You are on page 1of 11

PEguru

Home Article Categories  Tools  Ebooks Blog


Substation Design | Power System Analysis

Home » Power System Fundamentals

Easily correct phase shift on a delta-to-wye transformer for


paralleling
By Aleen Mohammed / August 8, 2020 / 6 minutes of reading

Aleen Mohammed
Professional Engineer (Electrical)

Skillset: Substation Design | Power

System Studies | Arc Flash Study

Figure 1: Paralleling two transformers with different phase-shifts

report this ad
Are you adding a new transformer, or perhaps replacing as existing one? Is the transformer’s phase

shift different compared to another transformer in the same yard?

You need to get two things right when it’s time to parallel two transformers at a transmission

substation.

1. Identify source vector rotation. Keep it intact – going into and out of the substation.
2. Identify the transformer phase-shift. If different from others, correct it. All transformers

must yield the same phase shift.

You get either one wrong and attempt closing the tie-breaker, sit-back and watch the mayhem. Not

sure why? I will share the details in the following sections, starting with the basics. But first, check

out the entire phasing process in the infographic below.


Figure 2: Complete process for getting the phasing right at the substation. Purchase a high-resolution

version for your reference, see below. Thank you for supporting this blog.

Download this infographic for free

Table Of Contents
Source vector rotation A-B-C or C-B-A

Phase shift due to delta-to-wye transformers

How to parallel transformers at a substation

Identify source vector rotation

Flipping vector rotation changed the transformer phase shift, now what?

Phase angle, frequency, and grid synchronization

Source vector rotation A-B-C or C-B-A

Figure 3: Vector rotation based on generator rotor spin. Images, courtesy of relaytraining.com

A generator’s rotor can spin one of two ways, shown above; this means the sequence of which

phase reaches the peak magnitude differs. For instance, in Figure 3 above:

At 0.5cycle
Phase B approaches peak positive magnitude, in A-B-C rotation system

Phase B departs peak negative magnitude, in C-B-A rotation system.

When it comes time to connect these two generators to the power grid, they will never synchronize

(as presented). You may assume they operate independently, feeding an islanded power grid.

However, have you seen the power grid in North America? There are hundreds, if not thousands of

generators interconnected, with A-B-C and C-B-A rotations. How did they manage to synchronize?

Figure 4: Generator and EHV lines in North-East USA. Source: eia.gov.

Phase shift due to delta-to-wye transformers

Figure 5: Transformer winding with taps brought out

Another conundrum pertains to the phase shift within the transformer. Depending on how the high

side and low side windings get wound on the core, the transformer shifts the phase angle

accordingly, explained in detail in this paper by Basler.


Figure 6: Source vector – getting

shifted in phase angle as you go

through a transformer.

Hypothetically, if you have a grid with transformers that shift phase angles equally (and has equal

loading), you would end up with something as shown in Figure 6 above. The vectors on both sides

of the tie breaker are in sync, yielding an ideal condition for the breaker to close. What if the two

systems contained transformers with different phase shifts? Is synchronization possible then?

How to parallel transformers at a substation

Let’s combine the two concepts discussed above. Both play significant role in paralleling.

Identify source vector rotation

If you’re presented with a source vector rotation, for instance: A-B-C, you can always flip it –

outside the generating station. A typical location in the transmission system is at a transformer.

In most substations, you are trying to preserve the vector rotation – in and out of the

substation. However, you will come across situations where you are tying two systems

with different rotations or feeding an end-user like an industrial customer whose motor

loads are wired for flipped rotation. In this case, use a transformer to change A-B-C to C-

B-A or vice-versa. Make sure to understand the application of your transformer.

One of the most convoluted ideas is how you land the phase conductor on the transformer

bushings, to change vector rotation. Follow the directions presented in the infographic to figure out

which phases go where.


Keep in mind, merely twisting the phase conductors on the low-side does not change the voltage

vector rotation, see the image below. The A-B-C rotation stays intact through the transformer.

Figure 7: Want C-B-A rotation on the low side? Don’t do this.

Conversely, if you do flip the phases on the high voltage bushings, the rotation gets changed.
Figure 8: Want to keep the A-B-C rotation intact through the transformer? Don’t

do this.

If you connect any one of the combinations shown in the negative rotation column below – to the

high-side bushings (for the above set-up), the rotation changes to a negative sequence on the low-

side.

