Stocklist Checklist
1. Drawing(s) and Hydraulic Caleulations should be checked by Design Manager
before stock-listing any materials
2. Start with flange located at the base of the riser.
3. List all mains frst following the flow of water through the system. Pick up
couplings, fittings & valves as you run into them.
4. When listing valves pick up all trims and accessories that go along with that
valve. Look in the Technical Data book and it will list all items required for that
valve along with the part number.
5. Check the list below for all items required. Order systems complete one time. NO
PARTIAL SYSTEM ERS.
6. Completing the order includes
Packet.
7. Order all items per supplier or vender.
8. VERIFY ALL PIPE AND FITTING TYPES SPECIFIED FOR THIS
PROJECT and pat this-information on the stocklist and plans
9. Verify all ordered material with approved product data. Do NOT deviate from
what was approved.
materials ordered and making of the Forman’s
Underground (Requisitioned List):
J. Elbows, Tees & Uniflange with accessories as required
____ Sectional Valves as required (Check depth of bury)
__ Hydrants if required.
___ Ductile Iron pipe 5’-0" out past building to spigot on riser.
___ Roadway Box or Post Indicator for all underground N.R.S gate valves.
___ Bent Eye Bolts (2 per fitting & 2 per dead man)
__ Uniflange
___ Two (2) Alll Thread Rod %” x 10’-0” per fitting (6” & 8” underground)
__ Two (2) All Thread Rod 5/8” x 10°-0” per fitting (4” underground)
Nuts & WashersRisers and System Components:
Control Valve - Couplings for grooved and bolt packs, grooved flanges and/or
tamper switches for OS&Y valves, (Wall post indicator when required)
__ Alarm Valve
Vertical open trim
Pressure switch(s) (if required)
Retard Chamber & trim
Misc. 2” & 1-1/4” pipe for drain lines and fittings
Water Motor alarm or Electric Bell
Misc %” & 1” galvanized pipe for WMA. Addition check valves &
strainer when more than one system is on a single WMA.
ae ae
Flowswitch
‘Tamper Switch
Fire Department Connection
1. Check Valve
Ball Drip Valve
All Caps, Chains, Wall Plates, etc. (Double check finishes)
Misc. Pipe & Fittings for drains out of the wall.
1. (1) 2” Black C.l. Elbow (per riser)
2. (1) 2” Galvanized 45 degree elbow
3. (1) 2” Galvanized wall plate
4. (1) 1-1/4" Black C.L. Elbow (per riser)
5. (1) 1-1/4” Galvanized 45 degree elbow
6. (1) 1-1/4” Galvanized wall plate
7. (1) 2” Random Black Schedule 40 Pipe
8. (1) 1-1/4" Random Black Schedule 40 Pipe
9. (1) 2” Black C.l. Tee for each additional riser
10. (1) 2” Union for each additional riser
Dry Pipe Valves and/or Preaction Valves
1. %" outlet on supply side of control valve for priming line
2. All Trims - Look at data sheet for which one is required for specific type
of system you are designing
Pressure Alarm Switch
High/Low Pressure Switch
Air Maintenance Device
Air Compressor (Sized for capacity of the dry system). See plan.
Pipe & Fittings from compressor to Valve
a. (6) 4” Galvanized M.L. Elbows
b. (1) 4” Random Galvanized Pipe
Noy ay____ Deluge Valves
1. 14" outlet on supply side of control valve for priming line
2. All Trims - Look at data sheet for which one is required for specific type
of system you are designing
3. 14" clamps for pilot lines
4, Pilot line pipe, fittings & heads
___ Fire Pumps
1. All pipe on suction side of Fire Pump (and Jockey Pump) to be
galvanized.
Alll Valves (Including those located in the Jockey Pump piping)
Outlets on pipe for jockey pump supply & discharge.
‘Tamper switches.
Test Header pipe, valve & materials.
24” Check Valves w/ 3/32” hole in clapper for sensing lines
‘A” Globe Valves for sensing lines
44” Brass Tubing (50”)
‘4” Brass Tees and Elbows
0.4" Plugs
1, Jockey Pump Piping and Fittings
See aH EEN
__ Inspector's Test
1. 1” Galvanized 45 degree elbow
2. 1” Galvanized wall plate
3. 1" Globe Valve or TestandDrain. (Pressure Relief for Gridded Systems)
4, 4" or 4” Test Connection (when not using TestanDrain). Size to match
smallest orifice of head in the system.
Sprinkler Heads (Verify type, size, temperature, K-factor and finish)
Sprinkler Wrench (1 for every type of head used)
Spare Head Cabinet (6 or 12)
Random Length of pipe for each size of pipe used (1” thru 2” only) along with
some additional fittings for each size of pipe use.
__Signs
Main Drain
Control Valve
Inspectors Test
Aux. Drain
Bee___ Hangers
1, Order all materials, ATR, Rings, TBC’s Sammy's, Drop-In Anchors, Etc.
(Verify type of materials required by spec.)
2. Order all trapeze materials (Pipe, Rings, TBC, etc.)
Gauges
1. Order nipples and valve along with gauge.
___ Sleeves
1. Verify what walls require sleeves and the material specified for the sleeves.
Order all sleeves required for the project along with sleeve information
placed on the drawing.