Professional Documents
Culture Documents
1
Table of Content
2
Part I
TAEIL KANG
CEO, One Energy Island Co., Ltd.
3
Purpose of Feasibility Study
▪ In Pacific Island Countries and Territories (PICTs), still many people living in remote
islands do not have reliable energy access. In recent years, a renewable energy based
mini-grid have been emerging as a solution to provide electricity in remote islands at
an affordable cost in PICTs.
▪ However, still there are issues, both technical and business, to be solved if a mini-grid
becomes a feasible solution to those remote islands.
▪ The purpose of this feasibility study is to design and propose a mini-grid model which
meets 1) grid stability with increased contribution of renewable energies, and 2)
LCOE competitiveness with cost of electricity from diesel, and which offers a suitable
and scalable mini-grid model for PICTs.
▪ This feasibility study was conducted by One Energy Island(OEI), in a consortium with
Anygate and Kookmin University. Korea Energy Agency funded the feasibility study.
4
Palau and Peleliu
5
Palau Energy Statistics
6
Palau Energy Statistics
7
Palau Energy Roadmap
8
Peleliu Energy System
▪ Population: 571
▪ Peak load: 240kW
▪ Power system
- Diesel: 2.218MW (2 units of 750kW, 2 unit of 275kW, 6 units of 28kW)
- Solar PV: 168kWp (Equipped with SMA Fuel Saver Controller)
- Total power generation: 1,217MWh (2016)
- Contribution of renewable energy in electricity supply: 17%
▪ Electricity Tariff
- Residential: USD 0.26/kWh
- Commercial: USD 0.31/kWh
9
Part III
11
Overall Microgrid Design Procedure
Iterative correction
Data Preparation
❖ Environmental
and energy data
❖ Financial data
❖ Power system
technical data
12
Microgrid Design Based on Techno-economic Analysis
Input data
Weather DERs technical
Load profile Project costs Project finance Incentives
resources parameters
Output
Sizing analysis Energy analysis Financial analysis
13
Power System Analysis
Final
Configuration!
▪ S/W Tool: Power Factory
14
Table of Content
❑ Techno-economic Analysis
▪ Optimal energy mix for each REP level
▪ Comparison for DER dispatching algorithm for each REP level
15
Peleliu Microgrid Operation Data
Daily power generation/consumption data analysis
16
Peleliu Microgrid Operation Data
Daily power generation/consumption data analysis
17
Peleliu Microgrid Operation Data
Daily power generation/consumption analysis
18
Peleliu Microgrid Operation Data
Solar irradiance and wind speed analysis
▪ For the purpose of microgrid design, one year of renewable energy data (solar
irradiance and wind speed) is adequate, however, having longer periods of data will
enhance understanding and help in rigorous prediction of resources.
▪ Weather data of solar irradiance and wind speed was obtained from the site visit.
There are three weather stations in Palau, which are located in the State of
Melekeok, Ngardmau, and Ngarrard. We use the data from Melekeok Station, as it
the most complete among the three stations. Monthly Daily radiation Wind speed
Average (kWh/m2/day) (m/s)
Jan. 3.934 4.969
Feb. 5.003 5.213
Mar. 5.185 4.869
Apr. 4.607 4.100
May 5.215 3.220
Jun. 4.286 2.768
Jul. 3.790 4.985
Aug. 4.407 3.121
Melekeok Sep. 3.917 4.989
Oct. 4.027 3.909
Nov. 4.461 3.334
Dec. 4.126 4.874
Annual 4.390 4.150
19
Peleliu Microgrid Operation Data
PV Panel and Inverters
20
Peleliu Microgrid Operation Data
Diesel generators
▪ There are two types of diesel generators normally used in Peleliu:
➢ Hatz (168kW in total = 6*28kW) and FG Wilson (300kW)
Model TDSA6
Rated power 28 kW
Manufacturer HATZ
Engine speed 1800 rpm
Standard voltage 480 V
Frequency 60 Hz
Lifetime 60,000 hours
Woodward Easygen 3000
for Hatz Minimum load ratio 25%
Source: Manufacturer’s datasheet
21
Peleliu Microgrid Operation Data
Diesel generators
Model P375-3
Rated power 300 kW
Manufacturer FG Wilson
Engine speed 1800 rpm
Standard voltage 480 V
Frequency 60 Hz
Lifetime 60,000 hours
Minimum load ratio 25%
Source: Manufacturer’s datasheet
22
Peleliu Microgrid Operation Data
Diesel generators
• Minimum Genset Load
Description Value
Deadband for error output related to the minimum Genset loading threshold 5%
Deadband timer for error output 60 seconds
Minimum genset loading of the genset system in % of the active nominal genset 25 %
power
Ramp time of the change in the gensets active nominal power 10 seconds
Setpoint offset related to the minimum genset loading threshold 5%
23
Peleliu Microgrid Operation Data
SMA Fuel Save Controller (FSC)
FG Wilson
300kW
Hatz
168kW for Total 6 units
28kW/unit
SMA inverters
(8 units of 20kW
Sunny Tripower
inverters)
24
Table of Content
❑ Techno-economic Analysis
▪ Optimal energy mix for each REP level
▪ Comparison for DER dispatching algorithm for each REP level
25
Microgrid Design Tools
Design S/W
26
Microgrid Design Procedure
Based on Techno-Economic Analysis
Evaluation of local
conditions • Power demand (load) analysis
• Resources analysis (solar irradiance, wind speed, etc.)
