Professional Documents
Culture Documents
OF
The COMMITTEE
ON
SECOND PHASE
MODERNISATION OF TRACK
MARCH, 2014
INDEX
Executive Summary i to
xiii
1. Background
1.0 Introduction…………………………………………………………… 1
2.0 First Phase of Modernization of Track…………………………….. 3
3.0 Mechanization of Track Maintenance……………………………... 4
4.0 Benefits from First phase of Modernization………………………. 6
5.0 Need for Second Phase of Modernization of Track……………… 7
6.0 Formation of Committee……………………………………………. 8
7.0 Deliberations by Committee……………………………………….. 9
2. Track structure
1.0 Introduction…………………………………………………………… 10
2.0 Formation…………………………………………………………….. 11
3.0 Ballast and Ballast Cushion………………………………………… 12
4.0 Sleeper and Sleeper density……………………………………….. 13
5.0 Fastening 16
System…………………………………………………….
6.0 Rails…………………………………………………………………… 17
7.0 Rail Welding………………………………………………………….. 22
8.0 Turnouts……………………………………………………………… 23
9.0 Level Crossings……………………………………………………… 24
10.0 Special features on Track………………………………………….. 25
11.0 Long Welded Rails…………………………………………………... 28
12.0 Summary and Conclusions…………………………………………. 29
2.0 Objectives :
The present study is made for upgrading the track structure and
redefining the track maintenance strategy with following objectives:
i) To universalize operation of 25T axle load at 100KMPH speed to
increase throughput.
ii) To permit operation of passenger trains upto speeds of 200 KMPH
on existing mixed traffic routes.
iii) To re-design the track structure and track maintenance practices to
achieve reduction in unit cost of maintenance with improved safety
and reliability of Permanent Way assets.
iv) To mechanize the maintenance and other activities to make system
more human friendly under the changed socio-economic scenario.
3.1 Adoption of the improved track structure is not likely to have significant
cost implications. The marginal increase in cost of rails due to higher
rail section will be offset by increased service life. The new design of
PSC sleeper with wider base and heavier section is likely to cost same
as present PSC sleeper due to reduced reinforcement steel. The
increased cost of sturdier turnout with thick web switches and weldable
CMS crossings will be offset by increased service life and reduced
i
maintenance needs. The proposed modernization will therefore result
in overall saving in track renewal and maintenance costs.
3.5 Overall, though initial inputs will be needed for measures suggested in
the report, substantial benefits in form of availability of infrastructure for
higher axle load and higher speed of operations, reduced cost of
maintenance, and improved availability of infrastructure for operations
will accrue to the system. The likely reduction in manpower
requirement after full implementation of the recommendations will be of
the order of 30-35% of the required strength as per MCNTM formula.
3.6 The modernization initiatives will align the track inspection and
maintenance practices with the changed socio economic scenario,
which will result into better satisfied and enabled workforce. Such
Intangible benefits cannot be quantified in monetary terms.
4.1 The review has been done for existing stipulations and practices with
emphasis on following:
4.1.1 The track structure shall be able to cater the present and foreseeable
traffic demands without any serious restriction with reduced
maintenance requirement with increased reliability.
ii
4.1.2 The subjective manual inspection system shall be replaced with
objective mechanized inspection to the extent possible. The present
inspection based system shall give way to compliance oriented system
with proper monitoring about quality of output.
4.1.3 The heavier and sturdier track structure will require mechanized
maintenance and the nature of maintenance will depend upon the track
degradation rate rather than maintenance at fixed periodicity. Complete
mechanization of maintenance with mechanized monitoring & analysis
tools is the prerequisite of the track modernization.
4.1.4 The track patrolling under extreme climatic conditions is required for
safety of train operations. Suitable technological aids need to be
identified/developed to eliminate/reduce need for track patrolling.
4.1.5 The systemic changes required for effective implementation of
modernization of track have also been considered for implementation
for optimum benefits of modernization measures.
4.1.6 The status of available technology with IR and technology required has
also been reviewed for sustainable modernization initiatives.
4.1.7 The uniformity of track structure with overall aim of reduced inventory
and effective material management.
4.1.8 The designed system of inspection & maintenance of P-way with the
objective of minimizing the present day highly manual & labour
intensive systems to suit the changing socio economic scenario of the
country.
5.1.1 Rails:
(a) 60 Kg 90 UTS rails with improved metallurgy on routes not
envisaged for 25T operations in near future.
(b) 68 kg, 90 UTS rails with improved rail metallurgy for enhanced
ductility, corrosion resistant properties etc on routes envisaged for
25t operations.
iii
(c) 68 Kg head hardened rails for specific locations like sharp curves,
steep gradients and on freight predominant routes with 25T axle
load regular operations.
5.1.2 Sleepers:
(a) Wider base PSC sleepers with rail seat design to accommodate
both 60 kg & 68 Kg rail sections with different set of liners.
(b) Sleeper density 1660 nos per km.
5.1.4 Ballast:
Existing stipulations i.e. hard stone machine crushed ballast and ballast
cushion of 350 mm are retained.
5.1.5 Formation:
Existing stipulations for new constructions of well compacted formation
with required blanket layer are retained.
5.1.6 Turnouts:
(a) Thick Web Switches with improved SSD
(b) Weldable CMS crossings
5.1.7 Long welded rails (LWR) with flash butt welds and improved switch
expansion joints.
iv
5.2.3 Water level monitoring systems for bridges:
To eliminate the need of stationary watchman at bridges.
5.2.4 Settlement & slip monitoring system for cuttings and vulnerable
locations:
To reduce/eliminate the need for monsoon patrolling at vulnerable
locations. Suitable system shall be developed for IR conditions.
TRC shall be upgraded with facility to record track geometry, car body
accelerations, rail profile measurement, corrugation measurement,
video monitoring of rail components, axle-box level accelerations,
structure clearance etc.
OMS with dedicated coaches fitted with facility of video monitoring for
track components, axle-box level accelerations and clearance
measuring system.
5.4.1 With the adoption of heavier track structure and elimination of fish
plated track, it will not be necessary to attend track periodically from
one end to other. The three tier mechanized maintenance system shall
v
replace the conventional periodical maintenance system, with set up as
under:
(i) OMU – On Track Maintenance Unit
(ii) MMU – Mobile Maintenance Unit
(iii) SG- Sectional Gangs
5.4.2 The MMU shall be implemented on all Divisions of Indian Railway with
special emphasis on following aspects:
5.5.2.1 The sectional gangs having 5-10 km beat headed by P-way Mates as
per existing.
5.5.2.2 JE/P-way in-charge of one or two sectional gangs, responsible for
activities presently assigned to Sr.PWS.
5.5.2.3 SSE/P-way/Section having jurisdiction of 40-50 Km on Single line
and 20-25 Km on double line will have three to four sectional gangs.
(existing)
5.5.2.4 SSE/ P-way /Incharge, having jurisdiction of 80-100 kms on single
line or 40-50 kms on double line, assisted by two SSEs/P-
way/Section and one SSE/ P-way /Special works.
5.5.2.5 Each Sub-Division (ADEN‟s jurisdiction) will span over two SSE/ P-
way /In-charge.
vi
5.5.3 The duties and responsibilities of SSE/Incharge and SSE/Section will
be broadly the same as stipulated in IRPWM with rationalized schedule
of inspection for modern track structures.
5.5.5 Inspection formats shall also be revised keeping in view the modern
track structure and the mechanized inspection aids now available.
5.5.6 With uniformity in track structure and provision of better mobility means
with field supervisors, the management of P-way stores will be
streamlined by amalgamating the supervisor-wise store into
subdivision-wise store for day to day material requirement. This will
result into reduced inventory as well as manpower requirement for
stores management.
5.6.1 Long welded rails shall be provided at all feasible locations for better
maintainability, reliability and riding.
5.6.1.1 The design of all new bridges shall be done for track-bridge
interaction forces for LWR, so that there is no limitation on
continuation of LWR.
5.6.1.2 In-house capability shall be developed at RDSO for analysis of track-
bridge interaction for technical scrutiny to allow LWR on existing
bridges as well as retro fitment.
5.6.1.3 Code of practice for continuation of long welded rails at critical
locations such as sharp curves, steep gradients, turnouts, bridges,
etc. shall be formulated by RDSO, along with requisite software.
5.6.1.4 Suitable system for rail stress monitoring and determination of stress
free temperature shall be deployed for need based de-stressing of
LWR.
vii
5.6.2.1 Higher UTS rails need special attention both during handling and in
service. Rail grinding and rail lubrication are must for rail of 90 UTS &
above to maximize service life of these rails.
The vehicle based system for ultrasonic testing of rail/ welds with
follow-up manual testing shall be adopted for better reliability of USFD
testing.
viii
(a) Facility for direct input from mechanized inspection means.
(b) Facility for direct input of USFD test results from USFD testing
machines.
(c) The modules assisting field officials such as module for Inventory
Management, Resource management in accordance with need for
predictive maintenance based on track degradation model, etc.
ix
5.11.3 System of Mobility:
With large scale adoption of small track machines (STM) & track tools
for complete mechanization, adequate arrangement for transportation
and regular repair and maintenance shall be made. Pick up vans/small
trucks shall be provided to all Sectional SSE/ JE (P. Way), so that they
are in position to move men and material to the site as per requirement.
For sustaining higher speed and axle loads, weak track formation will
require to be strengthened. For rehabilitation of present 2000 km
(approx.) of weak formation, formation rehabilitation machine shall be
deployed.
5.12.1 The design of end unloading rakes for transportation of welded panels
shall be improved for higher speed and better unloading system, so
that there is no gap between unloaded panels. These rakes should be
capable of transporting 260/520 m long panels. Adequate number of
improved rakes shall be arranged, so that only long panels are
supplied from Bhilai Steel Plant (BSP) to minimize site welding.
5.12.2 The design of hopper wagons shall be improved for automated
controlled discharge system. Required number of hoppers shall be
procured, so that efficient inter railway movement of ballast from Mega
depots is possible.
x
5.12.3 In order to ensure availability of proper quality of hard stone ballast,
Mega Ballast depots shall be setup and inter railway movements of
Ballast shall be organized.
6.1.1 Training center for training of trackmen, gatemen, keymen and P-way
mates in each division.
6.1.2 Training center for training of JE/P-way, SSE/P-way for each zone. The
Zonal Training Center (ZTC) shall also have training modules for
training of artisans/ operators of small track machines in association
with OEMs/ ITIs etc.
6.1.3 Requisite training to trainers to upgrade their knowledge and skills at
newly developed IRICEN Track Training Institute. At least three more
such other centers shall be developed.
6.1.4 The facility of Training for AT welding at TPP Lucknow and at
Vijayawada to be augmented to cater to the need of approx. eight
zonal railways at each centre.
6.1.5 Augmentation of infrastructure of Non-Destructive Technique (NDT)
Training center with M&C directorate of RDSO, to ensure that all
SSE/JE P-way have knowledge of checking the work of USFD
operators and adequate pool of trained USFD operators with each
railway
xi
6.3 Developing Centre of excellence in Railway Technology:
6.3.2 The MoU in following priority areas shall be considered with reputed
global research organizations:
a) Development of capability for design of target rail profile and
grinding patterns.
b) Development of simulation technique to verify suitability of track
components e.g. sleeper, fastenings for given combination of
speed, axle load, operating conditions, etc.
c) Development of suitable code of practice for continuation of long
welded rails on bridges on pattern of UIC leaflet.
d) Development of computer simulation for stability of long welded
rails at critical locations such as sharp curves, steep gradients,
etc..
6.3.3 There is also need to develop core competence at RDSO in
instrumentation, measurement and analysis of loading/forces in track
due to various operational conditions for design improvements of P-
way components.
xii
7.2 Outsourcing of Maintenance activities:
xiii
Chapter 1
Background
1.0 Introduction
1.1 Indian Railways, the premier transport organization of the country, is the
largest rail network in Asia and the second largest rail network in the
world with 64,952 route kms and 1,10,966 total track km as on 01.04.13.
