PRE OPERATIONS:
POST OPERATIONS:
1. Operator should ensure the machine is off position before
enter the machine inside for verify the critical dimensions in
online.
1. Operator should apply the Oil and greasing as per Machine Builder
Supplied Chart in all available machines with help of our maintenance team.
(If doubt ref. the manual)
2. Blow low pressure air on the Servo motors back side heat eliminating
fans and Hyd. Oil chiller fans areas.
3. Keep the machines Neat and Clean the inner and outer areas weekly
holidays or Idle time.
4. Remove the Tramp oil (lub oil,grease &Hyd. Oil) from the Coolant tanks
with help of Air Skimmer by weekly holidays or Idle time.
6. Greasing the Pallet pull & pushing Chains and Quill Spindle
bearing areas.
1. Hydraulic tank to be cleaned and Hyd oil to be filtered or replace every ten
thousand hours.
3. Check for the backlash in axis drives and adjust if required with
help of machine builders service Engineers.