You are on page 1of 4

Economic Feasibility Analysis of On-Grid PV System

without Battery Storage for a Commercial Building in


Karachi, Pakistan
Talha Javed Soleja, Muhammad Farooq Areeb Waseem
Siddiqui Muhammad Kashan
Department of Electrical Engineering Jubilee Corporation Jubilee Life Insurance Company Limited
NED University of Engineering and Fakhri Trade Centre, Shahrah-e-Liaquat, 74 / 1 –A, Lalazar, M.T. Khan Road,
Technology, Karachi, Pakistan Karachi, Pakistan
University Road, Karachi, Pakistan kashan_92@hotmail.com areeb.waseem@jubileelife.com
mfqsidd@neduet.edu.pk
talhajaved@neduet.edu.pk

Abstract—the prospect of global warming has seen the world’s In Pakistan, the dependency on oil and gas for the generation
transition towards zero carbon energy sources. Amongst the of electricity is significantly insufficient, but their insufficiency
renewable energy technologies, solar photovoltaic (PV) and wind is not primarily the reason for crippling the power shortage.
are the most mature. This paper discusses the modeling of on-grid There is a giant problem of circular debt which has been
solar PV system without battery storage along with its
accumulated in the power sector of Pakistan[6]. In
performance analysis. In the latter part of the paper, economic
feasibility and the reduction in carbon emissions from the project contradiction to the conventional power system, in which
are also calculated. The calculations and analysis discussed in the power generation is centralized and limited access for new
paper are performed for head office building of Jubilee Life producers, the distributed energy generation through
Insurance Company Limited, located in Karachi, Pakistan. The renewables experiences the power flow in multitude sources
city has longitude of 25°N and latitude of 67°E. and loads. The cost issues related to the power generation using
Keywords — PV system, PV modeling, renewable energy, renewable sources has always been the negative point for solar
feasibility analysis energy in general and unambiguously for photovoltaic.
I. INTRODUCTION Although the increased manufacturing of PV panels has a
significant impact on the cost of PV generated electricity.
The electricity short fall in Pakistan was recorded to be 5298 However, it is still far higher than the per unit cost of electricity
MW during the fiscal year 2015-16[1]. As per the “State of generated via conventional methods[7].
Industry Report” published by the National Electric and Power Various research work has been carried out worldwide for the
Regulatory Authority (NEPRA), the electric shortfall is likely determination of techno-economic feasibility of an on-grid PV
to persist for the upcoming 2 years[1, 2]. Given the strong system as discussed in section I. A techno-economic feasibility
existing potential of solar PV generation in majority areas of analysis has been carried out for a 500 KW on-grid PV system
Pakistan[3], the electricity shortfall can be catered by the use of in Bangladesh, the economic affect was evaluated in local
distributed generation at the consumer end. This will not only currency and the total payback for the said scheme was
reduce the maximum system demand, but also the cost of calculated to be 13.1 years and carbon emission reduction was
generation will be less if the roof top of buildings, which is calculated to be 658 tons[8]. The research was executed on RET
usually unoccupied, is used for PV generation. Screen and solar irradiation data was selected from NASA.
After tremendous researches, it has been found out that the Similar economic feasibility analysis research was profound for
demand shortfall can be suppressed by extending generation a commercial area in Bangladesh and was found feasible as the
through renewables. This will only lead to decrease in national internal rate of return was greater than the capital cost utilized
grid shortfall, but also cause decrement in carbon footprints[4]. in setting up the PV micro utility system[9]. A techno economic
Pakistan’s geographical resources favor the utilization of feasibility analysis was carried out for a deserted region whose
conventional generation techniques as it is rich in natural demand was met by the hybrid power generation system
resources but due to socio-economic difficulties and greenhouse consisting of PV and fuel cells that actually catered primary air-
effect, generation capabilities are restricted. The power sector of conditioning loads along with the surplus power supply to
Pakistan mainly comprises of WAPDA (Water and Power electrolyzer for hydrogen cell. It was found viable with the per
Development Authority), K-electric (Karachi Electric), unit cost of 145$/MWh with the minimal carbon emission rate
HUBCO (Hub Power Company) and Nuclear Power Plants. during generation[10].
Approximately 35% of national electricity is generated by using In order to design efficient solar photovoltaic panels, proper
furnace oil as a primary source[5]. To extend the power sizing of PV panels and batteries are essential to satisfy the cost
generation facility, Independent Power Producers have been and energy factors. Various strategies have been used for the
magnetized into this ever-expanding power sector.

