Professional Documents
Culture Documents
Abstract—the prospect of global warming has seen the world’s In Pakistan, the dependency on oil and gas for the generation
transition towards zero carbon energy sources. Amongst the of electricity is significantly insufficient, but their insufficiency
renewable energy technologies, solar photovoltaic (PV) and wind is not primarily the reason for crippling the power shortage.
are the most mature. This paper discusses the modeling of on-grid There is a giant problem of circular debt which has been
solar PV system without battery storage along with its
accumulated in the power sector of Pakistan[6]. In
performance analysis. In the latter part of the paper, economic
feasibility and the reduction in carbon emissions from the project contradiction to the conventional power system, in which
are also calculated. The calculations and analysis discussed in the power generation is centralized and limited access for new
paper are performed for head office building of Jubilee Life producers, the distributed energy generation through
Insurance Company Limited, located in Karachi, Pakistan. The renewables experiences the power flow in multitude sources
city has longitude of 25°N and latitude of 67°E. and loads. The cost issues related to the power generation using
Keywords — PV system, PV modeling, renewable energy, renewable sources has always been the negative point for solar
feasibility analysis energy in general and unambiguously for photovoltaic.
I. INTRODUCTION Although the increased manufacturing of PV panels has a
significant impact on the cost of PV generated electricity.
The electricity short fall in Pakistan was recorded to be 5298 However, it is still far higher than the per unit cost of electricity
MW during the fiscal year 2015-16[1]. As per the “State of generated via conventional methods[7].
Industry Report” published by the National Electric and Power Various research work has been carried out worldwide for the
Regulatory Authority (NEPRA), the electric shortfall is likely determination of techno-economic feasibility of an on-grid PV
to persist for the upcoming 2 years[1, 2]. Given the strong system as discussed in section I. A techno-economic feasibility
existing potential of solar PV generation in majority areas of analysis has been carried out for a 500 KW on-grid PV system
Pakistan[3], the electricity shortfall can be catered by the use of in Bangladesh, the economic affect was evaluated in local
distributed generation at the consumer end. This will not only currency and the total payback for the said scheme was
reduce the maximum system demand, but also the cost of calculated to be 13.1 years and carbon emission reduction was
generation will be less if the roof top of buildings, which is calculated to be 658 tons[8]. The research was executed on RET
usually unoccupied, is used for PV generation. Screen and solar irradiation data was selected from NASA.
After tremendous researches, it has been found out that the Similar economic feasibility analysis research was profound for
demand shortfall can be suppressed by extending generation a commercial area in Bangladesh and was found feasible as the
through renewables. This will only lead to decrease in national internal rate of return was greater than the capital cost utilized
grid shortfall, but also cause decrement in carbon footprints[4]. in setting up the PV micro utility system[9]. A techno economic
Pakistan’s geographical resources favor the utilization of feasibility analysis was carried out for a deserted region whose
conventional generation techniques as it is rich in natural demand was met by the hybrid power generation system
resources but due to socio-economic difficulties and greenhouse consisting of PV and fuel cells that actually catered primary air-
effect, generation capabilities are restricted. The power sector of conditioning loads along with the surplus power supply to
Pakistan mainly comprises of WAPDA (Water and Power electrolyzer for hydrogen cell. It was found viable with the per
Development Authority), K-electric (Karachi Electric), unit cost of 145$/MWh with the minimal carbon emission rate
HUBCO (Hub Power Company) and Nuclear Power Plants. during generation[10].
Approximately 35% of national electricity is generated by using In order to design efficient solar photovoltaic panels, proper
furnace oil as a primary source[5]. To extend the power sizing of PV panels and batteries are essential to satisfy the cost
generation facility, Independent Power Producers have been and energy factors. Various strategies have been used for the
magnetized into this ever-expanding power sector.
Jun 5.44 31.1 59.9 17.83 16.60 2,708.77 The cost savings resulting from the system will be:
Cost Savings = Annual System Yield × 16 PKR/kWh
Jul 4.37 30.3 59.1 17.90 16.66 2,257.12
= 33796.5×16
Aug 4.58 29.1 57.9 18.00 16.76 2,379.11 = 540,744 PKR
Sep 5.97 28.9 57.7 18.02 16.77 3,003.96 These savings should also incur the GST (General Sales Tax) of
Oct 6.14 29.1 57.9 18.00 16.76 3,086.58 16%. So:
Nov 5.43 24.9 53.7 18.36 17.09 2,783.98 Cost savings = 540,744×1.16
Dec 5.01 20.9 49.7 18.70 17.41 2,703.59 = 627,263 PKR
4 DC Cables 280 Meter 47,600 The savings are based on annual return so the formula of
5 AC Cables 40 Meter 27,200 present value of annuity must be applied and for inverter costs.
Simple compound interest formulae can be used as shown in (1)
6 Earthling 40 Meter 7,000 and (2) respectively.
7 AC Combiner 1 Nos. 12,000
P(1 + (1 + i) )
Present value of Annuity = (1)
i
Present Value = Future Value (1 + i) (2) [8] M. A. H. Mondal and A. S. Islam, "Techno-economic
where P is the periodic saving (in years) feasibility of grid connected solar PV system in
i is the interest rate (per year) Bangladesh," in Developments in Renewable Energy
n is the time duration (in years) Technology (ICDRET), 2009 1st International Conference
on the, 2009, pp. 1-4.