A-B-C positive rotation combinations C-B-A negative rotation combinations

A–B–C C–B–A

C–A–B A–C–B

B–C–A B–A–C

Table 1: Vector rotation combinations

Flipping vector rotation changed the transformer phase shift, now what?

Unfortunately, flipping the vector rotation affects the transformer’s nameplate phase shift too –

Dyn1 30degree transformer becomes Dyn11 330degree, and Dyn11 becomes Dyn1. Now, why this

phase shift occurs, is a topic for a future article.

With this new shift, make sure it matches the phase shift of other existing transformers in the

substation. Otherwise, paralleling is not possible.

In a high voltage station, crossing the two outside phases can be challenging. There might not be

enough space to squeeze in a phase transposition structure. Thus, if you roll the phases, as shown

in the infographic, you still keep the vector rotation you want and get a combination where you only

flip the outside 2 phases (H1-H2 or H2-H3) instead of H1-H3, making it easy to transpose.

Phase angle, frequency, and grid synchronization


On a related note, the interconnection of two power systems requires synchronization of the phase

angles. Ofcourse, the voltage magnitude shall be equal too.

It is quite possible, one system may have transformers with different phase shifts (30deg, 90deg,

or 150deg, but rotating in the same direction) than others. This may put the vectors at different

phase angles, at the point of coupling.

Using the synchroscope shown below, let’s see how we can synchronize the systems.

When the incoming source has a higher frequency (spinning faster \rArr squished Sine wave)

relative to the reference system, the synchroscope spins clockwise; indicating a positive \Delta{f}.

Vice versa holds true when the frequency is slow.

Figure 9: A synchroscope – when the bulbs turn OFF, the

systems are in sync. The bulbs are the brightest when

180degrees out of phase. Are your reflexes good enough to

hit the mark?

In this scenario, when the dial hits 12 o’clock position (where \Delta{f}=0), the phase angles of the

two systems are roughly synchronized; allowing the tie breaker to close.

If the two systems spin at exactly the same frequency and remain out of phase, the dial would

indicate the out-of-phase angle and stays fixed. The possibility of synchronization, in this case, is

non-existent.

When synchronization does occur, the system with higher inertia (or higher stiffness) will try to pull

the other system into its step. Check the video below to understand this flexible-electrical-

coupling-between-systems concept.
On a slightly unrelated note, this video also explains the underlying concept of how power can

either be imported or exported from one region to another. Modulate the frequency of an entire

region (using the generator governor or by adding load) and watch the power wheel through the

grid.

In this article, we explored the concept of phasing and how it affects transformer paralleling.

However, there are other factors such as kVA rating, \%{Z}, No-Load-Tap setting, etc. affecting

paralleling. Do check this paper by Schneider Electric that discusses them in detail.

What are your thoughts on this? Let it out below.

TRANSFORMER PHASING QUIZ

Think you have this covered? This should be a piece of cake.

Start
Please support this blog by sharing the article

Recommended posts for you:

Resistor
Resistor vs.
vs. Reactor
Reactor -- Power
Power Transformer:
Transformer: Current
Current Transformer:
Transformer:

Which
Which Transformer
Transformer Learn
Learn the
the Purpose,
Purpose, Learn
Learn the
the Purpose,
Purpose,

Neutral…
Neutral… Cost,
Cost, and
and Lead…
Lead… Cost,
Cost, and…
and…

Practical
Practical Voltage
Voltage Transformer:
Transformer:

Implementation
Implementation of
of Learn
Learn the
the Purpose,
Purpose,

Transformer
Transformer Winding…
Winding… Cost,
Cost, and…
and…

  

Leave a Comment
Your email address will not be published.

Type here..

Name* Email* Website

Post Comment »
report this ad

Recent Posts Categories Archives

Practical Implementation of Power System Fundamentals


Select Month
Transformer Winding Connections – 3 Substation Equipment

Critical Steps to Consider Substation Physical Design

Cheatsheet for calculating lightning Substation Protection and Control

surge arrester ratings

Easily correct phase shift on a delta-

to-wye transformer for paralleling

Major Substation Equipment – Learn

the Purpose, Cost, and Lead Time to

Procure

Wave Trap: Learn the Purpose, Cost,

and Lead Time to Procure

Designed with ‫ ڡ‬by Aleen About Contact Permissions and Disclaimers Privacy Policy

You might also like