It plays a crucial role in the development and operation of infrastructure
sector such as coal, power, steel, cement and other critical sectors. In
order to meet the increased traffic demands, Indian Railways have gone
for technology intensive modernization initiatives, which have enabled it
to sustain traffic demand on existing network without much addition to
fixed infrastructure. The total track kms of Indian Railways network has
grown from 77,609 kms in 1950-51 to 110966 Km. in 2011-12, which is
an increase of only 43%, while the increase in the level of traffic in
corresponding period has been more than 15 times. NTKMs per running
track kms in this period have increased from 1.47 to 8.34 and GTKMs
per running track kms have increased from 5.484 in 1950-51 to 24.51 in
2011-12. Total revenue earning freight traffic carried increased to 1010
Million Tonnes (MT) in 2012-13 from 73 Million Tonnes (MT) in 1950-51.
The increase in freight traffic has been sharp during the last decade
since 2000-01 i.e. from 504 MT in 2000-01 to 1010 MT in 2012-13. This
has been feasible by overstressing the track to certain extent by
permitting increase in axle loads. The permitted Axle load for freight
trains, which was 20.32T prior to 2005 has been increased in 2005 to
22.82T initially as a Pilot Project and now been rounded off to 22.90T
and extended on a track length of 35,000 kms (approximately).
1
Year Traffic Output Running GTKMs per Traffic
Freight Passenger Route Track running Carried
Traffic Traffic (Non-Kms Kms track km (Million
(NTKMs) suburban (Absolute Tonnes)
Passenger figure)
Kms)
1970-71 289 159 112 121 10.24 167.90
1.3 Even though, IR has been able to carry the traffic successfully by
overstretching the resources, Indian Railways suffer from acute capacity
constraints both in goods and passenger transport. With increased
demand on infrastructure, the maintenance blocks have drastically
reduced, seriously affecting the maintenance of infrastructure. This is
likely to be further affected with projected increase in traffic demands. As
per the IR Vision 2020 Document, the traffic is expected to increase by
10% annually and the projection of traffic at the end of this decade i.e by
2019-20 is given in Table-2 as under:
Table-2
Projected Traffic Demand on Indian Railways
Year Projected Traffic in
Million tons
2019-20 2165
2018-19 1968
2017-18 1789
2016-17 1627
2015-16 1479
2014-15 1344
2013-14 1222
2012-13 1111
2011-12 1010
2.1 The first phase of track modernization started in early 80‟s of the last
century. Prior to 1980, most of the track on broad gauge was laid with
90R/52 Kg, 72 UTS rails mostly welded into short welded rail panels on
wooden, CST-9 and ST sleepers. The Modernization of Track was
necessitated primarily due to introduction of CASNUB bogies for freight
wagons in early 80s. These bogies used in BOXN wagons were having
greater unsprung mass, as such were severe to track. Other factors
necessitating the modernization of track were increased traffic density,
increase in train speeds, gradual non availability of wooden sleepers etc.
This phase witnessed the development of PSC sleepers for all feasible
locations such as Plain Track, Turnouts, Level crossings, SEJs, Bridge
approaches etc. The Heavier section of Rails viz. 52 Kg/m and 60 Kg/m
with increased UTS (90 UTS) were introduced. Use of heavier track and
development of welding technology facilitated the laying of continuously
welded rails at majority of locations. The heavier track structure was not
suitable for manual maintenance; leading to introduction of On Track
Maintenance machines, which has improved the maintenance.
Infrastructure including track & bridges could withstand the increased
axle loads and speeds due to heavier track structure with 52kg/60kg
rails and PSC sleepers laid during this phase of modernization.
3
(i) More than 98% of Broad Gauge track is laid with 52 kg 90 UTS
and 60 kg 90 UTS rails on PSC sleepers.
(ii) About 88% track is laid with LWR (Long Welded Rails) and 11%
with SWR (Short Welded Rails).
(iii) Out of total 88200 turn outs, 77216 (87.55%) have been laid on
PSC sleepers.
Track renewal activities of points and crossing renewal and plain track
renewal has been mechanized by inducting T-28, PQRS and TRT
machines.
4
Table-3
Holding of Important Track Machines
Traffic block availability for other machines like BCM, SBCM, PQRS and
TRT has also been in the range of 44% to 70% of the demanded block.
5
duration of four hours in one spell or two and a half hour each in two
spells as laid down by the Railway Board for the proper functioning of
different track machines.
Table-5
Accidents on Engineering Account
4.1.3 As can be seen from Table-5 above, the percentage of accidents due to
rail fractures has increased substantially in the last few years. The
analysis indicates that increase in Rail/weld failures are primarily due to
corrosion of rails and increased axle loads. On Indian Railways the
excreta from the toilets is discharged directly on the track, which is the
main cause of the corrosion in rails as well as fastening system. This
6
combined with the heavier axle loads (22.9 ton) has resulted in
increased fractures. Indian Railways are replacing more than 400 kms of
rails every year due to corrosion and an equal length (more than 400
kms) due to rail fractures, which is also primarily the result of corrosion
of rail/track components, as can be seen from Table-6 below:
Table-6
Rail Renewals Sanctioned on account of Corrosion and Rail
Fracture
This has also reduced the maintenance cost of track considerably. The
share of P-way maintenance in total operating cost has come down to
7.82% in 2011-12 from 34.61% in 1975-76.
5.1 After the first phase of modernization, which consisted use of Higher
UTS Rails, PSC sleepers, long welded Rails and Machine maintenance,
the concentrated effort for further modernization has been missing.
7
Although the developments have been done in field of points &
crossings, improved diagnostic tools, AT welding technique etc., these
have not been completely amalgamated in the system. The need of hour
is to make a blue print for further action so that future needs of higher
speed and increased loads are met with without sacrificing safety.
8
vii) Shri Laxmi Narayana, CTE/SCR
viii) Shri Pradeep Kumar Garg, Sr. Professor/IRICEN (Now
CE/G/CR)
ix) Shri S. K. Aggarwal, ED/RVNL (Now ED/B&S/Railway Board)
9
Chapter 2
Track Structure
1.0 Introduction:
1.1 The permanent way of Indian Railway is catering to present day traffic
needs with certain limitation such as restricted speed of operation for
heavier axle loads, increased maintenance inputs etc. and minor
improvements affected. The PSC sleepers designed in 1977-78 primarily
on consideration of rail seat load of 15 ton have served for even
enhanced present day axle loads. The UTS of Rails have been
increased to 90 UTS from 72 UTS and sleeper density have been
increased from 1540 No./Km to 1660 No./Km.
1.2 The present stipulations about main line track structure on Broad Gauge
track are as under:
1.2.1 Rails:
60 Kg (Min UTS as 90) for all Track renewals, Doublings and All Gauge
conversions & New Line construction works.
(52 Kg rails can be used for Gauge Conversion & New Line
constructions having annual GMT less than 5 and not defined as mineral
route).
1.2.2 Sleepers:
1.2.3 Ballast:
1.3 At present, IR is operating freight trains with 22.9t axle load at speed of
60-75 Kmph and passenger trains at speed of 120-130 Kmph. Wagons
for 25/32.5 t axle loads with speed potential in excess of 100 Kmph are
already under development. Development of locomotives and coaches
with speed potential upto 200 kmph is also in progress. As such,
operation of freight trains with 25t axle load at 100 Kmph and passenger
trains at speed upto 200 kmph is foreseeable in near future. To
streamline the efforts and realize the full benefit of developments in field
10
of rolling stocks, track structure also needs up gradation to meet above
operational requirements.
1.4 The track structure will have to be improved in order to meet the future
traffic demands and scenario. The challenges of future requirements
which need to be overcome are as under:
1.4.1 Sustaining the operation of higher axle loads and speeds envisaged for
future on regular basis
1.5 The long welded rails have distinct advantage of reduced maintenance
effort of track and reduced fuel consumption due to smooth riding.
Continuation of LWR through all locations is required as part of
modernization effort. The design of PSC sleepers and fastening system
will require a relook to have increased resistance of track in line with that
used on advanced Railway systems.
1.6 Indian Railway system is operating mixed traffic. As such, the demand
for freight operations and passenger operations both have to be kept in
view.
1.7 With above broad objectives in view, the up gradation required for track
components and track structure is detailed in following paras.
2.0 Formation:
11
2.2 Stable formation is pre requisite for heavy axle load as well as for higher
speed operations.
2.2.1 For heavy axle load (25t to 32.5t) and speed potential upto 160kmph, all
new construction should be based on the document “Guidelines and
Specifications for Design of Formation for Heavy Axle Load Report No.
RDSO/2007/GE: G-0014 November 2009”.These Guidelines are
approved by Railway Board based on the recommendations of a HAG
level committee. The design of formation is based on the basic
consideration that the maximum pressure on formation at bottom of
ballast should not exceed 3 Kg/sq.cm and the pressure on sub-soil
should not exceed 1 Kg/sq.cm.
2.2.2 For speed higher than 160kmph, detailed study of the formation soil
behavior in regard to Rayleigh Waves generation including its effect over
the depth of formation/soil structure and consequential resonance
phenomena has to be taken up, to eliminate possibilities of future speed
restrictions and damage to structures/buildings in surrounding areas of
the rail corridor. The necessary study in this regard shall be undertaken
by RDSO.
2.3 As such, for new constructions, minimum 30cm blanket (for 25T axle
load) over a prepared subgrade of SQ3 type of soil having CBR value
not less than 7, shall be provided and formation shall be well compacted.
The thickness of blanket may vary upto 100cm, depending upon type of
soil used in the formation and the axle load. The formation width of 7.85
m in single line and 13.16 m in double line as already approved by
Railway Board shall be provided.
3.2 The ballast is the medium to disperse the load on formation. Higher
ballast cushion is desirable for better dispersion of load resulting in
reduced formation pressure. Studies done indicate that with further
increase in ballast cushion, its retention in position & packing is a
problem, thereby increasing the maintenance inputs. As such, the ballast
cushion of 350 mm as prevalent now is optimum and shall be continued.
3.3 The Quality of ballast is an issue. Hard stone ballast has properties of
lesser degradation and pulverization during machine tamping. Good
12
quality stone ballast is available only in limited reaches. However, in
recent times a lot of restrictions are being put on mining of ballast by
state governments due to environmental concerns. As such, to ensure
good quality ballast, setting up of Mega Ballast Depots will have to be
resorted to along with arranging the inter-Railway ballast movement.
4.1 As per existing stipulations, PSC sleepers with minimum sleeper density
as 1660 nos. per km are to be used for all Track Renewals, Doubling,
Gauge Conversion and New Line construction works.
4.2 The sleeper density has effect on formation pressure, longitudinal and
lateral ballast resistance and rail stresses. Studies on longitudinal ballast
resistance indicate that optimal values are obtained with sleeper density
of 1660 No./Km & further increase in sleeper density does not result in
any increase in the values of LBR. The ballast surface and sub grade
surface stresses remain more or less constant for sleeper density of
13
1540 to 1818 No per km. There is relief of max. about 1 kg/mm2 in rail
stresses with increase in sleeper density from 1540 to 1660 nos per km.
4.3 The existing design of PSC sleepers has served the present traffic
needs satisfactorily. However, the design needs review particularly on
following accounts:
4.3.1 The rail seat area is small, resulting in small plan area thus size of
GRSP. This has been one of the major factors for poor in service
performance of rubber pads. There is need to increase Rail seat area to
cater to requirements of future traffic needs.
4.3.2 The increased rail seat area and bottom width would help in reducing
pressure on the ballast further helping in improving the rate of ballast
degradation and improvement in deep screening cycle. A wider sleeper
with proper shape & design with heavier mass is likely to significantly
add to longitudinal and lateral resistance of track enhancing
maintainability in LWR track.
4.3.3 The Track frame resistance, a vital parameter for stability of Long
Welded Rails, need to be improved. This can be improved significantly
by sleeper with wider base.
4.3.4 The size and shape of sleepers will be limited and governed by the
tamping bank of existing track machines, as huge investment in
modification/procurement of new track machines is not considered
prudent.