978-1-5386-5517-7/18/$31.00 ©2018 IEEE


proper sizing of PV panels along with the auxiliaries. A The inverter size must be greater than the total panel size[14],
standalone PV system was examined for Sfax, Tunisia using so an inverter of 25 kW rating is selected. The system without
multi-criteria consideration and was found to be 55% annual battery is used, which means that the leftover demand of the
profitable by the proposed sizing technique[11].Another system will be fulfilled by the utility grid. Also, the net-metering
strategy for determination of best cost efficient design analysis setup is not used so the system needs to be cut off in case of
was performed for rural areas in Rajasthan, India for maximum lesser demand. Polycrystalline PV module CS6U-325 from the
annual cost savings of the system by using Improved Harmony manufacturer “Canadian Solar” with a tilt of 25 degrees and
Search Algorithm (IHSA) and was found robust and inverter from the manufacturer Sunny Tripower (SMA) is
feasible[12]. The technical terminologies involved are the I-V selected for installation. The system layout is shown in figure I.
characteristic curves of the PV module that must be examined,
along with the necessary short circuit current ratings(Isc), The output of a PV panel varies as a function of daily
maximum power voltage(Vmp), photovoltaic current(Ipv), diode insolation (hours of peak sun), panel efficiency at STC
saturation current (Is) and open circuit voltage(Voc). This data (Standard Temperature Condition), losses due to dirt, cable and
is usually provided by the manufacturer[13]. However, if the inverter[14] is given by:
mentioned characteristics are not available, they can be
obtained by using analytical or optimization techniques. Pdc = Prated × [1-CT(Tcell-TSTC)]
In this research work, analysis has been carried out for on-grid where Pdc is DC power from the panel
PV system for a commercial building in Karachi, Pakistan. The Prated is the rated power from the panel
grid connected solar PV system is one which is connected to the CT is Temperature coefficient in ⁰C
grid so that the power can be exported or imported via a net- Tcell is the cell temperature and is given by:
metering system. The PV generation system can be installed in
two ways, either with the battery storage system, or without a S(NOCT − 20)
battery storage system. The battery storage system gives the T =T +
800
advantage of high reliability and power storage, but is costly where Ta is the average temperature of the geographical
mainly due to the battery recurring battery replacement costs. location
Another option to install solar power is to use a PV system NOCT is the nominal operating cell temperature
without battery storage, this system will work only during the S is solar radiation intensity required = 1000 W/m2
sun hours. A grid connection is essential to ensure the supply of
electric power above the maximum plant capacity and during The selected module has a NOCT of 43°C and the
night hours. In case of non-availability of net-metering, a cut-off temperature coefficient is 0.41% / °C [15]. The AC output power
system is required to stop production of power on days where is given by:
the load is less than the system rating to avoid damage being Pac = Pdc × ninv × nmismatch
caused to the system. Therefore, this system is efficient for where ηinv is the efficiency of inverter
commercial buildings and offices where the running load during ηmismatch are the losses due to current mismatch
the daytime is almost constant.
In this paper, the economic feasibility analysis has been The inverter efficiency is 98% and the mismatch losses are
evaluated in terms of annual cost savings, payback period for the considered to be 5%[16].
utilized capital cost on the installation of on-grid PV system, the
internal rate of return along with the net present value. The Now considering the historical data of the site available[17],
analysis includes real time data for inverter efficiency at given the monthly units generated are shown in table I as under.
temperatures. The cost of equipment includes merely based on
market prices in PKR (Pakistani Rupees). Another feasibility
factor that has been encountered in this research work is the
carbon emission in grams/Kwh that has been calculated in
section IV.
II. MODELLING OF PV SYSTEM
The major factors that must be considered while modeling a
PV system are the load type, total load and space available for
the installation of solar panels. The building on which the project
is implemented has an area of around 270m2 and a connected
load of 342 kW. So, in this case, the available area is the major
constraint. It is determined that, keeping in view the
intermediate spacing between tilted panels and the shading
analysis, a PV system of 20.9 kW size can be installed at the roof
top of the selected building.
Figure I: The layout of On-grid solar without Battery Storage
Table I: Output of the Installed PV System
8 DC Combiner 1 Job 10,000
Average
Kwh/ Temper Tcell DC AC System 9 Perforated Cable Tray 100 Meter 90,000
m2day ature Power Power output
10 Miscellaneous Job 45,000
Month (°C) (°C) (kW) (kW) (kWh)
Transportation and
Jan 5.59 19.5 48.3 18.82 17.52 3,035.84 11 Material handling Job 35,000
Feb 5.54 22.3 51.1 18.58 17.30 2,683.04 12 Commissioning Job 20,000
Mar 5.88 26.4 55.2 18.23 16.97 3,093.48 13 Installation Job 65,000
Apr 6.15 29.0 57.8 18.01 16.76 3,093.07 Total Turnkey Cost of the System 1,947,280
May 5.76 30.8 59.6 17.85 16.62 2,967.97

