There are many methods to determine the volumes required for earthworks. In this course we will
be looking at;
As this method implies, firstly you need a site plan that has the land divided into equal grids with the
spot heights at the grid points. This may be done either by your own observations of derived from a
contour drawing as in the previous assessment.
Next you need to determine the physical actual grid size in this case we measured the grid to be 5
meters x 5 metres. The grid width and length do not need to be equal but they need to be the same
in each direction and evenly divide the subject land.
Next you need to determine the formation height. The formation height is the Reduced Level that
your earth works is required to be finished at. Let’s say we want to level the site to a Reduced Level
of 100.500.
1
Now we prepare a table listing all the spot heights in the following manner.
We look at every grid spot height and list the following details about it.
1. Formation Height
2. Grid Spot Height
3. Number of Grid Squares the spot height appears in
Grid x
Grid Formation Ht Spot Height No of Grids Cut/Fill Cut/Fill
A1 100.500 100.950 1 -0.450 -0.450
Then subtract the Spot Height from the Formation Height and place it in the cut & fill Column. Then
multiply the amount of “Cut/Fill” by the “Number of Grids” it appears in. Place the result in the last
column “Grid x Cut/Fill”.
2
Next grid point “A2”.
1
Spot Height appears
in two grids
Grid x
Grid Formation Ht Spot Height No of Grids Cut/Fill Cut/Fill
A1 100.500 100.950 1 -0.450 -0.450
A2 100.500 100.900 2 -0.400 -0.800
Then subtract the Spot Height from the Formation Height and place it in the cut & fill Column. Then
multiply the amount of “Cut/Fill” by the “Number of Grids” it appears in. Place the result in the last
column “Grid x Cut/Fill”.
3
Next grid point “A3”.
1
Spot Height appears
in two grids
Grid x
Grid Formation Ht Spot Height No of Grids Cut/Fill Cut/Fill
A1 100.500 100.950 1 -0.450 -0.450
A2 100.500 100.900 2 -0.400 -0.800
A3 100.500 100.750 2 -0.250 -0.500
4
Next grid point “A4”.
Grid x
Grid Formation Ht Spot Height No of Grids Cut/Fill Cut/Fill
A1 100.500 100.950 1 -0.450 -0.450
A2 100.500 100.900 2 -0.400 -0.800
A3 100.500 100.750 2 -0.250 -0.500
A4 100.500 100.550 2 -0.050 -0.100
5
To complete Grid A record grid point “A5”
Grid x
Grid Formation Ht Spot Height No of Grids Cut/Fill Cut/Fill
A1 100.500 100.950 1 -0.450 -0.450
A2 100.500 100.900 2 -0.400 -0.800
A3 100.500 100.750 2 -0.250 -0.500
A4 100.500 100.550 2 -0.050 -0.100
A5 100.500 100.394 1 0.106 0.106
6
Now we continue to grid point “B1”
2
1
Grid x
Grid Formation Ht Spot Height No of Grids Cut/Fill Cut/Fill
A1 100.500 100.950 1 -0.450 -0.450
A2 100.500 100.900 2 -0.400 -0.800
A3 100.500 100.750 2 -0.250 -0.500
A4 100.500 100.550 2 -0.050 -0.100
A5 100.500 100.394 1 0.106 0.106
B1 100.500 100.800 2 -0.300 -0.600
7
Next we continue to grid point “B2”
1
2
Grid x
Grid Formation Ht Spot Height No of Grids Cut/Fill Cut/Fill
A1 100.500 100.950 1 -0.450 -0.450
A2 100.500 100.900 2 -0.400 -0.800
A3 100.500 100.750 2 -0.250 -0.500
A4 100.500 100.550 2 -0.050 -0.100
A5 100.500 100.394 1 0.106 0.106