4.4 The size of PSC sleeper used on other World Railways is tabulated in
Table-1 as under:
14
Table-1
4.5 In order to achieve the prime objective of increased plan area for GRSP
and LBR/ track frame resistance, following action is to be taken:
4.5.1 Keeping in view the limits imposed by existing tamping bank of tie-
tamping machines, tentative top width at rail seat as 210-230 mm and
bottom width as 265-275 mm is possible. With these limiting dimensions,
design of PSC sleeper with use of 3 mm x3 wires to have a wider and
heavier sleeper has already been initiated by RDSO. The issue of
permitting further higher bottom width is being examined by TM Dte of
RDSO with Plasser (India) and suitable design modifications would be
carried out if possibility of permitting width higher than 275 mm is found.
15
4.6 There is no likelihood of major cost increase, as increase in concrete will
be offset by suitable reduction is reinforcement. The added advantage
will accrue once wider & heavier sleepers are used in track by way of
use of long welded rails having reduced maintenance cost and fuel
consumption. The possible reduction in destressing temperature due to
increased frame resistance may result in reduction in rail/weld fractures.
(i) Loss of toe load in service, getting toe load in the range of 600-
900 kgf rather than design toe load of 850-1100 kgf. This may be
on several accounts e.g. missing liners, crushing of pad, rail foot
corrosion, manufacturing tolerance adding on adverse side, etc.
(ii) Short life of rail pad.
(iii) Seizure of clips particularly on platforms lines.
5.2 A number of measures have been taken to address the above problem
e.g. design of higher toe load ERC Mk-V (with toe load range of 1200-
1500 kgf), design of 6.2 mm composite rubber pad (CGRSP) which has
been adopted by Railway Board after successful trial reports and
reportedly performing better than 6 mm GRSP). Trials for improvement
of liners are also under progress for having better service life. For
preventing seizure of clips, oval shape insert has been designed and the
same shall be used with the proposed new sleeper design.
5.3 With the proposed use of wider and heavier sleepers, the fastening
system may further require change. While designing the fastening
system, following broad guide lines should be adhered to:
(i) Fastenings system should be such that it does not loose its initial
toe load during service appreciably.
(ii) Minimum thickness of rail pad: 10 mm of larger area over rail seat
(iii) Reduced tolerances in fastening components so that tolerances
adding on adverse side do not result into significant toe load loss.
(iv) Wider size of liner, preferably with improved material to reduce
incidence of breakage during its use in field.
5.4 Further, the regime of fastening procurement system also needs review.
The system of tolerance of individual components shall give way to
overall tolerances in complete fastening system. The complete fastening
system should be procured as one unit with strict performance criteria
rather than individual components.
16
5.5 With above fastening system, the continuation of LWR will be possible,
giving substantial advantage of reduced maintenance, better reliability
and reduced fuel consumption. The increase in cost of fastening system
will be offset with added advantages indicated above.
6.0 Rails:
6.1 As per existing stipulations, 60Kg 90 UTS rails are to be used on Broad
Gauge track. These rails have been considered suitable for operation of
CC+8+2 (22.8t) freight trains at restricted speeds of 60/75 kmph with
marginal overstressing. However, for operation of 25t axle loads, the
section of rail needs to be increased to avoid overstressing of rails. The
sample rail stress calculations for 25t axle load at different speeds
indicate that 60 kg rail section will not be adequate. The detailed
calculations are enclosed as Annexure-„A‟. The status is summarized in
Table-2 below:
Table-2
Rail stresses due to bending for 25t axle load
Rail Stress Due to Bending (kg/mm2)
Rail &
Permi 60 kmph 75 kmph 100 kmph
Sleeper
ssible Foot Foot Foot Foot Foot Foot
Density Stress (Centre) (Edge) (Centre) (Edge) (Centre) (Edge)
60KG 90UTS 46.8 48.16 40.33 49.08 41.25 50.82 42.99
1540
60KG 90UTS 46.8 47.84 38.85 48.73 39.73 50.43 41.44
1660
60KG 110UTS 57.2 48.88 39.89 49.77 40.78 51.47 42.48
1660
68KG 90UTS 46.8 46.27 37.95 46.73 38.41 48.13 39.81
1540
68KG 90UTS 46.8 45.74 36.49 46.51 37.26 47.95 38.70
1660
75
70
65
60
55
50
17
45
10 15 20 25 30 35
Axleload (t)
Relationship between axleload and rail hardness
(tangent track)
450
Rail Hardness
400
(HBN)
350
300
250
200
10 15 20 25 30 35
Axleload (t)
2. „Impacts of Heavy Axle Loads on Light Density Lines in the state of Washington, chapter-3, Final Report,
February-2001
18
6.4 Based on available studies, it is noted that use of heavier rail section has
following advantages:
6.4.1 The service life of rail in terms of GMT is expected to be more and it is
proportional to (UTS)2 and (Section weight)3.
6.4.3 Lighter rails are not suitable for heavy axle loads at higher speeds, as
rails get overstressed and fatigue life of rails gets reduced. AREMA has
recommended 68 Kg/m or 71 Kg/m rails for heavy axle load/ heavy
haul operations.
6.4.4 ORE reports suggest that a stiffer rail maintains its alignment better
and is subjected to less vibrations and dynamic augment, as a result of
3
which cost of maintenance reduces . Vertical settlement also reduces
4
with increase in vertical inertia of rails . ORE report in one case found
that when axle load is increased by 10%, maintenance cycle gets
4
reduced by 30%, thereby increasing the maintenance cost .
3. ORE Question D-117, Optimum Adoption of conventional Track to future Traffic Sept. 1983.
4. ORE Question D-141, Effect on Track of Raising Axle Load from 20t to 22t, Oct.-1979
6.4.5 The experience on IR after the increase of axle load suggests that
maintenance requirement gets enhanced with increased axle loads.
Increase in instances of rail/weld failures after introduction of increased
axle loads confirms the need for increasing the rail section.
6.4.6 Studies on fuel consumption on track with 90R and 52 kg rails suggest
that for operating speed of 75 kmph, fuel consumption on 52 kg rails is
1
8.41% less than 90 R rails .
1. K.P.Singh & R.P.Agrawal, Heavier Rail section for reducing maintenance cost, IPWE(I) Journal, Vol.XIII.
No. 3, December 1994.
6.5 Thus, there is need to increase the rail section. Suitable rail sections
available internationally can be adopted. Out of various options available
for 68Kg/m rail, section 136RE, used by AREMA is most commonly used
and produced and therefore, it may be preferable to use this rail section,
to ensure availability of producers of this section globally. The
comparison of properties of UIC 60 kg rail section & 136RE are as under:
19
Dimensions Unit UIC 60 136 RE
Section Weight Kg/m 60.00 67.42
Rail Height mm 172.00 187.74
Foot Width mm 150.00 152.40
Head Width mm 72.00 74.61
Area mm2 7686.00 8588.00
Ixx cm4 3055.00 3917.00
Zxx cm3 335.00 387.00
Iyy cm4 512.90 600.00
Zyy cm3 68.40 79.00
This rail section can be used even on existing 60 kg PSC sleepers with
modified liner design as the difference between rail foot of 68kg (152.4
mm) and 60 kg (150 mm) rail is only 2.4 mm and the available rail seat
width is 162 mm on the existing design of sleeper.
6.6 In order to cater to the higher axle loads, use of rails with higher UTS is
also required. Higher UTS rails have problem of reduced ductility & are
susceptible to sudden failure. The 110 UTS rail being developed on IR
has 9% elongation. The ductility has to be improved to prevent chances
of sudden failure.
6.7 The existing 90 UTS rails suffer from drawbacks mainly being brittle in
nature, high residual stress and inadequate corrosion resistant
properties.
6.7.1 The 72 UTS rails used earlier were had 14% elongation and sudden
fractures were very less. 90 UTS rail has 10% elongation. This needs to
be improved by suitable micro-alloying the rails.
20
elongation and CRI of 1.5 (keeping CRI of 1.0 for existing rails) is likely
to serve the purpose.
6.8 With increased axle loads, the contact stresses will increase, resulting in
more rolling contact fatigue. The contact stresses is of the order of 22.32
kg/mm2 for 25t axle load. With section having continuous operation of 25
t axle loads, the head hardened rails with permissible shear stress of 33
kg/mm2 shall be required. For other sections, the rail grinding shall be
adequate for tackling the RCF problems on 90 UTS Rails.
6.9 Apart from routes having continuous operation of 25 t axle loads, the
Head Hardened (HH) rails will also be required for special locations such
as sharp curves & steep gradients. In this connection, the
recommendations of best practices in Heavy Haul can be considered as
under:
Above table indicates that head hardened rails are recommended on all
curves on routes having traffic over 50 MGT and on routes with traffic 10
to 50 MGT, head hardened rails are recommended for curves of
sharpness more than 1.50.
21
unloaded in continuity without any gap and need for drilling holes is
eliminated.
6.12 Thus, for new constructions, track renewals and gauge conversion
works, 68 kg 90 UTS rails with improved ductility and corrosion
properties shall be used. On predominantly freight traffic lines and on
curves sharper than 1.50 and gradients steeper than 1 in 100, 68 kg
head hardened rails shall be used. The rolling of 130 m long rails with
reduced residual stress (less than 10 kg/mm2) shall be ensured, so that
optimal utilization of rail is ensured.
6.13 Use of 68 Kg rails will increase the cost marginally, due to marginal
increase in sectional weight. But this is unavoidable considering the
strength of rails required for 25T axle load. This will be offset easily with
the reduction in maintenance effort and fuel reduction.
7.1 At present, IR is using 260 m long flash butt welded panels with site
welding done mostly by AT Welding. The 260 m long panels are having
3 to 9 flash butt welds depending upon length of rails welded. The weld
whether AT or FBW is a weak link. As such reduction in number of welds
will add to safety & reliability to system.
7.2 The supply of long rails (rolled rail length of 130m) will substantially
reduce the quantum of welding. With facility of transporting 520 m rail
panels, the requirement of site welds will further reduce.
7.3 The quality of AT welds depends much on welder, site conditions such
as availability of traffic blocks etc. The consistency of quality of AT welds
has been a cause of concern on IR, as rate of failures of AT welds is
higher. The flash butt welds are more reliable. As such all planned
welding works at site shall be done using Mobile Flash Butt welding
Plants. For new construction/planned renewals, only flash butt welds
shall be allowed.
7.4 The casual welding/repair weld shall also be done by the mobile flash
butt welding plants. As already decided, the procurement of Mobile
Flash Butt Welding Plants one on each railways needs to be expedited.
The specification of MBFW being developed by RDSO shall also include
the super puller to make machines capable of repair welds. One
MBFWP will however be not adequate to meet the complete requirement
of casual/ repair welding of Zonal Railway, thus requiring some alternate
arrangement till requirement of casual welds get reduced by control on
rail/weld fractures.
22
7.5 The SKV welds are used on most of the world railways for repair welds.
The technique is capable of giving good quality welds if executed
properly and dependence on personal skill is minimized. With reduced
requirement of urgent repair welds, the better control can be exercised.
Considering the fact that on LWR track, severe SR will have to be
continued unless welding is done and one MBFW on each railway may
not be able to cope up the workload of urgent repair welds, IR will have
to continue with SKV welds for urgent repair welds as temporary
measure. However, for such urgent repair welds, only improved SKV
welding technique with compressed air pre-heating, three piece mould,
auto thimble and single shot crucible with automatic monitoring of critical
welding parameters such as preheating time, preheating temperature,
reaction time etc. shall be used. The improved AT weld technique has
already been developed except single shot crucible. The strength
parameters for SKV welds should also be reviewed and it should be
comparable with flash butt welds.
7.6 In order to reduce the number of in-situ repair welds, it will be better to
use wider gap welds (75 mm gap) in place of normal 25 mm gap SKV
welds. The existing technique of wider gap weld shall be improved to
have compressed air pre-heating, three piece mould, auto thimble and
single shot crucible with automatic monitoring of critical welding
parameters.
