PROGRAM OF WORK

I. TITLE OF THE PROJECT


 Rehabilitation/Repair of the (20 meters) Seaside School Perimeter Fence

II. FUND
 Materials and Labor will be shouldered by School MOOE

III. PROJECT IMPLEMENTER


 Libertad National High School - Capoocan, Leyte

IV. TARGET DATE OF IMPLEMENTATION


 September 3, 2018 - December15, 2018

V. Rationale
A school safety fence will add a valuable asset to a school, protect the students, and
increase the pride students, staff, and the wider community feel for your school. Schools play
a vital role in our communities, and the education will be strengthened with the ability of the
school to maintain a safe and secure learning environment through a good perimeter fence.

VI. MATERIALS AND AMOUNT


Materials Quantity Unit Cost Total Amount
Hollow Blocks 400 pcs 17.00 6,800.00
Cement 50 bags 250.00 6,250.00
Sand 250 sacks 15.00 3,750.00
Steel Bars (10 mm) 40 pcs 160.00 6,400.00
Steel Bars (9 mm) 12 pcs 130.00 1,560.00
Tie Wire 6 kls 60.00 360.00
plywood 4 Sheets/pc 220.00 880.00
Coco lumber (2x2x8) 20 pcs 35.00 600.00
Paint 6 gal 600.00 3,600.00
Paint Brush 2 pcs 40.00 80.00
Paint Roller 2 pcs 85.00 170.00
Thinner 1 liter 200.00 200.00
TOTAL 30,650.00

VII. LABOR

Number of Days to Cost of Labor per Total Cost of


Payee work per panel Rate per Day Panel Labor
Mason 3 600 1800 18,000
Helper 3 350 1050 10,500

TOTAL 3 950 28,500 28,500


VIII. TOTAL AMOUNT OF THE PROJECT

Prepared by:
ABNER D. ETANG
Physical Facilities Coordinator/SST-I

Noted by:
LEONHEL P. LAGARDE
School Head

Recommending Approval:
RAMON CLENIO B. DE VEYRA
Division Physical Facilities Unit Head

Approved:
RONELO AL K. FIRMO, Ph. D., CESO V
Schools Division Superintendent