B1 100.500 100.800 2 -0.300 -0.600
B2 100.500 100.830 4 -0.330 -1.320
8
Next we continue to grid point “B3”
1
2
3 4
Grid x
Grid Formation Ht Spot Height No of Grids Cut/Fill Cut/Fill
A1 100.500 100.950 1 -0.450 -0.450
A2 100.500 100.900 2 -0.400 -0.800
A3 100.500 100.750 2 -0.250 -0.500
A4 100.500 100.550 2 -0.050 -0.100
A5 100.500 100.394 1 0.106 0.106
B1 100.500 100.800 2 -0.300 -0.600
B2 100.500 100.830 4 -0.330 -1.320
B3 100.500 100.730 4 -0.230 -0.920
9
Next we continue to grid point “B4”
1
2
3 4
Grid x
Grid Formation Ht Spot Height No of Grids Cut/Fill Cut/Fill
A1 100.500 100.950 1 -0.450 -0.450
A2 100.500 100.900 2 -0.400 -0.800
A3 100.500 100.750 2 -0.250 -0.500
A4 100.500 100.550 2 -0.050 -0.100
A5 100.500 100.394 1 0.106 0.106
B1 100.500 100.800 2 -0.300 -0.600
B2 100.500 100.830 4 -0.330 -1.320
B3 100.500 100.730 4 -0.230 -0.920
B4 100.500 100.470 4 0.030 0.120
10
Next we continue to grid point “B5”
1
2
Grid x
Grid Formation Ht Spot Height No of Grids Cut/Fill Cut/Fill
A1 100.500 100.950 1 -0.450 -0.450
A2 100.500 100.900 2 -0.400 -0.800
A3 100.500 100.750 2 -0.250 -0.500
A4 100.500 100.550 2 -0.050 -0.100
A5 100.500 100.394 1 0.106 0.106
B1 100.500 100.800 2 -0.300 -0.600
B2 100.500 100.830 4 -0.330 -1.320
B3 100.500 100.730 4 -0.230 -0.920
B4 100.500 100.470 4 0.030 0.120
B5 100.500 100.330 2 0.170 0.340
11
Now we continue to grid point “C1”
2
1
Grid x
Grid Formation Ht Spot Height No of Grids Cut/Fill Cut/Fill
A1 100.500 100.950 1 -0.450 -0.450
A2 100.500 100.900 2 -0.400 -0.800
A3 100.500 100.750 2 -0.250 -0.500
A4 100.500 100.550 2 -0.050 -0.100
A5 100.500 100.394 1 0.106 0.106
B1 100.500 100.800 2 -0.300 -0.600
B2 100.500 100.830 4 -0.330 -1.320
B3 100.500 100.730 4 -0.230 -0.920
B4 100.500 100.470 4 0.030 0.120
B5 100.500 100.330 2 0.170 0.340
C1 100.500 100.730 2 -0.230 -0.460
12
Next we continue to grid point “C2”
1
2
Grid x
Grid Formation Ht Spot Height No of Grids Cut/Fill Cut/Fill
A1 100.500 100.950 1 -0.450 -0.450
A2 100.500 100.900 2 -0.400 -0.800
A3 100.500 100.750 2 -0.250 -0.500
A4 100.500 100.550 2 -0.050 -0.100
A5 100.500 100.394 1 0.106 0.106
B1 100.500 100.800 2 -0.300 -0.600
B2 100.500 100.830 4 -0.330 -1.320
B3 100.500 100.730 4 -0.230 -0.920
B4 100.500 100.470 4 0.030 0.120
B5 100.500 100.330 2 0.170 0.340
C1 100.500 100.730 2 -0.230 -0.460
C2 100.500 100.720 4 -0.220 -0.880
13
Next we continue to grid point “C3”
1
2
3 4
Grid x
Grid Formation Ht Spot Height No of Grids Cut/Fill Cut/Fill
A1 100.500 100.950 1 -0.450 -0.450
A2 100.500 100.900 2 -0.400 -0.800
A3 100.500 100.750 2 -0.250 -0.500
A4 100.500 100.550 2 -0.050 -0.100
A5 100.500 100.394 1 0.106 0.106
B1 100.500 100.800 2 -0.300 -0.600
B2 100.500 100.830 4 -0.330 -1.320
B3 100.500 100.730 4 -0.230 -0.920
B4 100.500 100.470 4 0.030 0.120
B5 100.500 100.330 2 0.170 0.340
C1 100.500 100.730 2 -0.230 -0.460
C2 100.500 100.720 4 -0.220 -0.880
C3 100.500 100.690 4 -0.190 -0.760
14
Next we continue to grid point “C4”
1
2
3 4
Grid x
Grid Formation Ht Spot Height No of Grids Cut/Fill Cut/Fill
A1 100.500 100.950 1 -0.450 -0.450
A2 100.500 100.900 2 -0.400 -0.800
A3 100.500 100.750 2 -0.250 -0.500
A4 100.500 100.550 2 -0.050 -0.100
