= 16.88 x 2
= 33.77 m2
= 2.23 x 2
= 4.46 m2
= 8.40 x 2
= 16.81 m2
Area D = (1.5 -0.125/2) (3.048 –0.125)+ (4.335) (3.048 – 0.125/2) + (4.335– 0.125/2) (1.238)
= 34.57 x 2
= 69.14 m2
= 4.94 x 2
= 9.88 m2
= 3.88 m2
= 275.9 m2
= RM 641467.50
= 144.42 x 2
= 288.84 m3
= 23.16 x 2
= 46.31 m3
= 75.36 x 2
= 150.72 m3
= 287.75 x 2
= 575.50 m3
= 48.23 x 2
= 96.47 m3
= 20.59 x 2
= 41.18 m3
= 1199.02 m3
Total cost = RM 505 /m3x 1199.02 m3
= RM 605505.10
LIQUIDATED ASCERTAINED DAMAGES (LAD)
Calculation for amount of liquidated ascertained damages (LAD) per day if the project delay:
RM 492159.47 𝑥 6.65%
= 365
= RM 89.67/day