CADANGAN MEMBINA DAN MENYIAPKAN 60 LOT SESEBUAH DAN 8 LOT RUMAH BERKEMBAR, 2 UNIT PENCAWANG ELEKTRIK, SEBUAH TANGKI

AIR BERTINGKAT DAN KERJA-KERJA INFRASTRUKTUR BERKAITAN DI


SEBAHAGIAN SEKYEN 2B, ANTARA GAPI, BANDAR SUNGAI CHIK, DAERAH HULU SELANGOR, SELANGOR DARUL EHSAN
, ANTARA GAPI, BANDAR SUNGAI CHIK, DAERAH HULU SELANGOR, SELANGOR DARUL EHSAN

MASTER WORK PROGRAM UNTUK PROSES TENDER 60 UNIT LOT BANGLO


(PKNS/IP/AG-LOT/KON -03/2019)
Update on :
ACTUAL ACTUAL
ITEM WORK DURATION START FINISH 03/19 04/19 05/19 06/19 07/19 08/19 09/19 10/19 11/19 12/19
START FINISH

1. Tender Meeting No 5 1 days 19/7/2019 19/7/2019

2. Design and Preparation of BQ 30 days 20/7/2019 20/8/2019

3. Request for client signature 7 days 21/8/2019 28/8/2019

4. Submission to authority(Syabas,IWK dan Majlis) 4 days 29/8/2019 2/9/2019

5. First Comment from authority 30 days 3/9/2019 3/10/2019

6. comply comment 7 days 4/10/2019 11/10/2019

7 Tender preparation 15 days 12/10/2019 27/10/2019

8 Approval from Ukur Bahan PKNS 15 days 28/10/2019 15/11/2019