Professional Documents
Culture Documents
www.sciencedirect.com
journal homepage: www.elsevier.com/locate/sandf
Abstract
Synthetic polymer fluids have been used for the construction of bored piles (drilled shafts) for more than two decades, but their effect on the
performance of the completed piles is still a matter of debate. To investigate the effects of polymer and bentonite fluids on the behaviour of bored
piles, a field trial comprising three full-scale instrumented test piles has been conducted at a site in East London. It was found that the two piles
constructed using polymer fluids showed much stiffer load-settlement response than the one constructed using bentonite slurry. Surprisingly, an
extended pile bore open time of up to 26 h was found to have no adverse effect on the piles if supported by polymer fluids. Based on the results of
back-analyses using the load-transfer approach, polymer fluids were found to have little effect on the Woolwich and Reading Formations but a
noticeable effect on the Upnor Formation – the mixed results are believed be due to the different soil mineralogies. It has also been shown that the
common problem of ‘soft toes’ can be eliminated by adopting good construction practice including proper base checking and fluid cleaning or
exchange procedures on site.
& 2015 The Japanese Geotechnical Society. Production and hosting by Elsevier B.V. All rights reserved.
http://dx.doi.org/10.1016/j.sandf.2015.10.013
0038-0806/& 2015 The Japanese Geotechnical Society. Production and hosting by Elsevier B.V. All rights reserved.
1488 C. Lam et al. / Soils and Foundations 55 (2015) 1487–1500
on the performance of piles. For example, it is unclear whether effect of polymer and bentonite support fluids on the load-
a polymer-supported bore can be left open for longer without settlement behaviour of piles; (ii) to investigate whether
compromising the performance of the completed pile. In a extended pile bore open time would lead to worse behaviour;
recent bored piling project in central London utilising polymer (iii) to assess the effectiveness of improved construction
fluids, the design-and-build contractor had to reduce the design practice comprising rigorous fluid property control and pile
alpha (α) value for the London Clay and the Lambeth Group base cleaning to preventing the formation of ‘soft toes’.
from 0.5 to 0.35 for any unlined bores which were left open Various aspects of the trial are discussed in the following
overnight, effectively increasing the lengths of the piles. The sections: ground conditions, construction details, and inter-
reason for the alpha value reduction was to compensate for any pretation of load test results.
additional clay softening due to increased exposure to the
support fluids (LDSA, 2009). Although this practice has been 2. Ground conditions
developed from experience with piles drilled either dry or with
bentonite slurry support, in the absence of published case 2.1. Soil profile
histories on polymers, the same rule was adopted for the
design for the present project. In a professional news article, The test site is located at about 0.5 km south-east of the
Wheeler (2003) reported on a trial with a polymer fluid at Stratford International station ‘box’ in East London. Table 1
London's Canary Wharf. It was reported that the polymer fluid summarises the soil layers encountered and their descriptions.
did not lead to significant degradation of shaft friction with It can be seen that the ground consists of made ground, River
time but one of the production pile bores collapsed during Terrace Gravel, Lambeth Group, Thanet Sand and then Chalk.
excavation. The collapse was attributed to polymer fluids The made ground at the top was excavated material arising
behaving differently from bentonite. In addition to concerns from the construction of the Channel Tunnel Rail Link and the
for pile bore stability, the use of polymer fluids has been station box (Dyson and Blight, 2007). The Lambeth Group can
associated with an increased risk of ‘soft toe’ at the pile base be sub-divided into Woolwich Formation (Laminated Beds
(Fleming et al., 2009). This is because polymer fluids have a and Lower Shelly Clay), Reading Formation (Lower Mottled
lower particle-holding capacity than bentonite. In polymer Clay) and Upnor Formation. For the purpose of the back-
fluids, soil particles tend to settle faster than in bentonite so analyses, the made ground and the thin River Terrace Gravel
they tend accumulate at the base of the excavation during the layer were treated as one unit, and the Woolwich and Reading
insertion of steel reinforcement cages and build-up of the Formations were also treated as a single unit. Fig. 1a shows the
tremie pipes, and on the top of the rising concrete column idealised soil profile together with some details of the
during casting. The potential problems of ‘soft toe’ and test piles.
