GUIMARAS ENVIRONMENT AND NATURAL RESOURCES OFFICE

Standard For Number: SF-GOOD-59 Project Reference Number


Revised on: May 24, 2004 Name of the Project
Standard Form Title: Purchase Request Location of the Project
PURCHASE REQUEST
GENRO
Agency / Procuring Entity
DEPARTMENT: GENRO PR NO.: DATE:
SECTION: Admin. SAI No.: DATE:

Stock Unit ITEM DESCRIPTION Qty Unit Cost TOTAL


No.
1 Job
Supply of Materials and Labor for the PROVINCIAL TREE PARK
DEVELOPMENT AND MANAGEMENT(Site Clearing and
Fencing)
Site Clearing and Fencing with the following equipment and
technical personnel required
Equipment Qty. Technical No.
Personnel
Rebar Bender 1 Engineering Asst. 1
Bar Cutter 1
SCOPE OF WORKS
cu.m B. Reinforced Concrete (This item consist of Fabrication and 21.88 43, 896.34 960, 445.36
Installation of Concrete Fence
Post/Dimensions=0.125(x0.125x2.0m)
GRAND TOTAL 960, 445.36
Charge to: 20% DF Provincial Tree Park Development and Management 2018
Purpose: For PROVINCIAL TREE PARK DEVELOPMENT AND MANAGEMENT (Site Clearing and Fencing)
Delivery Schedule: 90 Calendar Days
Place of Deliver: Jobsite
Requested by: Noted by:

Signature
Printed Name LEONARD S. PASIDERIO MA. LOLITA S. ALELIS NOLINDA G. RONZALES
Designation Supervising EMS/OIC Engineer III/Acting Provincial Engineer Asst. PPDC/OIC PPDC
OK as to Appropriation Approved:

Signature
Printed Name JEAN L. PATANINDAGAT SAMUEL T. GUMARIN, MD, MPH
Designation Provincial Budget Officer Governor

(033) 581 2174 genroguimaras@yahoo.com


GUIMARAS ENVIRONMENT AND NATURAL RESOURCES OFFICE

Standard For Number: SF-GOOD-59 Project Reference Number


Revised on: May 24, 2004 Name of the Project
Standard Form Title: Purchase Request Location of the Project

PURCHASE REQUEST
GENRO
Agency / Procuring Entity

DEPARTMENT: GENRO PR NO.: DATE:


SECTION: Admin. SAI No.: DATE:
Stock Unit ITEM DESCRIPTION Qty Unit Cost TOTAL
No.
1 Job
Supply of Labor for the PROVINCIAL TREE PARK DEVELOPMENT,
Macopo Falls Rehabilitation and Provincial Nursery
Management (Construction of Provincial Nursery Shed)
Provincial Tree Park with the following equipment and technical
personnel required
Equipment Qty. Technical Personnel No.
Machine with 1 Engineering Asst. 1
Generator
Welding machine 1
including power supply
SCOPE OF WORKS
lot Clearing and Grubbing Layout 1.00 4, 110.00 5, 582.21
cu.m. Concrete Works 2.000 25, 950.00 70, 490.64
sq.m. G.I. Post and Support 140.00 263.57 50, 117.63
sq.m. Roofing Installation 140.00 70.00 13, 310.37
cu.m. Water Tank and Accessories 1.000 9,590.00 13,025.15
GRAND TOTAL 152, 526.00
Charged to: 2019 20% D.F. PROVINCIAL TREE PARK DEVELOPMENT, Macopo Falls Rehabilitation and Provincial Nursery Management
Purpose: for PROVINCIAL TREE PARK DEVELOPMENT, Macopo Falls Rehabilitation and Provincial Nursery (Construction of Provincial Nursery Shed)
Delivery Schedule: 120 Calendar Days
Place of Delivery: Jobsite

Requested by: Noted by:

LEONARD S. PASIDERIO MA. LOLITA S. ALELIS NOLINDA G. RONZALES


Supervising EMS/OIC Engineer III/Acting Provincial Engineer Asst. PPDC/OIC PPDC

JEAN L. PATALINDAGAT SAMUEL T. GUMARIN, MD, MPH


Provincial Budget Officer Governor

(033) 581 2174 genroguimaras@yahoo.com


GUIMARAS ENVIRONMENT AND NATURAL RESOURCES OFFICE

Standard For Number: SF-GOOD-59 Project Reference Number


Revised on: May 24, 2004 Name of the Project
Standard Form Title: Purchase Request Location of the Project

PURCHASE REQUEST
GENRO
Agency / Procuring Entity

DEPARTMENT: GENRO PR NO.: DATE:


SECTION: Admin. SAI No.: DATE:
Stock Unit ITEM DESCRIPTION Qty Unit Cost TOTAL
No.
1 Job
Supply of Labor for the PROVINCIAL TREE PARK DEVELOPMENT,
Macopo Falls Rehabilitation and Provincial Nursery
Management (Construction of Provincial Nursery Shed)
Provincial Tree Park with the following equipment and technical
personnel required
Equipment Qty. Technical Personnel No.
Machine with 1 Engineering Asst. 1
Generator
Welding machine 1
including power supply
SCOPE OF WORKS
lot Clearing and Grubbing Layout 1.00 4, 110.00 5, 582.21
cu.m. Concrete Works 2.000 25, 950.00 70, 490.64
sq.m. G.I. Post and Support 140.00 263.57 50, 117.63
sq.m. Roofing Installation 140.00 70.00 13, 310.37
cu.m. Water Tank and Accessories 1.000 9,590.00 13,025.15
GRAND TOTAL 152, 526.00
Charged to: 2019 20% D.F. PROVINCIAL TREE PARK DEVELOPMENT, Macopo Falls Rehabilitation and Provincial Nursery Management
Purpose: for PROVINCIAL TREE PARK DEVELOPMENT, Macopo Falls Rehabilitation and Provincial Nursery (Construction of Provincial Nursery Shed)
Delivery Schedule: 120 Calendar Days
Place of Delivery: Jobsite