A5 100.500 100.394 1 0.106 0.106
B1 100.500 100.800 2 -0.300 -0.600
B2 100.500 100.830 4 -0.330 -1.320
B3 100.500 100.730 4 -0.230 -0.920
B4 100.500 100.470 4 0.030 0.120
B5 100.500 100.330 2 0.170 0.340
C1 100.500 100.730 2 -0.230 -0.460
C2 100.500 100.720 4 -0.220 -0.880
C3 100.500 100.690 4 -0.190 -0.760
C4 100.500 100.330 4 0.170 0.680
1
2
Grid x
Grid Formation Ht Spot Height No of Grids Cut/Fill Cut/Fill
A1 100.500 100.950 1 -0.450 -0.450
A2 100.500 100.900 2 -0.400 -0.800
A3 100.500 100.750 2 -0.250 -0.500
A4 100.500 100.550 2 -0.050 -0.100
A5 100.500 100.394 1 0.106 0.106
B1 100.500 100.800 2 -0.300 -0.600
B2 100.500 100.830 4 -0.330 -1.320
B3 100.500 100.730 4 -0.230 -0.920
B4 100.500 100.470 4 0.030 0.120
B5 100.500 100.330 2 0.170 0.340
C1 100.500 100.730 2 -0.230 -0.460
C2 100.500 100.720 4 -0.220 -0.880
C3 100.500 100.690 4 -0.190 -0.760
C4 100.500 100.330 4 0.170 0.680
C5 100.500 100.300 2 0.200 0.400
16
1. Grid Spot Height 100.735
2. Formation Height 100.500
3. Number of Grid Squares the spot height appears in 2
2
1
Grid x
Grid Formation Ht Spot Height No of Grids Cut/Fill Cut/Fill
A1 100.500 100.950 1 -0.450 -0.450
A2 100.500 100.900 2 -0.400 -0.800
A3 100.500 100.750 2 -0.250 -0.500
A4 100.500 100.550 2 -0.050 -0.100
A5 100.500 100.394 1 0.106 0.106
B1 100.500 100.800 2 -0.300 -0.600
B2 100.500 100.830 4 -0.330 -1.320
B3 100.500 100.730 4 -0.230 -0.920
B4 100.500 100.470 4 0.030 0.120
B5 100.500 100.330 2 0.170 0.340
C1 100.500 100.730 2 -0.230 -0.460
C2 100.500 100.720 4 -0.220 -0.880
C3 100.500 100.690 4 -0.190 -0.760
C4 100.500 100.330 4 0.170 0.680
C5 100.500 100.300 2 0.200 0.400
D1 100.500 100.735 2 -0.235 -0.470
17
Next we continue to grid point “D2”
1
2
3
4
18
Next we continue to grid point “D3”
1
2
3 4
19
Next we continue to grid point “D4”
1
2
3 4
1
2
21
1. Grid Spot Height 100.724
2. Formation Height 100.500
3. Number of Grid Squares the spot height appears in 2
2
1
22
1. Grid Spot Height 100.650
2. Formation Height 100.500
3. Number of Grid Squares the spot height appears in 4
1
2
3
4
23
Next we continue to grid point “E3”
1
2
3 4
24
Next we continue to grid point “E4”
1
2
3 4
25
Next we continue to grid point “E5”
1
2
26
Now we continue to grid point “F1”
2
1
27
Next we continue to grid point “F2”
1
2
3
4
28
Next we continue to grid point “F3”
1
2
3 4
29
Next we continue to grid point “F4”
1
2
3 4
30
Next we continue to grid point “F5”
1
2
31
Now we continue to grid point “G1”
32
Next we continue to grid point “G2”
33
Next we continue to grid point “G3”
34
Next we continue to grid point “G4”
35
Next we continue to grid point “G5”
36
Grid Formation Ht Spot Height No of Grids Cut/Fill Grid x Cut/Fill
A1 100.500 100.950 1 -0.450 -0.450
The completed table is below A2 100.500 100.900 2 -0.400 -0.800
A3 100.500 100.750 2 -0.250 -0.500
A4 100.500 100.550 2 -0.050 -0.100
A5 100.500 100.394 1 0.106 0.106
B1 100.500 100.800 2 -0.300 -0.600
B2 100.500 100.830 4 -0.330 -1.320
B3 100.500 100.730 4 -0.230 -0.920
B4 100.500 100.470 4 0.030 0.120
B5 100.500 100.330 2 0.170 0.340
C1 100.500 100.730 2 -0.230 -0.460
C2 100.500 100.720 4 -0.220 -0.880
C3 100.500 100.690 4 -0.190 -0.760
C4 100.500 100.330 4 0.170 0.680