1,947,280= 577,263×{[1-(1+i)-25]/(i)}- [9] F. Ahammed and A. Azeem, "An economic analysis of
220,000[(1+i)-7+(1+i) -14+(1+i) -21] solar PV micro-utility in rural areas of Bangladesh," in
Developments in Renewable Energy Technology
Solving the equation for ‘i’, the IRR is found to be 28.9%. (ICDRET), 2009 1st International Conference on the,
2009, pp. 1-4.
D. Net Present Value (NPV):
[10] C. Ghenai, T. Salameh, and A. Merabet, "Technico-
The net present value is a tool that determines the net savings economic analysis of off grid solar PV/Fuel cell energy
from whole life of the project in current worth. The NPV of the system for residential community in desert region,"
project, over a life of 25 years and an interest rate of 10%, can International Journal of Hydrogen Energy, 2018.
be calculated from (1) and (2). [11] D. Fendri, M. Ammous, and M. Chaabene, "PV/Batteries
sizing under multi criteria consideration," in Renewable
NPV = 577,263×{[1-(1+i)-25]/(i)}-220,000[(1+i)-7 Energy Congress (IREC), 2017 8th International, 2017,
+(1+i) -14+(1+i) -21]-1,947,280 pp. 1-5.
NPV = 3,092,003 PKR [12] C. K. Nayak and M. R. Nayak, "Optimal size and cost
analysis of standalone PV system with battery energy
IV. ENVIRONMENTAL IMPACT OF THE PROJECT
storage using IHSA," in Signal Processing,
The carbon emission factor for Pakistan is 630gm- Communication, Power and Embedded System (SCOPES),
CO2/kWh, so by the installation of this project with a 2016 International Conference on, 2016, pp. 1037-1043.
production of 28,998 kWh/years, 18.3 tons CO2 will be saved [13] J. P. Ram, T. S. Babu, and N. Rajasekar, "A comprehensive
from being released into atmosphere. review on solar PV maximum power point tracking
techniques," Renewable and Sustainable Energy Reviews,
V. CONCLUSION vol. 67, pp. 826-847, 2017.
The project feasibility can be seen from various angles, it has a [14] D. G. F. Sonnenenergie, Planning and installing
payback period of 4.32 years which is lesser than its life, its photovoltaic systems: a guide for installers, architects and
NPV is positive and it has an attractive IRR. All these factors engineers: Earthscan, 2007.
indicate the feasibility of the project. Importantly, its [15] C. S. INC., "PV Module Product Datasheet," in CS6U-
environmental impact is appealing as in save 18.3 tons of 325|330|335|340P vol. V5.551_EN, ed, 2017.
CO2/year to be released into the atmosphere. [16] S. S. Technology, "Solar Inverters," ed.
[17] M. 7.1. Global climate database [Online]. Available:
VI. REFERENCES http://www.meteonorm.com/
[1] N. E. a. P. R. A. (NEPRA), "State of the Industry Report," [18] K. E. P. Ltd, "REVISED SCHDULE OF ELECTRICITY
2016. TARIFF FOR K-ELECTRIC LIMITED (Formerly
[2] D. Naeem, "Tariff setting for independent hydro power KESC)," ed, 2016.
producers in perspective of Pakistan's electric power
market," USPCAS-E, NUST, 2015.
[3] N. Jamal and O. Hohmeyer, "Solar resources' potential role
in the development of renewable based electric power
system by 2050: The case of Pakistan prospects of solar in
Pakistan," in 2014 International Conference on Energy
Systems and Policies (ICESP), 2014, pp. 1-7.
[4] I. N. Kessides, "Chaos in power: Pakistan's electricity
crisis," Energy policy, vol. 55, pp. 271-285, 2013.
[5] P. A. Samad, F. Xiumei, and N. Sangi, "CURRENT
POWER GENERATION AND ALTERNATIVE TRENDS
IN PAKISTAN (A CASE STUDY)," Science International,
vol. 28, 2016.
[6] R. Patel and N. Zhao, "Keeping the Lights On: Fixing
Pakistan’s Energy Crisis," Public Interest Report, vol. 67,
2014.
[7] S. Sandu, L. Jaques, M. Bradshaw, L. Carson, A. Budd, M.
Huleatt, et al., "Australian energy resource assessment,"
2010.