excavation instability are inhibiting the take-up of polymer
technology, though it should be emphasised that both the 2.2. Groundwater conditions
problems can be completely eliminated if the fluids are used
correctly, as will be demonstrated in this case history. As a result of the geological conditions in the London Basin,
To investigate the effect of polymer fluids on the perfor- two aquifers exist at the test site: a shallow aquifer in the made
mance of bored piles, a field trial consisting of three ground and River Terrace Gravel and a deep aquifer in the
comparative test piles has been carried out at a site in East Thanet Sand and the underlying Chalk. These two aquifers are
London. The aim of the trial was threefold: (i) to assess the separated by the Lambeth Group which is much less
C. Lam et al. / Soils and Foundations 55 (2015) 1487–1500 1489
Table 1
Soil profile at the East London test site.
Made ground/land raise 0 to 6.0 MADE GROUND: Dark brown gravelly fine to coarse sand with
(5.5 to 0.5) occasional shell fragments and pockets of stiff clay.
River Terrace Gravel 6.0 to 6.5 Brown fine to coarse SAND and rounded to angular fine to coarse
( 0.5 to 1.0) GRAVEL of flint.
Lambeth Group – Woolwich Formation – 6.5 to 9.5 Firm greyish brown slightly sandy thinly laminated CLAY with
Laminated Beds ( 1.0 to 4.0) closely spaced thin to thick laminations of silt and occasional shell
fragments.
Lambeth Group – Woolwich Formation – Lower 9.5 to 11.0 Firm to stiff dark greyish green sandy CLAY with many shells and
Shelly Clay ( 4.0 to 5.5) shell fragments.
Lambeth Group – Reading Formation – Lower 11.0 to 13.5 Stiff to very stiff green very sandy slightly gravelly CLAY with
Mottled Clay ( 5.5 to 8.0) occasional shell fragments. From 12.5 to 13.5 m, light green
limestone hardpan (calcrete duricrust).
Lambeth Group – Upnor Formation 13.5 to 19.5 Very stiff dark green very sandy gravelly CLAY with occasional
( 8.0 to 14.0) shell fragments at top.
Thanet Sand 19.5 to 33 Very dense grey slightly silty fine to medium SAND. From
( 14.0 to 27.5) 31.25 m, becoming silty.
Chalk 33 to end of boreholes at 35.0 Structureless CHALK (Grade Dm, Mundford Grade VI).
( 27.5 to 29.5)
a
b.g.l. stands for below ground level. Ground level stands at 5.5 mOD at the test pile locations.
3. Construction details
2.4. Drained shear strength of Thanet Sand The polymer used was the ‘SlurryPro CDP’ system supplied
by KB International LLC. This system consists of a granular
For routine pile design, the peak angle of shearing resistance base polymer (CDP) and a range of additives which can be used
0
(ϕp ) of Thanet Sand is taken as 361 because this value is to modify the polymer behaviour to suit particular ground
commonly found in direct shear box tests on recompacted conditions. Goodhue and Holmes (1995) state that the CDP
samples (Troughton, 1992). Ventouras and Coop (2009) polymer is a sodium-form acrylate/acrylamide copolymer (a
0
reported that the values of ϕp measured on intact samples partially hydrolysed polyacrylamide, PHPA) having an anionic
can actually range from 301 in drained triaxial extensional tests charge density of nominally 40% and a molecular weight of
to 391 in undrained compression tests, and that the critical state approximately 20 million g/mol. Previous experience of using
angle is 32.31 regardless of the silt content of the material. For this polymer in Glasgow is reported in Lennon et al. (2006).
0
the back-analyses ϕp is taken as 361 but as will be shown the Since the ground conditions at the test site consisted of firm to
C. Lam et al. / Soils and Foundations 55 (2015) 1487–1500 1491
Table 2
Properties of polymer and bentonite support fluids.
