• The new plant will have a production capacity of 160 tonnes per day.
• The project is estimated to cost Rs.1000 million.
• As of February 2011, work on the project is yet to begin.
• The new unit is expected to be operational by fourth quarter of 2011-12.

Contact Address :Piramal Glass Limited, Piramal Towers, Peninsula Corporate Park, GK Marg, Lower Parel, Mumbai - 400 013
Telephone : + 91 22 3046 6969 / 3046 6901 Fax Number : +91 22 24908824
Infrastructure

AAI to expand Juhu Airport

Sub Sector :Airports


Project Cost (in Rs.million) 2000
Project Capacity :NA
Project State :Maharashtra
Current Status :Environment Clearance Awaited

Project Details :

• Airport Authority of India is planning to take up up gradation and modernization of Juhu Airport in Mumbai in Maharashtra.
• The initial plan includes extending the runway from 4,000 ft to 5,500 ft for accommodating private jets.
• The project is likely to be developed under public private partnership (PPP) mode.
• The project is expected to cost anywhere between Rs1000-2000 million.
• Global consultancy firm KPMG had submitted a study four months ago suggesting a public private partnership (PPP) model for
upgradation work.
• As of February 2011, the ministry is yet to approve the project and awarding bids for the project and actual development would
take a long time.
• The project will be completed in 2 to 3 years from zero date.

Contact Address : Airports Authority of India, Rajiv Gandhi Bhawan, Safdarjung Airport, New Delhi-110003 Ph : 91-11-24632950

Ennore Manali Road Improvement Project – Updates

Sub Sector :Highways


Project Cost (in Rs.million) 6000
Project Capacity :NA
Project State :Tamil Nadu
Current Status :Project Approved

Project Details :

• Chennai Port Trust has reported progress on the .Ennore Manali Road Improvement Project' which has been under implementa-
tion for more than 10 years.
• The project envisages improvement of a 30-km road network in north Chennai that connects all the container freight station han-
dling containers for Chennai port.
• A special purpose vehicle , with equity participation from National Highways Authority of India , Ennore Port and the Chennai
Port Trust has been floated to implement the project.
• The project has been revised to Rs.6000 million (from the original Rs.1500 million)
• As of February 2011, work on the project has started.
• The project is expected to be completed in 2 years.

Contact Address :Chennai Port Trust, 1 Rajaji Salai, Chennai - 600 001 Tel : 25362201 to 25362220, 25360151 to 25360160 Fax :
25361228 Email : info@chennaiport.gov.in

MARG Reports Progress on Mugaiyur Port Project

Sub Sector :Ports


Project Cost (in Rs.million) 9000