be approved by Consortium & Owner
The only area where mandatory PPEs are not required is inside offices & outside the
identified construction areas
COMMERCIAL/QS BILLING
During Mobilization Stage
Study Contract Conditions, Specifications, Pre tender correspondences etc
Prepare a synopsis of the major commercial conditions of the Contract
Study the Tender estimate and prepare “Controlled Estimate” based on site condition
Assess Sub-contract /Labour contract scope of work and prepare the time table for award of the same
During Execution Stage
Monitor Bank Guarantee validity for both submitted to Client and received from Sub /Labour Contractor
on monthly basis
Maintain Client certification details as per “Payment details Format”.
Prepare “Cost To Complete” half yearly /quarterly and send to Div Office.
Revised the working program as and when necessary to complete the works within the stipulated time
frame
Prepare /evaluate Extension of time (EOT) Claim and get it approved from Client and evaluate the
additional cost incurred for the same.
Notification for Claim due to quantity variations and Additional works beyond Contract BOQ as and when
required.
Check and certify the Sub/Labour contractor’s bill on every month and keep record of the same.
On award of Contract prepare detail working program indicating all major activities and identification of
resources.
Monitor above program on weekly and monthly basis with respect to actual achievement.
Prepare “Client Bill” and Submit to Client as per the stipulated time schedule under the Contract
Prepare “Internal invoice” based on the actual progress achieved and send to DIV office on monthly basis
as per specified format.
Evaluate /estimate the actual cost incurred for achieving the above progress during the month
Compare the actual cost through “Cost Monitoring System” with respect to estimate and identify the
areas where excess cost incurred and notify
Check and certify the Sub/Labour contractor’s bill on every month and keep record of the same.
At closure of the Project
Preparation of Final Bill for submission to Client.
Close out all the Sub/ Labour contract. Release the final bill upon receiving the “No Claim Certificate” from
them.
Get release of the submitted Bank Guarantee from Client.
Get certified the final bill from Client and subsequent release of Final Payment
Prepare and monitor contract closure checklist on monthly basis till windup of the project and send to DIV
office
PROCUREMENT
Preparing SPI/PR
Give enquiry to the approved vendors
Receive Quotation
Preparing the Comparative Statement
Negotiation
PO
STORE
Purchase requisition based on types of materials.
Receiving of purchase order from purchase department.
Receive materials based on PO
Checking the received materials
Prepare GRN
IMS Policy contains Quality, Environment, Occupational Health and Safety Policy.
ITD Cementation strive to the followings:
Meet Customer’s requirements for quality of works and timely completion of projects;
Comply with the all applicable environmental, occupational health and safety related legal & other
requirements;
Prevent and control pollution, minimize consumption of resources and generation of waste
through adoption of better practices and technology;
Provide safe and healthy work environment through adaptation of better practices and
technology for prevention of incidents;
Ensure consultation and participation of workers to eliminate hazards and reduce OH&S risk to
improve the OH&S Management system;
Ensure that systems are in place, updated and continually improved through regular monitoring;
and
Create awareness amongst workers & relevant interested parties about significant environmental
aspects & impacts, OH&S risks, opportunities and control measures.
Signature :
Date : 15.08.2019