Pile no. Fluid details and exposure time Fluid test resultsa
Product name Concentration: kg/m3 Total fluid-soil pH Sand content: Density: Marsh funnel Viscosity
exposure time: h % g/cm3 viscosity: s curves
P1 SlurryPro CDP 1.0 (CDP); 0.08 (LA-1-D)b 7.5 11.2, 11.2, 11.2 0, 0.2, 0.2 (1.3)c 1.00, 1.02, 1.03 70, 56, 56 Fig. 4
P2 26 11.0, 11.0, 11.0 0, 0.1, 0.1 (1.4)c 1.00, 1.02, 1.02 69, 50, 50
B1 Berkbent 163 40 7.5 10.5, 10.3, 10.3 0, 6.8, 10 1.02, 1.10, 1.15 34, 40, 41
a
Fluid test results are given in the order: fresh fluid, used fluid from middle of pile bore, used fluid from bottom of pile bore.
b
Before the addition of CDP (base polymer) and LA-1-D (fluid loss control agent); ProTek 100 (potassium hydroxide) was used to adjust the pH of the potable
water to 11 prior to the addition of CDP.
c
Sand content results given in brackets were measured on samples taken from the bottom of polymer-supported bores immediately after excavation but before the
treatment with 10 L of 1% diluted MPA solution.
stiff clay and dense sand (the made ground was supported by a
temporary casing), only three additives were needed for the trial.
These were a pH raising additive (ProTek 100), a fluid loss
control agent (LA-1-D) and a flocculating agent (MPA) to
accelerate the settling of suspended soil particles at the end of
excavation. The fluid preparation procedure is generally the
same as that described in Lam et al. (2010). Table 2 summarises
the dosages of the various chemicals used for the trial.
The bentonite used was ‘Berkbent 163’ supplied by Tolsa
UK Ltd. This product is a sodium-activated bentonite and is
commonly used in the UK for fluid-supported excavations
(e.g., Suckling et al., 2011). The moisture content and
methylene blue index of the powder were 12% and 89 meq/
100 g respectively. The bentonite fluid was prepared at a Fig. 4. Apparent viscosity versus shear rate for polymer and bentonite fluids.
dosage of 40 kg/m3 by weight using a high-speed vortex
mixer. The resulting fluid was thixotropic as shown in Jefferis
and Lam (2012). After mixing, the fluid was left to hydrate in a given in the ICE Specification for Piling and Embedded
storage tank for over 24 h before use. No additives were used Retaining Walls (SPERW) (ICE (Institution of Civil Engineers),
with the bentonite slurry. 2007). Therefore, the used bentonite fluid was exchanged at the
end of the excavation – a step which is typically required when
3.3. Support fluids: properties excavating in sand under a bentonite support fluid. If this had not
been carried out, the coarse particles in the fluid could have
The properties of the fluids were measured both before and settled to the pile base to form a ‘soft toe’. The used polymer
after use. The fresh fluids were taken from the storage tank and fluids were cleaned by a chemical method, as will be discussed
the used fluids from the middle and bottom of the pile bores. The later. As regards the viscosity of the fluids, it can be seen that the
properties measured included pH, sand content, density, Marsh Marsh funnel viscosity of the polymer fluids reduced from around
funnel viscosity, and direct-indicating (Fann) viscometer viscosity 70 s when fresh to between 50 and 56 s after use. This reduction
at a range of shear rates. The procedures for these measurements was probably the result of shear degradation during pumping
can be found in FPS (2006) and Lam and Jefferis (2014a) and so (Lam et al., 2010). Polymer molecules absorbing onto the
they are not repeated here. Table 2 summarises the test results for excavated soil and the soil on the side walls could also be a
the pH, sand content, density, and Marsh funnel viscosity tests. It contributing factor for the viscosity reduction (Lam et al., 2014a).
can be seen that the pH of both the bentonite and polymer fluids Finally, it can be seen that the Marsh funnel viscosity of the
either remained the same or slightly reduced slightly with use. bentonite fluid increased slightly in use. This is due to the
This suggests that the chemical condition of the fluids remained suspended soil particles increasing the resistance to fluid flow.