C5 100.500 100.300 2 0.200 0.400
D1 100.500 100.735 2 -0.235 -0.470
D2 100.500 100.700 4 -0.200 -0.800
D3 100.500 100.550 4 -0.050 -0.200
D4 100.500 100.320 4 0.180 0.720
D5 100.500 100.200 2 0.300 0.600
E1 100.500 100.724 2 -0.224 -0.448
E2 100.500 100.650 4 -0.150 -0.600
E3 100.500 100.530 4 -0.030 -0.120
E4 100.500 100.350 4 0.150 0.600
E5 100.500 100.190 2 0.310 0.620
F1 100.500 100.680 2 -0.180 -0.360
F2 100.500 100.650 4 -0.150 -0.600
F3 100.500 100.450 4 0.050 0.200
F4 100.500 100.600 4 -0.100 -0.400
F5 100.500 100.140 2 0.360 0.720
G1 100.500 100.830 1 -0.330 -0.330
G2 100.500 100.600 2 -0.100 -0.200
G3 100.500 100.400 2 0.100 0.200
G4 100.500 100.290 2 0.210 0.420
G5 100.500 100.040 1 0.460 0.460
96 -5.132
Total ÷ No of Grid Pts Aveerage Cut/Fill
-5.132 96 -0.053
Aveerage Cut/Fill x Site Area = Total Cut/Fill
-0.053 600.000 -32.075
Now tally all the times a spot appears in the grid. In this case it totals 96.
Next total the column that has the result of the multiplication of the number of grids and cut/fill.
Notice it is important to take account of negatives. In this case the result the total is -5.132m.
Next divide the answer by the number of times the spot height appears in the grids. In this case it is
96 times.
-5.132 ÷ 96 =-0.053
To now determine the amount of the total of the excavation you multiply the average by the area of
the site. In our case the area of the site is 30m x 20m
-0.053 x 30 x 20 = -32.075 (Note you may get a slightly different answer due to rounding errors).
As the answer is negative you are CUTTING 32.075 m3 to get this site to a formation level of RL
100.500.
This method assumes that you are using material from the site to fill and compact the lower areas
Note this is the compacted volume. To calculate the amount of material you have to truck away you
need to allow for the bulking factor.
If our site was clay to determine how much material you are removing would be calculated as
follows;
If the answer was positive you would need to import fill and to determine the amount using the
shrinkage factor.
Slab Calculation
Some times you do not need to determine the whole area of the site, you may just want to bench
out for a slab.
38
Firstly we record all full grids
Totals 12 0.140
= 0.900 m3
Next we break the pad into smaller grids and Interpolates as required
39
x 100.780 x 100.705 x 100.625 x 100.590
In this case grid
size is 5m x 2.5m.
40
Next we break the pad into smaller grids and Interpolate as required
41
Next do the individual grids
100.525 x
Totals 4 0.130
42
Next do the individual grids
100.735 x
Totals 4 -0.460
43
Next do the individual grids
100.780 x
In this case grid 100.755 x
Totals 4 -1.005
44
Next do the individual grids
x 100.510
Totals 4 -0.220
45
Next do the individual grids
x 100.400
Totals 4 0.210
46
Next do the individual grids
x 100.400
x 100.510
100.250 x
Totals 4 0.760
47
Tally up all the results of the grid calculations.
Running Tally
1 0.900
2 -5.550
3 2.388
4 0.033
5 -0.575
6 -0.628
7 -0.096
8 0.199
9 0.143
Total -3.186
This again is an in-situ measurement. Bulking factors need to be allowed for to adjust the actual
quantity for estimating purposes.