8.0 Turnouts:
8.1 At present, built-up curved switches and CMS crossings laid on PSC
sleepers are being used on IR. The turnout is the portion of track
subjected to maximum deterioration on account of high flange forces,
discontinuity in track and number of joints. Use of CMS crossing restricts
continuation of LWR through turnouts due to limitation on weldability.
The fabricated curved switches also have limitation on maintainability
and continuation of LWR.
8.2 The thick web switches have been developed long time back, but have
not been adopted in big way so far. Similar is the case with weldable
CMS crossings. The limitation of conventional turnouts is largely
addressed in thick web switches and weldable CMS crossings. The
continuation of LWR and sturdy design of switches will significantly
reduce the maintenance requirement and improve the reliability of asset.
As such, it shall be mandatory to use thick web switches and weldable
CMS crossings on all new constructions and planned renewals. This will
facilitate immediate continuation of long welded rails through turnouts.
23
8.3 The wear on other side of tongue rail due to improper setting of switches
is a major factor, which needs to be addressed. The spring setting
device has been effective in ensuring proper setting of switches, but the
reliability has been not satisfactory. As such, the spring setting device
shall be integral part of thick web switches. The design shall be
reviewed and proper design of SSD, which does not require extensive
maintenance, shall be provided.
8.4 The fastening system for turnouts shall be re-designed to address the
problem of working out of rubber pads in crossing area and other such
locations. The studies shall be done for actual forces coming in the
switch and crossing portion on IR tracks through instrumentation and re-
designing of components be done, as needed.
8.5 On high traffic density routes, explosive depth hardened crossing shall
be provided for increased service life due to reduced wear.
8.7 RDSO should also work on design and development of canted turnouts,
which will be required for use on high speed routes.
8.8 Thus, for new constructions and planned renewals, thick web switches
and weldable crossings should be used. LWR shall be continued
through turnouts using system advised by RDSO. The marginal increase
in cost due to above will be easily offset by increased service life and
reduced maintenance efforts.
9.1 Level crossings are major obstacle in smooth operations in traffic. The
provision of check rails to have flange way clearance for rolling stock
increases the maintenance efforts and put limitations at locations for
continuation of LWR. The situation is critical at locations where LC is
located at approach of stations, resulting in long length of unwelded
track. Elimination of LC shall be the ultimate aim.
9.3 Till such time, the LCs are eliminated, the arrangement at level crossing
needs review to provide system which does not require provision of
check rails for ensuring flange way clearance. The surfacing of existing
24
level crossing shall be re-designed and standardized so that there is no
requirement of check rails & resurfacing shall be possible immediately
after attention to level crossing without delay. This will also eliminate the
restriction of continuation of LWR at number of locations, where LC falls
in breathing length of LWR.
9.4 The system of fiber reinforced precast RCC blocks has been developed
and used on South Central Railway. This arrangement is considered to
meet the requirements. The details of the system along with comparison
of cost with existing arrangements are given in Annexure-B.
10.1.2 The improved SEJ designed & developed by RDSO addresses the
major issues of conventional SEJs. As such, this shall be standard SEJ
and conventional SEJ should be phased out. Further efforts should be
made to explore a switch expansion joint design that does not have
any discontinuity on running gauge face for reliable service life. For this
various designs used on advance railways systems should be studied.
10.1.4 Suitable arrangement for providing improved SEJ over bridge wherever
needed shall also be developed both for existing channel sleepers and
futuristic composite sleepers.
10.2.1 Glued insulated joints are required to be provided to meet the present
day signaling needs. These are introduced discontinuity in rail and are
not desirable for reliability of track. As such, there is serious need for
relook in design of signaling system to eliminate the need of GIJ. In
new construction (New Lines as well as Gauge Conversion), the
25
signaling system adopted should be such that there is no need for
glued insulated joint. On existing routes, with improvement/
modernization of signaling system, the glued insulated joint should be
gradually phased out.
10.2.2 Use of prefabricated glued joints requires minimum two additional site
welds at each location. As such, till such time the glued insulated joint
is required, feasibility shall be explored for use of in-situ GIJ. The
technique for in-situ manufacture of glued joint shall be developed and
standardized. This will require quick setting high strength glues to have
requisite strength in time normally available for manufacture. The
experience with poor quality of site welds indicates poor availability of
traffic blocks as major reason. As such, the system for in situ glued
joints shall be such that track is ready for use in maximum one hour
time. The in situ GIJ will reduce the number of site welds which are
weak link in track. The manufacturing methodology of glued insulated
joint shall be reviewed thoroughly to obtain consistency of in situ Glued
Joints for better in service reliability. After development of technique,
only in-situ glued joint shall be allowed.
10.2.3 Other types of insulated joints are also available, which use
prefabricated components in place of glue and provide requisite
properties as glued joints. Such systems shall be studied through trial
and if found successful shall be considered for standardization in place
of glued joints. This will address the issue of excessive requirement of
traffic blocks.
10.2.4 The fish plate of GIJ should be redesigned so that it can accommodate
grip rollers of the tamping machines.
10.3.1.2 The composite sleepers have performed well in trials and are
proper replacement of bridge timbers due to inherent advantage of
ease in use and inbuilt resilience. The composite sleeper shall be
standardized for use on steel girder bridges and shall be the bridge
sleeper for track.
26
10.3.1.3 The suitable fastening system having zero toe load and
adequate torsional resistance will be needed for continuation of long
welded rails over girder bridges. Such fastening systems shall be
designed and developed, which will be standard fastening for use with
composite sleepers.
The OHE bonds are fixed to track for return current, which require
drilling of holes in rails. Such holes are potential source of Rail
fractures. The rail used for return current is susceptible for more
corrosion. As such, suitable system shall be designed which does not
require drilling of holes in rails. Ideal system will be one where Rail is
not used for return current. RDSO shall device such system, which will
go a long way in improving the service life of rails.
Indian Railway track has open access to man and cattle, trespasses
being very common. The trespass on track seriously affects the track
maintenance due to frequent disturbance of ballast profile,
27
contamination of ballast & drainage. The track is also prone to
vandalism, affecting the reliability of systems installed on track. Cases
of cattle run over resulting into derailment of train are also not very
uncommon. Thus, the trespass needs to be strictly controlled for
effective train operation. The complete Broad Gauge network shall be
provided with suitable fencing/isolation system, with priority to sections
having speed of 110 kmph and above. This will also facilitate
implementation of the vision of Indian Railway to increase the speed of
passenger trains upto 200 kmph on existing network.
11.2.1 The existing bridges are not designed for forces which arise due to
continuation of LWR on account of track-bridge Interaction.
28
Railway Code of practice shall be developed on pattern of UIC leaflet
for checking existing bridges for continuation of LWR.
11.2.3 All New Constructions & Gauge Conversions shall have long welded
rails. The bridge design shall be done taking Track Bridge interaction
forces into account both for ballasted deck as well as Non-Ballasted
decks, so that they are fit for continuation of LWR. In case of any
deviation, specific approval from Railway Board shall be obtained.
11.3 Turnouts
11.3.1 The LWR can be continued through turnouts using thick web switches
and weldable CMS crossings with arrangements advised by RDSO.
11.3.2 All New Constructions & Gauge conversions shall have Long Welded
Rails continued through turnouts.
12.1.1 Rails:
12.1.2 Sleepers:
29
12.1.3 Fastening system:
12.1.4 Ballast:
12.1.6 Long Welded Rails with flash butt welds and improved switch
expansion Joints.
12.1.7 Turnouts:
Thick web switches with improved SSD and weldable CMS crossings.
12.3 The design of end unloading rakes for transportation of welded panels
shall be improved for higher speed and better unloading system, so
that there is no gap between panels and these rakes are capable of
transporting 260/520 m long panels. Adequate number of improved
rakes shall be arranged, so that only long panels are supplied from
BSP and site welding is minimized.
30
12.6 The design of all new bridges shall be done for track-bridge interaction
forces for long welded rails, so that there is no limitation on
continuation of LWR.
12.7 Composite sleepers shall be standardized as the bridge timber & shall
be used with proper fastening system for all new
constructions/renewals.
12.9 All new constructions shall have Long Welded Rails without any
exception. In case continuation of LWR is restricted on site conditions,
conscious decision be taken after detailed technical review.
31
Annexure-A
RAIL STRESS CALCULATIONS
Sheet-1
Rail stress for 25t Axle Load on 68kg (90 UTS) rail, 1540 Sleeper Density
25t Axle Load 68kg (90 UTS )Rail, 1540 Sleeper Density
60 kmph 75 kmph 100 kmph
2 Foot Foot Foot Foot Foot Foot
Rail Stresses (in kg/mm )
(Centre (Edge (Centre (Edge (Centr (Edge)
) ) ) ) e)
Stress Due to Bending 11.84 16.52 12.3 16.98 13.7 18.38
Residual Stress 19 6 19 6 19 6
Unforeseen Condition 4.68 4.68 4.68 4.68 4.68 4.68
Stress Due to Thermal Force 10.75 10.75 10.75 10.75 10.75 10.75
Total Stress 46.27 37.95 46.73 38.41 48.13 39.81
Permissible Stress 46.8 46.8 46.8 46.8 46.8 46.8
32
Sheet-2
Rail stress for 25t Axle Load on 68kg(90 UTS) Rail, 1660 Sleeper Density
33
Sheet-3
Rail stress for 25t Axle Load on 60kg (90 UTS )Rail, 1540 Sleeper Density
34
Sheet-4
Rail stress for 25t axle load on 60kg(90 UTS) rail, 1660 sleeper density
35
Sheet-5
Rail stress for 25t Axle Load on 60kg(110 UTS ) Rail, 1660 Sleeper Density
36
Annexure ‘B’
1.3 Thus, the need for suitable system on following is dealt in this section
1.3.1 Fencing along track to prevent trespassing.
1.3.2 Suitable road surface arrangement at level crossings.
1.3.3 Suitable design of ballastless track & washable aprons
2.1 On high-speed lines, trespassing is very risky. Even the train may
suffer accident and consequences of accidents can be alarming. It is
noticed from the experience of high speed corridors world around that
at very high speeds, track ballast stones sometimes fly off and hits the
surroundings. To avoid such incidences, track fencing is required to be
provided. Thus, the entire high-speed track is provided with fencing. In
any case, areas prone to trespassing have to be provided with fencing
on high-speed routes.
37
2.1.2 Unauthorized pedestrians, cattle and light vehicles crossings poses
bigger challenge to high speed train operation in Indian socio-cultural
scenario. Less reaction time and heavier impact on high speed train of
collision, prevents permitting higher speed beyond 110 kmph without
taking adequate precautions.
2.1.3 It is also necessary that boundary wall is made in sufficiently longer
patches much beyond the zone of habitation with impermeable sealing
at level crossings and all possible entry points. Steel chain link fencing
at most critical location in track vicinity and security patrolling needs to
be tried selectively in addition to the boundary wall at railway boundary.
2.1.4 Alternatively, railway land at such trespassing prone stretches can be
leased to commercial establishments with condition of erecting
effective fencing and providing watch ward staff as a cost effective
solution.
2.2 Different types of fences exist in the market. Provision of fencing for
Indian conditions is very costly. However, in view of safety for high
speed train service, punctuality and un-interrupted traffic, fencing on
both sides is highly essential. The minimum height of 5 feet is required.
The following types of fencing can be adopted.
38
Pro-Mesh Mesh Panel Fence
Concrete post and chain weld mesh panel varies of different size from
2.6 m to 3.2 m length and height also varies from 1.8 m to 2.4 m.
There are intermediate posts and straining posts and strut and cost of
the same also varies depending on the size and height.
39
2.5 Bow Top Railings
Bow top fencing is another traditional
style. Attractive as ornamental
railings, bow top fencing can also
provide a reasonable security solution
for certain sites and provided the
height is sufficient. Bow Top Fencing
2.7.1 Out of above fencings, „Pro-Mesh‟ profiled mesh fencing panels are
considered suitable for Railway fencing where the execution and
erection is easier than the others. Also this is cost effective and
cheaper as is evident from following:
40
2.7.2 In non-urban area, the concrete post for Chain Link Weld mesh will be
suitable. In metros, the masonry wall with 1.5 m height is desirable and
cost effective.