stable during excavation. However, it can be seen that there was a Fig. 4 shows the viscosity (flow) curves of the two fluids in
substantial difference between the two types of fluids for the other both the fresh and used conditions. To assist the interpretation of
parameters. The sand content and the density of the used the results, the data points for the fresh polymer and bentonite
bentonite fluid were found to be much higher than those of their fluids have been fitted to the power-law and Herschel–Bulkley
polymer counterparts. This may be explained by the greater models respectively. Fig. 4 shows that the apparent viscosity of
particle-holding ability of the bentonite fluid. In fact, the sand the bentonite fluids was considerably higher than that of their
contents were so high that they exceeded the limiting values polymer counterparts especially at low shear rates. This explains
1492 C. Lam et al. / Soils and Foundations 55 (2015) 1487–1500
Axial load tests were carried out on the piles when the
concrete was 28 days old. The sequence of testing was: P2, P1, 4. Load test results and interpretation
and B1. Therefore, the testing of pile P2 (located between piles
P1 and B1) may have an effect on the other two test piles due 4.1. Load-settlement response
to pile–soil–pile interaction. The tests were conducted in
accordance with the ‘slow’ maintained load (ML) method Fig. 5 shows the measured load-settlement curves of the
specified in the SPERW. Although this specification only three piles. These results have not been corrected for any
requires the maximum load to be 100% design verification interaction effect due to the upward soil movement caused by
C. Lam et al. / Soils and Foundations 55 (2015) 1487–1500 1493
curves for them are not shown. It can also be seen from Fig. 9f
that pile did not show any sign of having a ‘soft toe’. This
confirms the effectiveness of the rigorous fluid-cleaning and
base-checking procedures adopted for the construction.
Fig. 9. Measured and simulated load versus displacement curves at various instrumentation levels for pile P1.
strain stiffness of Thanet Sand is about 150 MPa estimated means that the back-analysed G values for the two piles
using the Gvh p0 curve given in Ventouras and Coop (2009) constructed using polymers are 80% of the small-strain value,
and the depth-averaged mean effective stress (p0 ) of 520 kPa. It suggesting little soil disturbance caused by the construction
C. Lam et al. / Soils and Foundations 55 (2015) 1487–1500 1497
Fig. 10. Measured and simulated shear stress versus displacement curves for the Woolwich and Reading Formation for all piles.
Fig. 11. Measured and simulated shear stress versus displacement curves for the Upnor Formation for all piles.
process. As regards the parameters for the pile base, the qbf reported range of between 0.36 and 0.8 for the Lambeth Group
values given in Table 3 were directly obtained by conducting by Hight et al. (2004). As mentioned before, there is no
Chin analyses without any adjustment so there are some evidence of α value reduction due to extended pile bore open
differences between them (Chin, 1970). It must be emphasised time when supported by polymer. The back-analysed values
that the back-analysed qbf and wbf values are only approximate also confirm the necessity for residual load correction at this
due to the small amount of base resistance mobilised during the site. If the effect of residual loads had not been considered, the
tests. Sensitivity analyses showed that if the chosen qbf values calculated α values would have doubled.
are increased or decreased by, say, 20%, the overall effect on the
back-analyses is still relatively small and can be compensated
5. Limitations of polymer support fluids
by adjusting the values of wbf .
Although this case history has shown that polymer fluids can
4.6. Back-analysed pile design parameters be successfully used for the construction of bored piles, it must
be recognised that these engineered fluids are fundamentally
To put the back-analysed parameters into the context of pile different from the conventional bentonite slurries, and that
design practice, the τp values have been converted to adhesion problems may occur if the properties of these fluids are not
factors (α) using the chosen Su profiles for the two idealised fully respected (Jefferis and Lam, 2013). For example, polymer
Lambeth Group layers; the results are summarised in Table 4. fluids are known to be prone to shear degradation due to
It can be seen that for the Woolwich and Reading Formations, scission of the long-chain molecules. To avoid viscosity
the α values are about 0.65 for all piles, and that for the Upnor reduction, polymer fluids should not be continuously circulated
Formation, the α values are 0.52, 0.63 and 0.41 for piles P1, P2 at a high flow rate in a closed-loop circuit (Lam et al., 2010).
and B1 respectively. These values are within the previously For the transport of polymer fluids on site, it is recommended
1498
Table 3
Summary of back-analysed soil parameters from load-transfer analyses.
Pile no. Soil layer Pile shaft Pile base Common parameters
Shear Peak shear Yield Ratio of residual Displacement Strain-softening Ultimate unit Displacement
modulus stress parameter to peak shear to residual parameter base to ultimate
stress resistance base
resistance
G: MPa τp : kPa ξ τr =τp Δwres : mm η qbf : kPaa wbf : mm
Ata, A.A., O'Neill, M.W., 1998. Side-wall stability and side-shear resistance in Lam, C., Martin, P.J., Jefferis, S.A., Goodhue Jr., K.G., 2014a. Determination
bored piles constructed with high-molecular-weight polymer slurry. In: of residual concentration of active polymer in a polymeric support fluid.