27
Economic Analysis for Microgrid Design
Key Inputs and Outputs
28
Data Analysis for Microgrid Optimal Design
Load and Energy Resource Data
▪ Load Data: Statistically generated for a year- ▪ Renewable Energy Data: Solar
long data (w/ 10-minute-resolution) from the irradiance and wind speed measured
load data obtained from Peleliu SMA FSC from Melekeok Station in Palau Main
Island
Solar irradiance
Wind speed
29
Data Analysis for Microgrid Optimal Design
Diesel Fuel Price and Consumption
• Environmental
properties of diesel fuel
Lower heating value 43.2
(LHV) MJ/kg
Density 820 kg/m3
Carbon content 88 %
Sulfur content 0.33 %
Power level (kW) 28 22.4 14 Power level (kW) 300 225 150
Consumption (L/hr.) 9.6 7.6 5.25 Consumption (L/hr.) 80.4 60.4 42.9
Source: Manufacturer’s datasheet Source: Manufacturer’s datasheet
30
Data Analysis for Microgrid Optimal Design
ESS and WT Technologies
31
Data Analysis for Microgrid Optimal Design
DER Costs
Costs Value
Photovoltaic
Capital cost per kW $ 2,000
O&M cost per kW per year $ 10
Replacement cost per kW $ 2,000
Wind Turbine
Capital cost per 100 kW $ 500,000
O&M cost per 100 kW per year 1% of capital cost
Replacement cost per 100 kW Not applicable
Energy storage systems
Capital cost per kWh $500
O&M cost per kWh per year $10
Replacement cost per kWh $250
ESS inverter
Capital cost per kW $300
O&M cost per kW per hour Not applicable
Replacement cost per kW $300
Diesel generator
Capital cost per kW $500
O&M cost per kW per hour $0.03
Replacement cost per kW $500
Diesel price 1.01 $/liter (3.82 $/gallon)
33
Preview of Microgrid Design Results
▪ Renewable energy penetration vs. LCOE of simulated cases.
WT is less economical than PV in many cases.
REP 100%
REP 17%
REP 50% is the most economical.
34
Preview of Microgrid Design Results
Capital Cost
Operating Cost
LCOE
35
Summary of Four Cases
Cases Description
• 17% renewable energy penetration (current microgrid in Peleliu)
Case 1 • 164 kW of PV, 160 kW of PV inverter, 7 diesel generators, and a
SMA central controller with communication network
36
Summary of Microgrid Optimal Energy Mix
37
Case 1: 17% Penetration (Current State)
▪ Microgrid Configuration
Component Optimal size Units
PV 164 kW
FG Wilson generator 300 kW
HATZ generator 168 (28 kW x 6 units) kW
▪ Cost Summary
Cost Value Units
Levelized cost of energy (LCOE) 0.353 $/kWh
Net present cost (NPC) 5,637,429 $
Capital cost 562,000 $
Operating cost 392,607 $/year
Renewable penetration 17 %
Fuel consumption 320,837 liters/year
Total emission 845 ton/year
38
Case 1: 17% Penetration (Current State)
39
Case 1: 17% Penetration (Current State)
Operating reserve
▪ Power dispatch profile on a certain day
(= 10% of load + 80% of PV)
40
Cases 2, 3 and 4
Introducing ESS to store surplus energy from RES
▪ ESS Converter
➢ Grid-parallel mode: The ESS converter needs to be synchronized to the grid
frequency, which is controlled by diesel gensets.
➢ Grid-forming mode: The ESS converter supplies the system frequency when
diesel gensets are off.
Diesel Off
41
Cases 2, 3 and 4
Introducing ESS to store surplus energy from RES
▪ Coordination algorithm between diesel gensets and ESS:
➢ Diesel generators and ESS must supply the power for the load demand and the
operating reserve.
➢ Cycle Charging: Similar to load following strategy, cycle charging also use
economic dispatch. However, under this strategy, whenever a generator operates,
it runs at its maximum rated capacity (or as close as possible without incurring
excess electricity) and charges the ESS with the excess.
42
Cases 2, 3 and 4
Introducing ESS to store surplus energy from RES
43
Case 2: 50% Penetration
▪ Optimal Configuration
Component Optimal size Units
PV 564 kW
ESS 925 kWh
ESS Converter 200 kW
FG Wilson generator 300 kW
HATZ generator 168 kW
▪ Cost Summary
Cost Value Units
Levelized cost of energy (LCOE) 0.320 $/kWh
Net present cost (NPC) 5,122,881 $
Capital cost 1,884,500 $
Operating cost 250,502 $/year
Renewable penetration 50.4 %
Fuel consumption 182,867 liters/year
Total emission 482 ton/year
44
Case 2: 50% Penetration
45
Case 2: 50% Penetration
46
Case 3: 75% Penetration
▪ Optimal Configuration
Component Optimal size Units
PV 839 kW
ESS 2,200 kWh
ESS Converter 350 kW
FG Wilson generator 300 kW
HATZ generator 168 kW
▪ Cost Summary
Cost Value Units
Levelized cost of energy (LCOE) 0.328 $/kWh
Net present cost (NPC) 5,251,338 $
Capital cost 3,117,000 $
Operating cost 165,100 $/year
Renewable penetration 75.2 %
Fuel consumption 93,949 liters/year
Total emission 247 ton/year
47
Case 3: 75% Penetration
48
Case 3: 75% Penetration
49
Case 4: 100% Penetration
▪ Optimal Configuration
Component Optimal size Units
PV 1,389 kW
WT 100 kW
ESS 3,750 kWh
ESS Inverter 550 kW
▪ Cost Summary
Cost Value Units
Levelized cost of energy (LCOE) 0.408 $/kWh
Net present cost (NPC) 6,426,707 $
Capital cost 5,318,000 $
Operating cost 85,763 $/year
Renewable penetration 100 %
Fuel consumption 0 liters/year
Total emission 0 ton/year
50
Case 4: 100% Penetration
51
Case 4: 100% Penetration
52
Considering Future Load Increase
53
Effects of Dispatching Algorithm
54