Professional Documents
Culture Documents
INDONESIA
Multiple engine solution with higher Can follow load without reducing
Very large operating window required
efficiency than open cycle GT plants overall plant efficiency
Currently baseload plants must be used Smart Power Generation plants used
More efficient use of baseload plants
also for peaking for peaking & grid stability
Fast growing demand soon renders Attractive delivery time, financial and Customer can deliver power faster and
current capacity insufficient development services start earning on electricity sales earlier
Peaking operation also has a negative impact track basis – around 18 months from contract
The Arun power plant will serve signing to full commissioning.
on lifecycle costs of gas turbines. An engine-
to strengthen the Aceh Special
based plant has another benefit in that it can Notably, it is the first project where PLN re-
District electricity system,
be started up and shutdown without impacting quested the contractor and the equipment man-
ensuring reliable electricity
maintenance schedules. supply to consumers during ufacturer to arrange financing through export
The plant’s 19 engines will be split across peak loads. credit. Wärtsilä worked closely with Finnvera
four blocks of engines (5 + 5 + 5 + 4) housed and Standard Chartered Bank to secure the loan
in two adjacent powerhouses. Radiators for each agreement at attractive interest rates. Wärtsilä’s
block are located on the roof and the entire plant support in arranging financing has also helped
will be controlled from a single control room. PLN’s large baseload plants to run at full power, to expedite the project.
As the plant will be used purely for peaking where they are most efficient, all year round. For When it fires up in 2015, Arun will not only
as a grid stabilising plant, it is expected to oper- PLN the savings will be dramatic. help satisfy Indonesia’s enormous appetite for
ate for between 2000 and 3000 hours a year. In its effort to satisfy burgeoning power de- power, it will also serve as a reference for a more
Using the Arun plant purely for this purpose mand, Indonesia is pulling out all the stops in flexible way of tackling peak demand and pro-
has overall system benefits. It will allow opti- getting the new plant up and running as soon as viding grid stability throughout the region.
misation of the total power system by enabling possible. Arun is therefore being built on a fast-
MAIN DATA
Customer.... PT Wijaya Karya Persero Tbk (PT Wika) (Utility)
Type............................................Wärtsilä 34 gas power plant
Operating mode................Peak load/stand-by & emergency
Gensets............................................. 19 x Wärtsilä 20V34SG
Total output............................................................... 184 MW
Fuel .............................................LNG (Liquefied natural gas)
Scope...................................EEQ (Engineering & Equipment)
Delivered.........................................................................2015
WARTSILA.COM