Proceedings of the 3rd International Geotechnical Seminar on Deep Geotech. Test. J. 37 (1), 46–59. http://dx.doi.org/10.1520/GTJ20130019.
Foundations on Bored and Auger Piles, Ghent, pp. 111–117. Lam, C., Jefferis, S.A., 2014a. Interpretation of viscometer test results for polymer
Axtell, P.J., Thompson, W.R., III, Brown, D.A., 2009. Drilled shaft foundations support fluids. In: Proceedings of Sessions of GeoShanghai 2014 International
for the kcICON Missouri River Bridge. In: Proceedings of the 34th Annual Conference, Shanghai, China, Geotechnical Special Publication No. 242,
Conference on Deep Foundations, Kansas City, Missouri, pp. 3–12. pp. 439–449. http://dx.doi.org/10.1061/9780784413449.043.
Berry, A.G., 2009. Method for cleaning and checking the base of diaphragm Lam, C., Jefferis, S.A., Goodhue, K.G., Jr., 2010. Observations on viscosity
wall panels. Ground Eng. 42 (11), 29–31. reduction of PHPA polymer support fluids. In: Proceedings of Sessions of
Camp, W.M., Brown, D.A., Mayne, P.W., 2002. Construction method effects GeoShanghai 2010 International Conference, Shanghai, China, Geotechni-
on axial drilled shaft performance. Proc. Int. Deep Found. Congr. 2002, cal Special Publication No. 205, pp. 184–191. http://dx.doi.org/10.1061/
193–208 Geotechnical Special Publication No. 116, Orlando, Florida. 41106(379)23.
Chin, F.K., 1970. Estimation of the ultimate load of piles from tests not carried LDSA (London District Surveyors' Association), 2009. Guidance Notes for the
to failure. In: Proceedings of the 2nd Southeast Asian Conference on Soil Design of Straight Shafted Bored Piles in London Clay. LDSA, London,
Engineering, Singapore, pp. 81–90. UK.
Dyson, S., Blight, I., 2007. Channel tunnel rail link section 2: stratford. Proc. Lennon, D.J., Ritchie, D., Parry, G.O., Suckling, T.P., 2006. Piling projects
Inst. Civil Eng. – Civil Eng. 160 (6), 29–32. constructed with vinyl polymer support fluid in Glasgow, Scotland. In:
Fellenius, B.H., 2002. Determining the resistance distribution in piles. Part 2: Proceedings of the 10th International Conference on Piling and Deep
Method for determining the residual load. Geotech. News 20 (3), 25–29. Foundations, Amsterdam, pp. 499–506.
Fleming, K., Weltman, A., Randolph, M., Elson, K., 2009. Piling Engineering, Likos, W.J., Akunuri, K., Loehr, J.E., 2005. Performance of PHPA polymer
3rd ed. Taylor & Francis, Abingdon, UK. slurries for applications in Missouri shale. In: Proceedings of Sessions of
FPS (Federation of Piling Specialists), 2006. Bentonite Support Fluids in Civil Geo-Frontiers 2005 Congress, Austin, Texas, Geotechnical Special Pub-
Engineering, 2nd ed. FPS, Kent, UK. lication No. 132, pp. 665–676.
Goodhue, K.G., Jr., Holmes, M.M., 1995, Earth support fluid composition and O’Neill, M.W., Reese, L.C., 1988. Drilled Shafts: Construction Procedures and
method for its use. United States Patent 5,407,909. Design Methods. Federal highway Administration, U.S. Department of
Hight, D.W., Ellison, R.A., Page, D.P., 2004. Engineering in the Lambeth Transportation, Washington, D.C Publication No. FHWA-HI-88-042.
Group, Report C583. Construction Industry Research and Information O'Riordan, N.J., 1982. The mobilisation of shaft friction down a bored, cast-in-
Association, London, UK. situ pile in the Woolwich and Reading Beds. Ground Eng. 15 (3),
ICE (Institution of Civil Engineers), 2007. ICE Specification for Piling and 17–20 23–26.