Requested by: Noted by:

LEONARD S. PASIDERIO MA. LOLITA S. ALELIS NOLINDA G. RONZALES


Supervising EMS/OIC Engineer III/Acting Provincial Engineer Asst. PPDC/OIC PPDC

JEAN L. PATALINDAGAT SAMUEL T. GUMARIN, MD, MPH


Provincial Budget Officer Governor

(033) 581 2174 genroguimaras@yahoo.com


GUIMARAS ENVIRONMENT AND NATURAL RESOURCES OFFICE

Standard For Number: SF-GOOD-59 Project Reference Number


Revised on: May 24, 2004 Name of the Project
Standard Form Title: Purchase Request Location of the Project

PURCHASE REQUEST
GENRO
Agency / Procuring Entity

DEPARTMENT: GENRO PR NO.: DATE:


SECTION: Admin. SAI No.: DATE:
Stock Unit ITEM DESCRIPTION Qty Unit Cost TOTAL
No.
Supply of Materials for the PROVINCIAL TREE PARK DEVELOPMENT, Macopo Falls
Rehabilitation and Provincial Nursery Management (Construction of Provincial
Nursery Shed)
Provincial Tree Park
Equipment Qty. Technical No.
Personnel
Machine with 1 Engineering Asst.
1
Generator
Welding machine 1
including power supply
1 pcs. Plywood (10mm x 4’ x 8’) 5 1, 164.00 5, 820.00
2 Bd.ft. Lumber (2’’ x 2’’ x 8’) 267 40.00 10, 680.00
3 kgs. CW Nails (4’’ )long 5 78.00 390.00
4 kgs. CW Nails (2-1/2’’) long 5 81.00 405.00
5 kgs. CW Nails L (1-1/2’’) long 5 85.00 425.00
6 bags Cement (40 kg., Portland) 55 310.00 17, 050.00
7 cu.m. Sand (washed) 9.5 2, 145.00 20, 377.50
8 cu.m. Gravel (screened) 10.5 2, 795.00 29, 347.50
9 pcs. RSB (10 mmØ x 6m, def.) 34 192.00 6, 528.00
10 pcs. RSB (9mmØ x 6m, def.) 15 130.00 1, 950.00
11 pcs. CHB (4’’ x 8’’ x 16’’) 600 22.00 13, 200.00
12 kgs. Tire wire (# 16 G.I.) 8 96.00 768.00
13 pcs. G.I. Pipe (1-1/2’’Ø x 6m) schedule 20 55 1, 768.00 97, 240.00
14 pcs. G.I. Pipe (1-1/2’’Ø x 6m) schedule 21 42 995.00 41, 790.00
15 kgs. Welding rod (wipweld) 60 152.00 9, 120.00
16 kgs. Tie wire (# 16 G.I.) 10 96.00 960.00
17 roll Shade net (2.5m x 30m net) PP woven shade, 50% shade 8 11, 000.00 88, 000.00
18 kgs. MF Nylon (80 lbs. capacity) 15 605.00 9, 075.00
19 roll Hog wire (4’ x 36m) 5 1, 716.00 8, 580.00
20 pcs. Water Tank (800 liters capacity) 1 16, 500.00 16, 500.00
22 pcs. G.I. Pipe (1-1/2’’Ø x 20’) schedule 40 7 1, 768.00 12, 376.00
23 pcs. G.I. Pipe (1’’Ø x 20’) schedule 41 4 995.00 3, 980.00
24 pcs. Flat bar (1-1/4’’ x 2’’ x 6m) 9 988.00 8, 892.00
25 kgs. Welding rod (Wipweld) 20 152.00 3, 040.00
26 can Solvent cement (200mg) PVC Solvent 1 85.00 85.00
27 pcs. PVC Pipe (1’’Ø x 10’) 15 150.00 2, 250.00
28 pcs. PVC Elbow (1’’Ø x 90 )̊ 5 20.00 100.00
29 pcs. PVC Adaptor (Male Threaded) 4 25.00 100.00
30 pcs. PVC Reducer (1-1/2’’Ø x 1’’Ø) 1 30.00 30.00
31 pcs. Control valve (1’’Ø) PVC Ball valve 1 150.00 150.00
32 pcs. Suction valve (1-1/2’’Ø) foot valve with strainer 1 215.00 215.00
33 roll Teflon tape (1/2’’) 1 50.00 50.00
TOTAL…………………… 409, 474.00

(033) 581 2174 genroguimaras@yahoo.com


GUIMARAS
Charged to: 20% DF Provincial Tree Park ENVIRONMENT AND
Development (Macopo Falls NATURAL
Rehabilitation and RESOURCES OFFICE
Provincial Nursery Management)
Purpose: for the CONSTRUCTION OF NURSERY SHED
Delivery Schedule: 10 days upon receipt of approved purchase order
Place of Delivery: Jobsite

Requested by: Noted by:

LEONARD S. PASIDERIO MA. LOLITA S. ALELIS NOLINDA G. RONZALES


Supervising EMS/OIC Engineer III/Acting Provincial Engineer Asst. PPDC/OIC PPDC

JEAN L. PATALINDAGAT SAMUEL T. GUMARIN, MD, MPH


Provincial Budget Officer Governor