3.0 Surfacing at Level Crossings:
FRP blocks have been designed for provision at manned and unmanned
level crossing gates to get better surface than the conventional roads.
These FRP blocks will facilitate the maintenance of level crossings more
easily than the conventional type. Removal and re-fixing of FRP blocks is
easier since it has got the provision of lifting hooks on both sides. This
also facilitates the tamping of track at regular interval by removing the
blocks without damaging the road surface restored back after planned
maintenance. It avoids corrosion and damage to the track components, it
avoids the drilling of holes in the running rail thereby increases the service
life. The road surface achieved is aesthetically pleasing, does not require
any maintenance and well appreciated by the public. A drawing has been
developed by SCR, which can be adopted.
3.2 Comparison of the cost per / sqm for different types of LC surface:
41
Fibre Reinforced Precast RCC Blocks on LC.
4.1.1 Washable aprons 52 kg/60 kg. for 30 kmph speed with LWR using
RCC slab foundation :
4.1.2 Washable Aprons for 130 kmph speed with L.W.R. using RCC slab
foundation – RHEDA
42
Item/ Feature Conventional apron RHEDA 2000 apron
(RDSO/T-4781)
A. Design No bond between sleeper 1.Two steel lattice girders are protruding
1.Bond and surrounding concrete. from precast sleeper block into concrete
Epoxy and bitumen used as apron
bonding 2.RHEDA 2000 sleepers are of bi-block
type and they are integral parts of the
monolithic RCC structure
1. Speed Up to 30 kmph 100 kmph
2.Material Concrete, regular track Special sleepers and special fastenings
sleepers & fastenings
3.technnology Conventional; based on Modern; (Vossloh 300)
experience
C. Functional
1.Track Rigid Flexible, can be adjusted
geometry
2.Retension of Deteriorates with time Not much deterioration is observed as the
track sleepers are bi-block type, represent
parameters integral part of monolithic RCC structure.
Breaking, spalling in central portion or
opening gaps along slipper is prevented.
Hence, a sound structure is retained.
3.Drainage Good Very good
4.2 Washable Aprons with LWR using partly cast rail seat beam
(PCRSB), designed by RDSO:
43
The provision of RCC/CC apron in the yards avoids the contamination
and keeps the premises clean and maintains hygienic condition. The
area is easily washable where the night soil drops. It replaces the manual
cleaning of platforms by semi-mechanical means also facilitating ease in
drainage arrangements and watering of the trains. The ballastless track
also permits continuation of LWR in the station yards improving
maintainability of track.
So far, there has not been any indigenous design which could serve the
purpose of apron, having the added advantage of stability, durability and
speed potential of main line which facilitates running of goods trains
without any damage to the permanent way. Rheda-2000, which is a
patented design, has been used at certain locations having some of the
above mentioned features. Recently RDSO has designed a system with
the use of partly cast rail seat beam (PCRSB), which is to be cast in
concrete sleeper plant, with indigenous fastenings, suitable to be used as
washable apron on platform lines with sectional speeds upto 110 kmph.
The design is based on the successful results of two trials by Central
Railway, one in 2006 at Pune station (Platform no. 5) and other in 2007 at
Mumbai CST main line Platform no. 18 with further improvement done by
RDSO. Railway Board has already approved the design for trial vide letter
No. 2011/Proj/9/2 dtd. 7.10.2013.
44
This design would be used for future construction of washable aprons as
due to use of indigenous fastening system, it is considered to be costing
lesser in the long run due to increased maintenance ease, ready
availability of fastening components for maintenance, and supporting
higher speeds on platform lines (wherever the yard configuration permits
it) etc.
45
Chapter 3
1.3 The availability of diagnostic aids for condition monitoring of track has
also aided to reduce the need of manual inspection. The type of defects
in track which were prevalent in earlier day track structure such as
gauge spread, low joints, poor alignment etc. are no longer prevalent on
46
IR. New type of defects such as RCF defects, rail/weld fractures, track
buckling etc. are now prevalent with increased traffic density and need to
be taken care of for safe and reliable track.
1.4 At present, manual inspections are being done at all levels (JE, SSE,
AEN, DEN/Sr.DEN). JE & SSE are also responsible P-way supervisors
to get the defects attended. As such, these P-way supervisors get the
list of short comings noted during inspections at various tiers based on
manual inspection inputs and some of the recordings done. These
shortcomings are to be attended by SSE/P-way & JE/P-way, who also
have their own scheduled inspections. Thus, the present system is more
inspection oriented and emphasis on compliance has been found
lacking. Inspections are useful only if the compliance is done. As such,
there shall be more stress on compliance. Whatever systemic changes
are required for proper compliance shall be brought into focus.
2.1 For modern track structure, the suitable system of track maintenance will
be 3 tier maintenance system comprising of following:
47
Tier 3 - Sectional Gangs
2.2 The present system of inspection and maintenance of track has one
SSE/P-way incharge of unit assisted by two or more JE/P-way. The
sectional gangs are headed by P-way Mate. Over one or two P-way
gangs, there are Sr. P-way supervisors, who report to JE/P-way. There
has been major restructuring in supervisory staff for P-way. The existing
cadre of Sr. P-way Supervisor has been merged with JE/P-way. The
ratio of JE/P-way and SSE/P-way has also been altered. The category of
Mate/Keyman/Trackman has also been restructured. Thus, the proposed
structure shall also take these changes into consideration.
2.3 In the present system, SSE and JE are mostly engaged in inspections
and arranging resources for machines, with very limited time for analysis
of data for prioritization of activities and actual compliance. In the
proposed system, it is considered that one SSE/P-way/ special works
shall be provided under SSE/P-way/Incharge in addition to sectional
SSE. SSE/SW will be assigned the responsibilities mostly relating to
analysis of track measurement data and works on OMU. SSE/Section
will be responsible for works of sectional gangs and MMU as per existing
duties. However, there will be an overlap of sectional gang and MMU
activities between the SSE/section and SSE/SW and the resources will
be shared by both as per the requirement. Broad planning for sharing of
resources will be done by SSE/Incharge. Thus, the SSE/P-way incharge
having section of about 80-100 Km on single line or 40-50 km on double
line section will be assisted by two or more SSE/P-way/section and one
SSE/P-way/SW (special works). The duties and responsibilities of
SSE/Incharge and SSE/Section will be broadly the same as stipulated in
IRPWM with rationalized schedule of inspection as required for modern
track structures.
2.4 The basic structure of sectional gangs shall be retained. P-way mates,
who are in-charge of sectional gangs having 5-10 Km track, are well
conversant with their sections. IRPWM lays down various responsibilities
of mates, therefore, this authority to be kept as it is and not to be diluted.
Keyman is responsible for daily inspection of track, as such essential to
be retained. As such, there will not be any change in status and duties of
Mate and Keyman. Mate & Keyman will be in the same grade and will
be designated as Track Maintainer-I.
48
2.5 As the category of PWS has been abolished, P-way units (consisting of
one or two sectional gangs) will now be headed by JE/P.Way, who will
carry out the duties and responsibilities of Sr.PWS with further
rationalization as required.
2.7 The system of independent quality audit of work done at field level is
lacking in the present system. It is considered that such system shall be
introduced with suitable set up at Divisional level. As such, Sr.DEN/DEN
will be assisted by SSE/P-way/QC (Quality Control). SSE/P-way/QC will
exercise quality checks of all P-way maintenance works & renewal
works in the jurisdiction of Sr.DEN/DEN.
3.1 The inspection and maintenance regime for modern heavier machine
maintained track equipped with diagnostic aids will require thorough
review. With the proposed diagnostic tools in place, the requirement of
manual system shall reduce to a great extent. The manual inspections
will be limited to items where mechanized inspection systems are not
49
available at present. Manual inspections will be mostly need based
detailed inspection to get to the root cause of the problem. Thus the
manual inspection schedule shall be reviewed to limit the periodic
inspections. The items as well as frequency of inspections at various
levels shall be critically reviewed.
All the above inspections are skilled inspections and will be carried out
at the supervisors level (except item no. x above) with the help of 3-4
Track Maintainers. The supervisors will have light weight self propelled
vehicle to improve his mobility.
50
measurement system has been proposed for procurement by RDSO in
the WP of 2014-15.
State of the art track geometry cars are available to measure the
following parameters during the run:
Track Geometry
Car body acceleration
Rail component video monitoring system (rail surface, fastenings,
concrete sleepers condition)
Rail profile measurement
Corrugation measurement
Axle box acceleration measurement
Clearance measuring system
All above measurements can be taken in one run, thereby avoiding the
need for multiple running of various vehicles and eliminating the
subjectivity involved in manual measurements.
51
2. Full rail profile measurement will be helpful in assessing status of rail
inclination, gauge, lateral, vertical & angular wear of rails and condition
of rail-wheel interaction. The rate of wear can be worked out and
appropriate measures can be taken to arrest the excessive wear rate.
This will also be useful for planning the rail renewal and rail grinding.
3. Corrugation measuring system will be helpful in effective depth of cut
selection during rail grinding to remove the corrugations on the rail.
4. Axle box acceleration will be helpful for identification of short
wavelength track defects viz. loose packing, low joints, cupped welds,
corrugations etc.
5. Clearance measuring system shall ensure the minimum required
clearances as per SOD by taking timely action and thus prevent
untoward incidents due to infringements.
In future, Indian Railways should procure state of the art track recording
cars capable of measuring all the above parameters.
4.2.2 The coach for acceleration measurements should also be provided with
rail component video monitoring system and clearance measuring
system. With the problem of inspections by trolley due to trains running
at close intervals, it is necessary to record the condition of rails,
sleepers, fastenings etc. and the safety clearance around the track
frequently by the field engineers to appreciate the problem in the initial
stages and take further remedial action.
4.3.1 The OMS used at present measures accelerations at coach floor level.
Accelerations measured at axle box level give better idea about track
maintenance. As such, efforts are being made to record the
accelerations at axle box level to assess the track geometry. RDSO has
finalized the specification for equipment for measurement of acceleration
52
at axle box level. Since the vehicle suspension characteristics do not
come in picture, the recorded accelerations are a better representation
of the track geometry.
At present, the official on the foot plate inspection has to give more
attention to track chainage instead of concentrating on track defects. We
should use a GPS based system where the inspecting official has to only
press the key related to a particular defect without bothering for the
location of the defect as the location will be automatically picked-up by
GPS. The GPS antenna shall be magnetically provided on the
locomotive and palm top will be designed to have the track defects as
keys on its keypad. This will improve the quality of inspection. Such
system has already been approved for trial by RDSO.
53
accuracy. However, in two recently procured track geometry
measurement systems, which are under commissioning, RFID based
location identification sensors have been used which give an accuracy of
about one meter.
4.5.2 We should go for GPS based location identification system for which it is
necessary to carry out GPS mapping of IR track. DGPS (Differential
GPS) will be used for accuracy of the data. RDSO has already approved
one such equipment (called Route Data Preparation System) for GPS
mapping.
4.5.3 In future, every new measuring equipment should have the provision for
correlating the track location with the GPS data with the help of GPS
receiver installed on the measuring equipment. This facility is normally
built in on the international systems.
4.5.4 The current monitoring equipment will also be retrofitted to use GPS
based location identification.
One time video shooting of the track features and surroundings of the
track should be done for quick appreciation of the site conditions by
higher officials. The access to the track such as LCs, approach roads,
major bridge locations and other important track features shall be clearly
demarcated. The data will be linked to track locations (i.e. hectometer
posts) so that user can see the details of a selected track location.
Software needs to be developed for this purpose. Alternatively, this can
be integrated in Track Management System being developed by CRIS.
4.7.1 The long welded rails require lesser maintenance but require continuous
monitoring for rail stresses to prevent track buckling and rail fractures.