Embedded Retaining Walls, 2nd ed. ICE, London. Poulos, H.G., Davis, E.H., 1980. Pile Foundation Analysis and Design. Wiley,
Jefferis, S.A., Lam, C., 2012. Letter to the Editor: Hydraulic characteristics of New York.
bentonite cake fabricated on cutoff walls. Clays and Clay Miner. 60 (6), Randolph, M.F., 2003. RATZ Manual Version 4.2: Load Transfer Analysis of
557–560. http://dx.doi.org/10.1346/ccmn.2012.0600601. Axially Loaded Piles. University of Western Australia, Perth, Australia.
Jefferis, S.A., Lam, C., 2013. Polymer support fluids: use and misuse of Randolph, M.F., Jewell, R.J., 1989. Load transfer model for piles in calcareous
innovative fluids in geotechnical works. In: Proceedings of the 18th soil. In: Proceedings of the 12th International Conference on Soil Mechanics
International Conference on Soil Mechanics and Geotechnical Engineering, and Foundation Engineering, Rio de Janeiro, Brazil, pp. 479–484.
Paris, pp. 3219–3222. Schünmann, D., 2004. Fisherman's friend. Ground Eng. 37 (12), 17.
Jefferis, S., Troughton, V., Lam, C., 2011. Polymer systems for fluid supported Schwarz, J., Lange, U., 2004. Brückengründung mit 70 m tiefen flüssigkeits-
excavations. In: Proceedings of the 2nd Conference on Geotechnical Issues gestützten gebohrten Pfählen in Benin/Afrika. In: Proceedings of the 19th
in Construction, London, CIRIA Report X513, pp. 7–12. Christian Veder Kolloquium, TU Graz, Austria, pp. 73–89 (in German).
Lam, C., Jefferis, S.A., 2010. Critical assessment of pile modulus Suckling, T.P., Lam, C., Jefferis, S.A., Pantling, C.J., 2011. Evaluation of
determination methods. Can. Geotech. J. 48 (10), causes of bleeding of free water from a bentonite slurry. In: Proceedings of
1433–1448. http://dx.doi.org/10.1139/t11-050. the 36th Annual Conference on Deep Foundations, pp. 401–407.
Lam, C., Jefferis, S.A., 2011. Reply to the discussion by Fellenius on “Critical Troughton, V.M., 1992. The design and performance of foundations for the
assessment of pile modulus determination methods”. Can. Geotech. J. 49 Canary Wharf development in London Docklands. Géotechnique 42 (3),
(5), 622–629. http://dx.doi.org/10.1139/t2012-030. 381–393.
Lam, C., Jefferis, S.A., 2014b. The use of polymer solutions for deep Veder, C., 1953. Method for the construction of impermeable diaphragms at
excavations: lessons from Far Eastern experience. HKIE Trans. 21 (4), great depth by means of thixotropic muds. In: Proceedings of the 3rd
262–271. http://dx.doi.org/10.1080/1023697X.2014.970749. International Conference on Soil Mechanics and Foundation Engineering,
Lam, C., Jefferis, S.A., 2015. Physical properties of polymer support fluids in pp. 91–94 (in French).
use and their measurement techniques. Geotech. Test. J. 38 (7), Ventouras, K., Coop, M.R., 2009. On the behaviour of Thanet Sand: An
490–500. http://dx.doi.org/10.1520/GTJ20140032. example of an uncemented natural sand. Géotechnique 59 (9), 727–738.
Lam, C., Jefferis, S.A., Martin, C.M., 2014b. Effects of polymer and bentonite Wheeler, P., 2003. Piles unlock polymer potential. European Foundations,
support fluids on the interface shear strength between concrete and sand. Summer, pp. 8–9.
Géotechnique 64 (1), 28–39. http://dx.doi.org/10.1680/geot.13.P.012. Whitaker, D., 2004. Groundwater control for the Stratford CTRL station box.
Lam, C., Jefferis, S.A., Suckling, T.P., 2014c. Construction techniques for Proc. Inst. Civil Eng. – Geotech. Eng. 157 (GE4), 183–191.
bored piling in sand using polymer fluids. Proc. Inst. Civil Eng. – Geotech. Yetginer, A.G., White, D.J., Bolton, M.D., 2006. Field measurements of the
Eng. 167 (GE6), 565–573. http://dx.doi.org/10.1680/geng.13.00128. stiffness of jacked piles and pile groups. Géotechnique 56 (5), 349–354.