QUANTITY CALCULATION

Name of Structure : Siphon

BOQ
Description of work Drawing
ITEM

B-3.3 Excavation type - C


with spreading and
triming at disposal area

`
QUANTITY CALCULATION

Name of Structure : Siphon

BOQ
Description of work Drawing
ITEM

B-3.3 Excavation type - C


with spreading and
triming at disposal area

+12.56

+13.754

+13.084
POTONGAN Ts4 - Ts4
SECTION

+13.854

+13.154 +13.154

+12.494

POTONGAN Ts4 - Ts4


SECTION
ULATION Page : 1

Calculation Quantity Remark

Excavation type - C with spreading and triming at disposal area

Culvert L = 25.00 m

Area = 14.01 m2

Volume = area x L1
= 14.01 x 25.00
= 350.25 m3 350.25 m3

Potongan C-C L = 17.20 m

Area = 6.69 m2

Volume = area x L1
= 6.69 x 17.20
= 115.07 m3 115.07 m3

Arah flushing L = 13.64 m


Area = 2.74 m2

Volume = area x L1
= 2.74 x 13.64
= 37.37 m3 37.37 m3

Sub Total 1 502.69 m3


ULATION Page : 2

Calculation Quantity Remark

SEGMENT-4 0.00 m3

Potongan Ts2-Ts2 L = m

Area J = 0.70 m2

Volume = area x L
= 0.70 x 0.00
= 0.00 m3

SEGMENT-5 0.00 m3

Potongan Ts4-Ts4 L = m

Area J = 1.51 m2

Volume = area x L
= 1.51 x 0.00
= 0.00 m3

SEGMENT-6 0.00 m3
Potongan Ts4-Ts4 L = m

Area J = 1.09 m2

Volume = area x L
= 1.09 x 0.00
= 0.00 m3

Sub Total 2 0.00 m3


TOTAL 502.69 m3