The continuation of long welded rails through various locations will
require regular monitoring of locked up thermal rail stresses and
determination of stress free temperature for deciding the need based de-
stressing of welded panels. Keeping the vast IR network in view, it will
not be practically possible to install systems, which continuously monitor
the rail stresses on account of large fund requirement. Thus, the two-
pronged approach will have to be adopted to have systems for
continuous monitoring at extremely vulnerable locations and spot
measurement systems for other locations. Thus, the two systems
detailed in following paragraphs need to be implemented.
54
4.7.2 Stationary Rail Stress continuous monitoring system:
The systems are in use over world Railways which continuously record
the rail stresses and determine stress free temperature. One such
system is which uses strain gauges fixed on rails. There is need to
evaluate available systems and decide upon the most suitable system
for IR. Such system shall be installed at critical/vulnerable locations such
as bridges, bridge approaches, sharp curves, gradients etc. for safety
against rail breaks and buckling tendency. The system will also be
useful for detection of rail fractures and shall have these features. The
software shall be compatible with direct inputs to track management
system.
55
sends the result to software program, which translates the magnetic
values into neutral temperature value for that particular rail.
56
defects. Confirmatory follow-up manual testing will be limited to only
suspect defects locations identified by measuring vehicle.
Till the vehicular rail defects testing system is adopted on IR, improved
manually operated USFD machines shall be used.
57
The system has been inspected by RDSO team. Modification has been
suggested to have facility of “A” scans of defects, so that defect
classification is possible as per USFD Manual. After modification, the
system shall be standardized after trials and testing for adoption on IR.
58
detectors will be installed ahead of such important installations/major
yards which help to control the affected train before it enters a major
yard/bridge/tunnel. This will not only reduce the chances of damage to
infrastructure, but will also enhance safety of the passengers/goods
being carried.
59
penetration. GPR surveying provides a continuous survey and
characterization of the track substructure, quickly locating the areas of
potential trouble for further investigation and maintenance.
5.1.1 The rail/weld fractures are major safety hazard. There is no system
available on IR to detect/forecast rail breaks. As such, the manual
patrolling is resorted to in extreme weather conditions as preventive
measure for detection of rail breaks. The present system of patrolling is
manpower intensive and strenuous and provides only partial safety.
There is considerable gap between two successive rounds and the
possibility of fractures in the intervening period remains uncovered.
5.1.2 The systems available have been studied by RDSO and following two
systems have promise for IR:
60
5.1.2.1 Ultrasonic Broken Rail Detection System for LWR track:
The system has limitation that broken rail detection is not available while
a train is present in the monitored section. Thus, it is “passive” broken
rail detection through continuous monitoring of the track condition.
61
transmitted from each of the sensors. Periodically, the master station
polls stress and temperature readings sent from each sensor
approximately once every 10 minutes. Through the use of proprietary
analysis techniques, the stress and temperature variations at adjacent
measurement locations are evaluated and compared. Certain
combinations of stress and temperature can indicate a rail break,
buckled track, or both.
5.1.3 The trial for above systems shall be initiated on IR after evaluating the
suitability in IR conditions. Evaluation of other available technologies
shall also be pursued by RDSO. This is the most important aid for
modernization and shall be pursued vigorously.
62
Remote Flood Detection system Typical Remote scanning of track bed
6.1 Cases of run-over of P-way staff are increasing day by day due to
increased frequency of trains and ageing work force. Suitable
technological aids need to be developed/deployed to warn the staff
working/walking on track about approaching trains. Two types of
equipments i.e stationary for work place and mobile for
patrolmen/keymen need to be developed.
6.3.1 One such system “RAKSHAK” has been tried on South Central Railway.
The equipment is handy with audible warning system. It can be
connected to the nearest station signal for warning the bearer of
equipment about the approaching train. During the limited trials, the
system has worked effectively without obstructing any other railway
installation and alarmed the men at work in these sections well in
advance about the approaching trains and thus taken care of the safety
of workmen.
6.3.2 Other such systems may also be available, which shall be evaluated
and proper equipment shall be standardized and proliferated for all
Keymen/Patrolmen.
63
7.0 Track Management System
65
8.0 Management of P-way stores:
8.1 The present system of P-way store management is to have store with
every SSE/P-way/Incharge. He is responsible for drawing the material
from centralized track depots, maintaining inventory and submitting the
returns. This is a responsibility in addition to his primary responsibility of
inspection and maintenance of track.
8.2 With modernization of track and use of uniform track structure, the
requirement of inventory has considerably reduced. Maintenance of
stores with every SSE/P-way will also not be required in view of
availability of adequate transport arrangements.
8.3 Thus, the present system of stores with every SSE/P-way shall be
replaced with provision of SSE/P-way/Store under each subdivision
(ADEN).
9.1 The inspection system for track and maintenance shall be critically
reviewed to have more emphasis on objective mechanized system and
compliance oriented system. The manual inspection shall be limited only
to inspection of structures causing discontinuity in track such as
turnouts, SEJ, glued joints etc, condition monitoring of rails and
fastening, drainage, emergencies etc.
9.2.1 The system of P-way gang headed by P-way Mate shall not be
disturbed, as this is the basic unit of maintenance.
9.2.2 With merger of Sr. PWS with JE/P-way, JE/P-way shall head P-way unit
consisting of 1-2 sectional P-way gangs with rationalized responsibilities
laid down for Sr.PWS in IRPWM.
66
9.3 The existing system of maintaining P-way store with every SSE/P-
way/Incharge shall be modified to have P-way store for each
subdivision.
9.4 The mechanized inspection aids shall be deployed, which shall include
the following:
9.4.1 Track geometry measurement cars with facility to record track geometry,
car body accelerations, rail profile measurement, corrugation
measurement, video monitoring of rail components, axle box level
accelerations, structure clearance etc.
9.4.2 Oscillation Monitoring System with dedicated coaches fitted with facility
of video monitoring for track components and clearance measuring
system.
9.4.3 Axle box mounted track monitoring system
9.4.4 GPS based foot plate Inspection system
9.5 Track patrolling is a major activity which accounts for major requirement
of manpower. The patrolling is done mostly in extreme weather
conditions, effectiveness of which is always suspect. The tools, which
eliminate/reduce need of manual patrolling, shall be deployed,
particularly the following:
67
9.7 Suitable aids shall be developed for protecting the Keyman/Patrolman to
avoid run over cases.
9.8 The condition monitoring of rolling stock for impact and dynamic
augment on track is important for proper track maintenance. Suitable
systems such as in-motion weigh bridges, WILD, bogie monitoring
systems etc. shall be installed.
9.9 All the mechanized inspection aids and testing equipments shall have
location identification system such as GPS for precise determination of
location of defects and for run-on-run analysis.
68
Annexure-I
Duties and Responsibilities of P-way Officials
1.0 SSE/P-Way/Incharge:
1.1 He will report to ADEN and will perform all duties assigned in IRPWM.
2.2 He will be responsible for carrying out the inspections as per provisions of
IRPWM on following:
2.2.1 Inspection of SEJs, points and crossings and glued joints.
2.2.2 Inspection of drainage system of track in cuttings and yards.
2.2.3 Condition of fittings and ballast cushion.
2.2.4 Inspection of level crossings and bridges.
2.2.5 Corrosion measurement of rails.
2.3 He will be responsible for all the activities of sectional gangs such as:
2.3.1 Periodical oiling and greasing of T/outs, SEJs and rail sleeper
fastening system.
2.3.2 Minor cess repairs and de-weeding, boxing of ballast.
2.3.3 Maintenance of side drains, catch water drains and cuttings.
2.3.4 Clearing of water way and bridges before the monsoon.
2.3.5 Assisting the OMU & MMU whenever they work in the beat of
these gangs, pre & post tamping attention.
2.3.6 Attention of emergencies viz. temporary repairs of fractures.
2.3.7 Greasing of ERC, lubrication of joints, casual changing of rubber
pads and other fittings.
2.3.8 Cleaning of crib ballast for effective cross drainage.
2.3.9 Permanent repairs to fractures.
2.3.10 Rail cutting/ drilling and chamfering.
2.3.11 Any other functions assigned.
69
3.0 SSE/ P-Way/Special Works:
Explanatory Notes:
70
Chapter 4
1.1 The conventional track had had lighter section of rail laid on lighter
sleepers with limited ballast cushion. This track was suitable for manual
maintenance and maintenance practices evolved accordingly. Increase
in traffic density combined with increase in speed and axle load has
necessitated adoption of heavier track structure. The higher UTS rail and
PSC sleeper used in modern track make the track structure more brittle
than the traditional track, requiring mechanized handling for renewals
and maintenance. Increased traffic has reduced the availability of the
track for maintenance, thus necessitating adoption of mechanized
maintenance.
2.1.1 Indian Railways have on-track machines for almost all required
maintenance and renewal activities. With increased modernization of
track and reduced availability of traffic blocks, the requirement of
machines will go up. Critical review will be needed for machines and
adequate number shall be ensured. The Master Plan 2010-2020 for
mechanization of track maintenance, renewal and construction works
has been made and shall be adhered to.
71
2.1.2 Mobile Flash Butt Welding Plants will be required to attend to repair
welds. Suitable plant at least one for each zonal Railway shall be
procured.
Indian Railway has quickly adopted large track machines whereas the
use of small track machines could not be introduced in a manner that is
required. Front line track maintenance staff is not able to use the small
track machines (which are also not so small) because of the problems
of transporting these machines to the mid-section. Track maintenance
staff is forced to still depend on age old traditional manual methods to
cut, drill, weld and attend the track at isolated spots as was done for
decades. One of the main reasons of poor utilization of small track
machines is non-availability of suitable means of transportation with the
track maintenance staff of IR. As a result, most of the small track
machines are stocked only in the maintenance depots without being
actually utilized in the field barring a few of items on specific
locations/sites.
2.2.3 Instructions for hiring of trucks for PWIs (SSE/P-way) exist vide
Board´s letter No.2002/CE II/Genl/1 dated 27.05.2002. The Master
Plan 2010-2020 for mechanization of track maintenance, renewal and
72
construction works, circulated vide Board´s letter No.2002/Track
III/MC/10 dt. 06.05.10 also provides for (ii)-(iv) above. Thus, action is
already on hand for implementation of recommendations of committee.
2.2.4 In KRCL, one RBMV is available with each SSE (P-way) Incharge. This
way, SSE/P-way/Incharge unit becomes independent in planning of
movement of men and material. Resources will not get blocked on
account of limitation of their transportation to site. Thus, RBMV should
be made available with each SSE (P Way) Incharge. Also, RBMV
should be capable of lifting itself and get off the track. This will increase
mobility and also ensure that valuable track space is not occupied by it.
Thus the recommendations shall be implemented with modification that
RBMV shall be provided for each SSE/P-Way/Incharge rather than
each ADEN.
Para 1.6 (h) of IRSTMM provides for one year manufacturer´s warranty
followed by Annual Maintenance Contract (AMC) for 5 years. At
present, AMC for Small Track Machines do not find priority with existing
vendors on approved list. The approved vendors are not quoting in
supply tenders if AMC is made part of supply. The issue of AMC needs
to be addressed for effective utilization of machines. This can be
addressed if availability of requisite infrastructure for providing AMC is
made a prerequisite for approval of vendors.
In each Division, there shall be a Small Track Machine Depot which will
process for supply & repairs of equipments of MMU. This depot will
have imprest of tools & plants along with consumables. Supervisors
from field units will send their equipments for repairs to this depot.
Defective T&P received from field will be immediately replaced with this
imprest. Scale of imprest shall be decided based on need, which
depending on local features and characteristics may vary from Division
to Division. Imprest will also be reviewed on yearly basis by respective
Divisions.
73
year. After dispensing with the manual patrolling, the size of sectional
gangs will be considerably reduced.
2.3.2 Only the following activities will be required to be done by the sectional
gangs:-
(i) Periodical oiling and greasing of T/outs, SEJs and rail sleeper
fastening system.
(ii) Minor cess repairs and de-weeding, boxing of ballast.