Jun 5.44 31.1 59.9 17.83 16.60 2,708.77 The cost savings resulting from the system will be:
Cost Savings = Annual System Yield × 16 PKR/kWh
Jul 4.37 30.3 59.1 17.90 16.66 2,257.12
= 33796.5×16
Aug 4.58 29.1 57.9 18.00 16.76 2,379.11 = 540,744 PKR
Sep 5.97 28.9 57.7 18.02 16.77 3,003.96 These savings should also incur the GST (General Sales Tax) of
Oct 6.14 29.1 57.9 18.00 16.76 3,086.58 16%. So:

Nov 5.43 24.9 53.7 18.36 17.09 2,783.98 Cost savings = 540,744×1.16
Dec 5.01 20.9 49.7 18.70 17.41 2,703.59 = 627,263 PKR

Total annual yield of the System 33,796.5


B. Payback Period:
The payback period is an effective tool to determine the
feasibility of a project. The operation and maintenance cost are
III. ECONOMIC FEASIBILITY OF THE PROJECT taken to be 50,000 PKR/year, taking a discount rate of 10%
A. Cost and Savings of the Project: (KIBOR-Karachi Inter Bank Offer Rate + 3%), the payback
The total cost of the project, inclusive of all taxes and period is given by:
installation charges, as quoted by the vender is PKR 2,147,280. (1 + i) − 1
Total Cost = Yearly Saving ×
The cost breakdown is shown as under in table II. i(1 + i)
The facility electricity pricing is charged as a two part tariff
A-2B, fixed charges, which are a function of the system where n= payback period
maximum demand (PKR 400/kW) that occurs during the billing i= interest rate
cycle and the variable charges, which are a function of the n n
1,947,280= 577,263×[(1+10%) – 1]/ [10% × (1+10%) ]
kWh(kilo watt hour) of energy consumed (PKR 16/kWh)[18]. Solving the equation for ‘n’;
The installation of the project will greatly affect the no. of units n= 4.32 years
consumed from the utility as these units are now being generated
locally. C. Internal Rate of Return (IRR):
The project IRR for a life of 25 years, for which the output
Table II: Total Cost of the Project
of the solar panel is guaranteed. It is assumed that the annual
Amount derating in the performance of the system is balanced by the
S.No Component Qty. Units (PKR)
effect of inflation on the electricity prices that are to be
1 Solar PV Panel 64 Nos. 1,040,000 purchased from utility if the solar system is not present.
2 Solar Inverter, 1 Nos. 220,000 Inverter replacement cost (every 7 years) = 220,000PKR
Solar PV mounting Total Cost = Present Value of (Savings – Operation and
3 structure 1 Job 328,480 Maintenance Costs) – Present Value of Replacement Costs

