Page 14 IndScan Projects Newsletter– February I, 2011

Project Capacity :NA


Project State :Tamil Nadu
Current Status :Environment Clearance Awaited

Project Details :
• Marg has reported progress on its ship yard-cum-minor port at Mugaiyur in Tamil Nadu
• The ship yard-cum-minor port is situated at Mugaiyur on the East Coast Road near Chennai.
• The project is estimated to cost Rs.9000 million.
• As of February 2011, the project is awaiting environmental clearance.
• The project is expected to be completed in 2012.

Contact Address :MARG Ltd, 'MARG Axis', 4/318, Old Mahabalipuram Road, Kotivakkam, Chennai - 600 041 Tel : 91 - 44 -
24541111 Fax No : 91 - 44 - 24541123 Email : info@marggroup.com

Leather

Viking Leathers to set up Leather Processing Unit.

Sub Sector :Leather


Project Cost (in Rs.million) 35
Project Capacity :20000 Skin Leather
Project State :Haryana
Current Status :Environment Clearance Awaited

Project Details :

• Viking Leathers to set up Leather Processing Unit.


• Viking Leathers is planning to set up a Semi Finished (Wet Blue) to Finished Leather Processing Unit (20000 Skin Leather per
day) at HSIIDC Industrial Area in Bahadurgarh in Jhajjar in Haryana.
• The project is estimated to cost Rs.35 million
• As of February 2011, the company has been directed the project prepare a detailed Environmental Management Plan / Environ-
ment Impact Assessment Report and submit the same for Environment Clearance.

Contact Address :Viking Leathers Pvt. Limited, 937-A, Sector-7, Urban Estate, Ambala City- 134 003 Ph: 0171- 2515423 Fax:
0171-2446762 E-mail: dharminder@vikinggroup.in /jmeviron@hotmail.com

Metallurgical Industries

Metal Corp Plans Sheet Metal Manufacturing Plant

Sub Sector :Steel


Project Cost (in Rs.million) 850
Project Capacity :NA
Project State :Chhattisgarh
Current Status :Environment Clearance Awaited

Project Details :

• Metal Corp to set up sheet making manufacturing plant.


• Metal corp is planning to set up a Steel manufacturing plant at Mahroomkala in Khairagarh in Rajnandgaon district of Chhattis-
garh.
• The project is estimated to cost Rs.850 million
• As of February 2011, Ministry of Environment and Forests has directed the company to prepare a detailed Environmental Man-
agement Plan / Environment Impact Assessment Report and submit the same to the state pollution control authorities for con-
ducting public hearing.