(iii) Maintenance of side drains, catch water drains and cuttings.
(iv) Clearing of water way and bridges before the monsoon.
(v) Assisting the OMU & MMU whenever they work in the beat of
these gangs, pre & post tamping attention.
(vi) Attention of emergencies viz. temporary repairs of fracture.
(vii) Greasing of ERC, lubrication of joints, casual changing of rubber
pads and other fittings.
(viii) Gap survey & gap adjustment.
(ix) Cleaning of crib ballast for effective cross drainage.
(x) Any other functions assigned.
74
3.3 Resource Planning::
4.2.2 Minimum two hours of single corridor block shall be mandatory in every
working time table, with clear stipulation that maintenance officials will
use the block without any need for clearance from control.
4.3.1 The traditional way of carrying out maintenance works of major nature
such as track renewal, ballast cleaning and similar other works including
those of OHE and signaling etc. is by way of granting few hours blocks
75
on day-to-day basis until the work is completed. Such a practice requires
long duration to complete the work and normalize speed thereby leading
to hindrance in operation for a very long duration. Further, due to the
short duration of blocks of few hours, substantial time of the block is lost
in works for setting up and winding up and movement of machines
thereby significantly reducing the effective time and hence the
productivity during the block. This also affects quality of work.
4.3.4 Central Railway has successfully carried out two mega blocks for major
maintenance works of track in two block sections on Diva-Vasai section
of Mumbai Division by converting double line into single line for a period
of 4-5 days for each block section. The section was opened after
completing all the works which included deep-screening of track by
BCM, several other works of track maintenance, OHE and signaling
maintenance thus wiping out the arrears of maintenance in the section.
76
mega contract may be for a longer period say 3 years with adequate
clauses for ensuring satisfactory performance and availability of certain
minimum labour force at all the times along with required tools, plants
and machinery.
However, the type of mega contract will depend on the availability of big
enough agencies/contractors. Initially it may not be possible to go for
mega contracts in all parts of the country because of non-preparedness
of the agencies but our efforts would be to develop such agencies
gradually.
5.1.1 One of the major maintenance problems with running of higher axle
loads and high speeds is the rolling contact fatigue (RCF) damage on
the rails. RCF will reduce the life of the rails, necessitate more
maintenance efforts and will jeopardize safety due to increased rail/weld
failures. One of the effective methods to control RCF is correction of rail
profile to improve rail-wheel interaction and shifting of contact band
through rail grinding. Indian Railway has recently purchased two rail
77
grinding machines. However, two machines can cover only part of our
track network. More rail grinding machines need to be inducted into the
system to cover the complete track.
5.1.4 At present, Indian Railway does not have sufficient technical knowledge
to design target rail profile and grinding patterns to achieve the desired
target rail profile. The profile currently being used was designed by
NRC/Canada. World over, there are experts using other software for
this purpose. MOU for technology transfer to RDSO for analyzing rail-
wheel interaction in IR condition on software interface with such
experts will be required. Purchasing user rights for this type of software
are available and its training is also essential.
With introduction of heavier axle loads and rail grinding, gauge face
lubrication will be required even for mild curves. Manual lubrication is not
effective, as lubricant is lost after few trains. Automatic gauge face
lubricators shall be installed on all curves on Indian Railways as per
technical specification of track based lubricators issued by RDSO.
Study shall also be undertaken to judge efficacy and need for top of rail
lubrication in heavily graded/curved sections. Worldwide experience has
been very encouraging. After detailed study, the system top of rail
lubrication shall be developed and adopted.
78
effects are only short-lived. The permanent solution to the problem lies
in replacing the existing soil with good soil and this can‟t be done without
a formation rehabilitation machine in running traffic condition. The
requirement of block for this machine in a single stretch is more but this
is inevitable considering the perpetual problem on this account. One
formation rehabilitation machine requiring a traffic block of more than
four hours and higher output needs to be inducted on Indian Railways to
tackle the problem of poor formation under existing tracks.
17. Providing & repairing road surface at LCs including speed breakers.
79
7.2 Manpower as per MCNTM norms is not available on most of the Zonal
Railways, resulting in backlog of maintenance. As such, there is need
for identifying additional activities, which can be executed through
outsourcing. The activities which do not have immediate direct bearing
on safety of track operations can be considered under this category.
Based on experience of Zonal Railways, it is considered that following
additional activities can be out-sourced without compromising the safety
of train operations.
7.3 Apart from the above maintenance activities, the site conditions
sometimes necessitate deployment of two patrolmen in every beat. The
2nd person in such conditions can be considered to be deputed through
outsourcing.
8.1 As per prevalent system, Indian Railways is procuring the required track
machines which are operated by available departmental operators and
maintained by departmental staff. With increased mechanized
maintenance activities, the requirement of track machines is going up
day by day. New machines for specialized maintenance activities such
as rail grinding, mobile flash butt welding, formation rehabilitation etc.
and track renewals such as track relaying trains etc. are being
introduced, which require specialized operation and maintenance with
heavy consumable requirement. The downtime of such machines
80
requiring costly spares/consumables needs to be controlled for optimal
utilization. There are certain machines such as rail grinding machine
where apart from high initial cost, the requirement of consumable in the
form of grinding stone and technological requirement for design of rail
profile is very high. The comprehensive service contract for such
machines will be helpful in getting the proper output with these
machines. Depending upon the availability of machine and
technological need, one of the following models can be implemented as
and when required.
81
arrangements of spares can be outsourced. This model can also be
implemented for carrying out IOH of track machines.
82
Saving in manpower requirement on account of mechanized maintenance of
250 Km track ( One subdivision)
10.2 Indian railways are having contingent of “On-track machines” for most of
the maintenance and renewal activity. Critical review shall be done
about adequacy of machines and adequate number shall be ensured.
The Master Plan 2010-2020 for mechanization of track maintenance,
renewal and construction works already drawn shall be adhered.
10.3 One suitable Mobile Flash Butt Welding Plant for each zonal Railway
shall be procured to attend to repair welds. IR shall also consider
procurement of one formation rehabilitation machine for attending to
problematic formation on IR.
83
10.4.1 Rail Borne Maintenance Vehicle (RBMV) shall be provided with each
SSE/P-way/Incharge.
10.4.2 The system of approval of small track machines shall be reviewed to
include availability of requisite Infrastructure for providing AMC as a
prerequisite for approval of vendors.
10.4.3 Setting up of Small Track Machine Depot in every Division, which shall
function on unit exchange method. The depot shall have adequate
cash imprest, spares, tools & plants, consumables etc.
10.5.1 Assured Corridor Blocks: One single block of minimum two hour‟s
duration as corridor block shall be mandatory in every working time
table, with clear stipulation that maintenance officials will use the block
without any need for clearance. This shall not be breached except in
real emergency.
10.5.2 System of Mega Blocks: Instead of number of short duration blocks,
Mega Block shall be arranged for planned works by introducing single
line working in double line sections and diversion/ regulation of trains in
single line section. This will facilitate completion of quality work in time.
10.5.3 System of Mega Contracts: Mega contracts will ensure adequate
availability of manpower, T&P and machinery all the times for lot of
activities of track renewal and maintenance which are being
outsourced.
10.5.4 Review of signaling and traction installations on track affecting
mechanized maintenance shall be done and suitable systems be
designed.
10.5.5 Empowering Field Units: Liberal powers for small procurements
through cash imprest, enhancement of imprest shall be provided.
10.7 Automatic gauge face lubricators shall be installed on all the curves of
IR. The efficacy of Top of Rail Lubrication (TOR) on IR shall be studied.
84
put in place. In technology intensive areas, such as rail grinding, where
new technology is emerging fast and technical consultancy is needed for
proper utilization of machines, long term service contract with
comprehensive design, operation and maintenance including supply of
consumables will be cost effective and will give desired output. Similar
will be case with formation rehabilitation machines etc.
85
Annexure-A
Saving in Manpower
5 13.08 12.81 13.80 14.59
(%) between (1) and (2)
Saving in Manpower
6 (Nos.) between (1) and 65 60 56 52
(3)
Saving in Manpower
7 18.90 18.75 18.86 18.51
(%) between (1) and (3)
Saving in Manpower
6 (Nos.) between (1) and 105 100 96 92
(4)
Saving in Manpower
7 30.52 31.25 32.32 32.74
(%) between (1) and (4)
86
Chapter 5
1.0 General
1.3 There are issues related to quality of training in Zonal Training Centers
as well as training in Divisions due to lack of infrastructure and
competency of trainers in these training centers. IRICEN is having
capacity constraint in training the supervisors.
1.4 Present training is overly dependent on old patterned class room lecture
methodology. It needs to be more interactive including model rooms and
Audio Visual Aids.
2.1 With ever increasing demand of traffic and increase in axle loads, it will
be inescapable to adopt more and more mechanized maintenance as
well as new technologies for the maintenance of track. To meet the
training needs for improved maintenance of P-way as well as to adopt
mechanized maintenance, it is necessary to develop training centres as
„Centres of Excellence‟. For this, not only the modern infrastructure and
gadgets are required but the trainers also need to be trained. There is
greater need to cover aspects such as, modern track structure, more
scientific & modern methods of maintenance; and personal safety.
87
2.2.1 Every Zonal Railway should have a Civil Engineering Training Centre for
training of supervisors within the zone on lines similar to Civil
Engineering Training Academy (CETA) at Kanpur.
2.2.2 There should be a Divisional Training Centre in every Division for
training of staff below supervisory level with a structured curriculum.
2.2.3 It is very important to equip the training centres with required
infrastructures in terms of properly lit and well ventilated class rooms
away from the busy city areas, modern teaching aids such as personal
computers and projectors in addition to boards, well equipped model
rooms and other required resources.
2.2.4 Similarly hostels, messing and recreational facilities also need to be
augmented to ensure reasonable level of comfort to the trainees.
2.2.5 The instructors, in these training centres, should be suitably picked-up
who have aptitude for teaching and learning.
2.2.6 The trainers shall be imparted training on some of the core subjects and
new technologies in a centralized training Institute for Civil Engineering
under the technical control of IRICEN.
2.2.7 One such centre i.e. IRICEN Track Training Institute has started
functioning at Pune. But one centre will be inadequate to meet the
requirements and it will be difficult to send the supervisors from all over
the country to one location. We should, therefore, have four such
centres spread over at different locations, each one catering to four
Zonal Railways.
2.2.8 The trainers selected for these centres will be trained at IRICEN and
shall get technical support in terms of power points, technical literature
and guidance from IRICEN resources. Even some of the specific
lectures can be arranged through IRICEN faculty.
2.2.9 These four centres will provide training to the supervisors of adjacent
zone as well as the trainers of Zonal and Divisional Training Centres.
88
large numbers of persons in one go without disturbing them from their
place of work.
One of the reasons for the poor quality of AT welds is the inadequate
training of welders and supervisors. At present, there are two training
centres for them. The supervisors are trained at RDSO/LKO by M&C
Directorate while training to welders is imparted by Thermit Portions
Plant (TPP)/LKO and another center at Vijaywada. With the limited
facilities and capacity constraints, these centers are unable to meet the
present day demand of training for AT welding. It is necessary to expand
these centers with more instructors to train the welders. The
infrastructure at these centers also needs upgradation with the proper
lodging and boarding facilities for the trainees along with modern
teaching aids.
USFD testing of rails and welds is an important diagnostic tool for safety
of the traffic. Supervisors carrying out testing are trained by M&C
Directorate at RDSO. The facilities as well as capacity of training at
RDSO need upgradation for proper implementation of this technology.
89
The sectional and incharge SSEs responsible for track maintenance
should also have basic knowledge of USFD testing for which a separate
training module has been developed, but due to capacity constraint, all
supervisors are not trained.
90
augmented to have adequate facility for catering to the requirements of
Zonal Railways @ 8 Zonal Railway at each center.
4.3 The facility of training for USFD with M&C directorate, RDSO shall be
augmented substantially to ensure that all SSE/JE P-way have
knowledge of checking the work of USFD Operators and each Railway
has adequate pool of trained USFD operator.