4 DC Cables 280 Meter 47,600 The savings are based on annual return so the formula of
5 AC Cables 40 Meter 27,200 present value of annuity must be applied and for inverter costs.
Simple compound interest formulae can be used as shown in (1)
6 Earthling 40 Meter 7,000 and (2) respectively.
7 AC Combiner 1 Nos. 12,000
P(1 + (1 + i) )
Present value of Annuity = (1)
i
Present Value = Future Value (1 + i) (2) [8] M. A. H. Mondal and A. S. Islam, "Techno-economic
where P is the periodic saving (in years) feasibility of grid connected solar PV system in
i is the interest rate (per year) Bangladesh," in Developments in Renewable Energy
n is the time duration (in years) Technology (ICDRET), 2009 1st International Conference
on the, 2009, pp. 1-4.
1,947,280= 577,263×{[1-(1+i)-25]/(i)}- [9] F. Ahammed and A. Azeem, "An economic analysis of
220,000[(1+i)-7+(1+i) -14+(1+i) -21] solar PV micro-utility in rural areas of Bangladesh," in
Developments in Renewable Energy Technology
Solving the equation for ‘i’, the IRR is found to be 28.9%. (ICDRET), 2009 1st International Conference on the,
2009, pp. 1-4.
D. Net Present Value (NPV):
[10] C. Ghenai, T. Salameh, and A. Merabet, "Technico-
The net present value is a tool that determines the net savings economic analysis of off grid solar PV/Fuel cell energy
from whole life of the project in current worth. The NPV of the system for residential community in desert region,"
project, over a life of 25 years and an interest rate of 10%, can International Journal of Hydrogen Energy, 2018.
be calculated from (1) and (2). [11] D. Fendri, M. Ammous, and M. Chaabene, "PV/Batteries
sizing under multi criteria consideration," in Renewable
NPV = 577,263×{[1-(1+i)-25]/(i)}-220,000[(1+i)-7 Energy Congress (IREC), 2017 8th International, 2017,
+(1+i) -14+(1+i) -21]-1,947,280 pp. 1-5.
NPV = 3,092,003 PKR [12] C. K. Nayak and M. R. Nayak, "Optimal size and cost
analysis of standalone PV system with battery energy
IV. ENVIRONMENTAL IMPACT OF THE PROJECT
storage using IHSA," in Signal Processing,
The carbon emission factor for Pakistan is 630gm- Communication, Power and Embedded System (SCOPES),
CO2/kWh, so by the installation of this project with a 2016 International Conference on, 2016, pp. 1037-1043.
production of 28,998 kWh/years, 18.3 tons CO2 will be saved [13] J. P. Ram, T. S. Babu, and N. Rajasekar, "A comprehensive
from being released into atmosphere. review on solar PV maximum power point tracking
techniques," Renewable and Sustainable Energy Reviews,
V. CONCLUSION vol. 67, pp. 826-847, 2017.
The project feasibility can be seen from various angles, it has a [14] D. G. F. Sonnenenergie, Planning and installing
payback period of 4.32 years which is lesser than its life, its photovoltaic systems: a guide for installers, architects and
NPV is positive and it has an attractive IRR. All these factors engineers: Earthscan, 2007.
indicate the feasibility of the project. Importantly, its [15] C. S. INC., "PV Module Product Datasheet," in CS6U-
environmental impact is appealing as in save 18.3 tons of 325|330|335|340P vol. V5.551_EN, ed, 2017.
CO2/year to be released into the atmosphere. [16] S. S. Technology, "Solar Inverters," ed.
[17] M. 7.1. Global climate database [Online]. Available:
VI. REFERENCES http://www.meteonorm.com/
[1] N. E. a. P. R. A. (NEPRA), "State of the Industry Report," [18] K. E. P. Ltd, "REVISED SCHDULE OF ELECTRICITY
2016. TARIFF FOR K-ELECTRIC LIMITED (Formerly
[2] D. Naeem, "Tariff setting for independent hydro power KESC)," ed, 2016.
producers in perspective of Pakistan's electric power
market," USPCAS-E, NUST, 2015.
[3] N. Jamal and O. Hohmeyer, "Solar resources' potential role
in the development of renewable based electric power
system by 2050: The case of Pakistan prospects of solar in
Pakistan," in 2014 International Conference on Energy
Systems and Policies (ICESP), 2014, pp. 1-7.
[4] I. N. Kessides, "Chaos in power: Pakistan's electricity
crisis," Energy policy, vol. 55, pp. 271-285, 2013.
[5] P. A. Samad, F. Xiumei, and N. Sangi, "CURRENT
POWER GENERATION AND ALTERNATIVE TRENDS
IN PAKISTAN (A CASE STUDY)," Science International,
vol. 28, 2016.
[6] R. Patel and N. Zhao, "Keeping the Lights On: Fixing
Pakistan’s Energy Crisis," Public Interest Report, vol. 67,
2014.
[7] S. Sandu, L. Jaques, M. Bradshaw, L. Carson, A. Budd, M.
Huleatt, et al., "Australian energy resource assessment,"
2010.

You might also like