You are on page 1of 1

Agenda for Kick-off Meeting on dated 10/12/2019 at MaGL Office,

Pune

Project: Civil Construction Work of City Gas Station (CGS) and Mother Station
for City Distribution Project at Jategaon, Pune.
Contractor: M/s Hemant Enterprises
P.O. No.& Date: MGL/19-20/0042 & 02/12/2019

Sr.No. Points for Discussion Remarks

1 PBG-10%

2 Contractor All Risk Policy

3 Workmen Compensation Policy

4 EPF and ESIC Registration

5 Power of Attorney
Mobilization Schedule- within 2 Weeks
6 from date of PO

7 Equipment List

8 Organisation Chart

9 Material Procurement Schedule