4.4 The Officers at RDSO, IRICEN and Railway Board will be given specific
training in new technologies being adopted by advance Railway
Systems. This will facilitate faster selection and finalization of
technologies as well as help in in-house research. Liberal system of
visits to new technologies shall be made. Similarly, officers at middle
and senior management level shall also be given in-depth exposure of
new technologies for faster assimilation of technology.
91
Chapter 6
Research Projects for Track Modernization
1.2 There are number of research projects already in progress, which are
considered to be relevant to the modernization envisaged by the
committee. These are listed below as on-going projects.
1.4 The list of projects in progress and new projects envisaged are
enclosed as Annexure-A.
2.2 The MoU in following priority areas shall be considered with reputed
global research organizations:
2.2.1 Development of capability for design of target rail profile and grinding
patterns.
92
The MOU with NRC/ Canada, which has developed the grinding
strategy for IR will be helpful.
2.2.2 Development of simulation technique to verify suitability of track
components e.g. sleeper, fastenings for given combination of speed,
axle load, operating conditions, etc.
2.2.3 Development of suitable code of practice for continuation of long
welded rails on bridges on pattern of UIC Leaflet.
The MOU with UIC, which has already developed leaflet for standard
gauge track will be helpful.
2.2.4 Development of computer simulation for stability of long welded rails at
critical locations such as sharp curves, steep gradients, etc..
The MOU with UIC/AREMA, which has already developed systems for
standard gauge track will be helpful
93
Annexure-A
On-going Projects:
94
Futuristic Projects:
On-Going Projects:
95
maintenance practices to
ensure safety against
buckling and rail fractures
for LWR Track.
96
Futuristic Projects:
97
for Rail stress provisions which are
calculation on mostly empirical in
Indian Railways nature at present.
2. Simulation & field
study to validate the
theoretical
parameters so
decided.
3. Development of
software based on
above study for rail
stress calculation for
different operation
conditions.
98
laid on sharp out Phenomenon for
curves, steep Indian Railway
gradients and other operating conditions.
critical locations 2. Development of
computer simulation
for various conditions
for stability of LWR
and validation by
actual field
measurement.
3. Development of
package like CWR
safe for Indian
railway Broad Gauge
Track.
99
proven systems.
2. Rail pad needed for
noise and vibration
attenuation for
various civil
structures.
100
ballast/BLT,
formation including
trial of short listed
system.
14 Consultancy for Being 2 Years Capability for designing
design of Target worked Rail profile for optimum
Rail profile and out rail/wheel contact under
grinding pattern for various operating
effective Rail/ conditions.
Wheel interaction
on IR
15 Study of noise and To be 3 years With increasing speed,
vibration with use worked load and habitation,
of different out environmental issues
fastening system are gaining importance.
with/without This study will facilitate
resilience understanding the
base/ballast mat subject and designing
separately for various components of
(i) Ballasted track track form such that the
territory environmental norms for
(ii) Ballast less noise and vibrations are
track territory respected.
For track on
(a) Bridges
(b) Tunnels
(c) Formations
101
Chapter-7
1.1 The track modernization will require quicker evaluation, adoption and
assimilation of new technologies in deficient areas. As the emphasis of
modernization is to gradually switch over to mechanized system of
inspection and maintenance with overall objective of reducing reliance of
manual means, the equipments/systems available in other railway
system need to be evaluated and adopted on Indian Railway system.
1.2 The technologies required for modernization can be broadly grouped
into following two categories:
1.2.1 Completely new technology which is not in use on Indian Railways.
1.2.2The technologies in use in some form but needing further improvement.
1.3 While the traditional system of inviting EOI will be useful in areas where
improvement is required in existing system, this may not deliver results
in acquiring new technologies in view of the past experience in some
cases in the past for acquiring green field technology e.g the technology
of ultrasonic broken rail detection system, which could be located in
literature survey with best efforts and was not offered in any EOI. The
efforts are continuing since 2004 and expression of interest for choosing
suitable technology was invited twice, but suitable technology was not
offered in response to expression of interest. Thus in technology
intensive areas the system of EOI may not work primarily on following
accounts:
(a) Exceptional time taken in floating EOI and evaluation of response.
(b) All/ majority of offers in EOI are not found meeting the functional
requirements, thus defeating the very purpose and resulting in delays.
(c) The agency having suitable technology does not participate in the EOI
due to various reasons such as technology developed by govt. R&D
centers, unwillingness on the part of the agencies to participate etc.
(d) No proper system is in place for going ahead with selected technology
for adoption.
102
1.4.1 The technologies available over World Railways shall be
technically studied through available literature and promising
technologies shall be short listed.
1.4.2 A technical team is shall be constituted for evaluation of the
technology in operation covering various conditions where the
technologies are installed. The team shall carry out critical review
of the technology in special reference to Indian Railway operating
conditions and would make out comprehensive recommendations
on suitable technology considered most suitable.
1.6 These systemic changes will facilitate faster evaluation, adoption and
assimilation of new technologies.
2.1 The large scale mechanization will require the longer duration, though at
lesser frequency, of track possession for the effective maintenance. The
conventional system of providing traffic block of small durations spread
over number of days has resulted in serious wastage of manual labour
and costly machines. The quality of work has also been found lacking.
For an appropriate maintenance system to be in place, the mindset and
the existing system on Indian Railways has to undergo a major change.
While the corporate objective of providing transportation remains the
key, this cannot be achieved effectively unless the infrastructure assets
are maintained. The current priorities of pushing traffic without
consideration of maintenance of infrastructure resulting into its
continuous degradation needs to be changed to a more rational system
of honouring requirement of track possession by the infrastructure
103
departments for optimal utilization of available assets. The infrastructure
maintenance has to be done with quality output so as to prolong the
maintenance cycle. The short term disturbance of traffic can be
compromised for larger gains. As the mechanized maintenance
infrastructure is costly and availability of resources is limited, any
wastage due to non-availability of requisite track possession for
maintenance will result in accumulation of maintenance working. The
maintenance needs of infrastructure, if differed beyond reasonable
period, seriously affect the maintainability of assets. Thus the co-
ordinated effort is needed and system of corridor blocks and mega
blocks needs to be adhered, as is being done on advanced railway
systems and has been tried in limited way on Indian Railway system
successfully.
A fixed time corridor block of minimum one spell of two hours duration in
each section shall be provided in working time table for regular
maintenance of infrastructure. It shall be clearly stipulated that it is
sacrosanct. Minor operational disturbance due to corridor block has to
be absorbed in the system. This is imperative to reap the maximum
benefits of modernization.
The planned works require longer track possession time for getting the
quality output and economical utilization of expensive modern machines
and equipment. The quality of work done in spells of traffic block of 3-4
hours every day for number of days suffers and system has following
disadvantages:
(a) Wasteful effort and expenditure for both traffic and infrastructure
departments in arranging the traffic blocks on day to day basis.
(b) Lesser than stipulated output due to frequent preparatory working,
opening and closing time required in start of work and making
infrastructure fit for operation.
(c) Effect on train operations for longer duration, as speed restrictions
continue for longer duration.
104
(i) Double line section:-
As single line sections are normally not very busy and important
from traffic considerations, the feasibility of regulation/diversion of
trains shall be examined. The feasibility of closing the section for
required duration for mega block shall be also be examined as is
being done for gauge conversion and other works.
4.1 The technologies in field of track modernization are emerging fast. The
advanced railway systems as well as Research Institutes are constantly
105
working on technologies, which are relevant for Indian Railway track
also. Instead of reinventing the wheel, mechanism for adoption of
technology developed in such areas on IR will be more logical.
5.1 For true modernisation, the existing inspection and maintenance regime
will require major changes. A comprehensive review is needed for
inspection actually to be required to be done and measurements need to
be undertaken keeping the degradation pattern in view. As such,
provisions on Indian Railway Permanent Way Manual regarding
inspection, up keep of records shall be comprehensively reviewed. The
maintenance of records in hard copy has been done away for divisions
where track management system (TMS) has been implemented.
Further, rationalization and standardization of formats on which data is to
be monitored, arrangement for direct input from mechanized inspection
means in TMS records thus dispensing with the needs for manually
entering data and other user friendly features will be required to be
carried out.
106
6.0 Training and Skill Development:
107
8.0 Service Contracts of Track machine works:
8.2 The other machines such as train relaying trains (TRT), formation
rehabilitation machines etc. will also be considered for similar
experience.
108
Chapter 8
Recommendations
1.0 In order to meet the projected traffic needs and changing socio-economic
environment coupled with the technological upgradation, the
modernization of track is inevitable. Reliance on manual system of
inspection and maintenance, manual safety patrolling has to be gradually
reduced with induction of more and more diagnostic aids.
3.0 Track structure – The basic track structure to be adopted for new
constructions, gauge conversions and track renewal shall consist the
following :-
(a) Rails: 68 kg, 90 UTS with improved metallurgy. Head hardened rails
shall be used at sharp curves, steep gradients and on freight
predominant routes. 60 Kg, 90 UTS rails with improved metallurgy
can continue for sections not envisaged for 25T operations.
(b) Bridge Sleepers: Use of composite sleepers on girder bridges with
appropriate fastening system.
(c) Sleepers: Wider base PSC sleepers (conventional sleeper till
design is finalized) at sleeper density of 1660 no./km.
(d) Fastening system: A fastening system with tighter tolerance with
comprehensive performance criteria having reduced loss of toe load
in service and better performing rubber sole plates.
(e) Ballast: Hard stone machine crushed ballast, ballast cushion of 350
mm on well compacted formation with required blanket layer..
(f) Turnouts: Thick Web Switches with improved SSD and Weldable
CMS crossings.
(g) Long welded Rails with Flash Butt welds and Improved Switch
Expansion Joints. Indian Railways shall gradually switch over to the
standard track structure as detailed above to avoid multiplicity of
track components thereby better control on inventory.
109
(In-Charge) shall be provided with SSE/P-way (Special works) apart from
required SSE/P-way (section). The organization proposed in report can
be adopted without much disturbance to existing set up and additional
resources. However, based on the duties and responsibilities, schedule
of inspections will have to be critically reviewed and laid down. The
relevant provisions of IRPWM will also require suitably amendment.
8.0 The systemic changes required for effective implementation of three tier
system of track maintenance shall be implemented. The MMU shall be
implemented with modification that one RBMV shall be provided for each
SSE/P-way/In-charge. The requisite infrastructure for stabling and
110
maintenance of rolling stock/machine, availability of small track machines,
positioning of staff for operation and maintenance shall be done on priority
for effective implementation of the system.
9.0 All JEs (P-way) should be provided with pickup vans/small trucks, which
can move men and material to the site at the earliest.
11.0 The fixed signaling and traction installations provided on track require
critical review as these installations pose serious challenge to the
mechanized maintenance of track. Many a time, these installations are
required to be disconnected/removed for machine working, which is
increasingly becoming a bottleneck. The new signaling and traction
installation technologies shall be such that they do not require fixtures on
track.
12.0 For designed rail-wheel interaction and for controlling the rolling
contact fatigue defects on rail, rail grinding is essential. Two RGMs
available on Indian Railway can cover only part of Indian Railway network.
Adequate number of RGMs to cover complete IR network including the
facility of grinding the turnouts shall have to be arranged for effective rail
maintenance. The system of service contract shall also be considered for
this activity.
13.0 Automatic track based gauge face lubricators shall be installed on all
curves of Indian Railways as per technical specification issued by RDSO.
111
c) Development of computer simulation for stability of Long Welded Rails
at critical locations such as sharp curves, steep gradients, etc;. In this
regard, MoU with UIC may be helpful.
17.0 The end loading rakes for transportation of long welded panels of
260/520 meter length with capability of movement at 100 kmph and better
unloading system shall be developed.
112
of 130 kmph. Necessary infrastructure in this regard shall be conceived
and provided.
21.0 The substantial financial saving of the order of 30% due to reduced
manpower requirement after implementation of modernization measures
will not only offset the capital requirement but will also result in continuous
reduction in cost of maintenance.
113