Professional Documents
Culture Documents
: P1-CON-A03-420
Job No. : 2011020
AND RESPONSE Rev. No. :0
PROCEDURE Page : i OF ii
REVISION LOG
TABLE OF CONTENTS
1 PURPOSE ............................................................................................................... 1
2 SCOPE .................................................................................................................... 1
3 REFERENCES ........................................................................................................ 1
4 ABBREVIATIONS ................................................................................................... 1
5 DEFINITIONS .......................................................................................................... 1
6 RESPONSIBILITIES ............................................................................................... 2
9 DISPOSAL .............................................................................................................. 6
12 ATTACHMENT ........................................................................................................ 8
SPILL PREVENTION Doc. No. : P1-CON-A03-420
Job No. : 2011020
AND RESPONSE Rev. No. :0
PROCEDURE Page : 1 OF 8
1 PURPOSE
The procedure defines the methods & strategies of preventing and controlling
chemical spills as well as relevant responsibilities at PTC JPP project.
2 SCOPE
This procedure is applicable to JPP Site and Camp Areas. Contractor shall follow
relevant PTC procedures and regulations.
3 REFERENCES
Key references for the present document are:
Project HSE Plan (P1-CON-A03-120)
Construction Environmental Procedure (P1-CON-A03-412)
PROJECT HSE POLICY
Royal Commission Environmental Regulations (RECR)
Waste Management Procedure ( P1-CON-A03-419)
Emergency Response Plan (P1-CON-A03-415)
4 ABBREVIATIONS
COMPANY POLYSILICON TECHNOLOGY COMPANY (PTC)
PROJECT PTC Jubail Polysilicon Project (PTC-JPP)
CONTRACTOR Hyundai Engineering Co., Ltd., KCC Engineering &
Construction Co. Ltd. and Hyundai Saudi Arabia Co., Ltd.
HSE Health, Safety & Environment
PM PROJECT Manager
SM Site Manager
SHSEM Site HSE Manager
EIA Environmental Impact Assessment
JIC Jubail Industrial City
MSDS Material Safety Data Sheet
5 DEFINITIONS
5.1 Spill/Leak
Any release of solid or liquid (pollutant) discharged into the Natural Environment,
releases into secondary containment with impermeable barriers are not considered a
release to environment, i.e.: Release into the bunded area without any impermeable
SPILL PREVENTION Doc. No. : P1-CON-A03-420
Job No. : 2011020
AND RESPONSE Rev. No. :0
PROCEDURE Page : 2 OF 8
ground liner allowing the spilled materials to seep into the ground below would be
considered us a release to environment and shall be reported.
6 RESPONSIBILITIES
HSE Organization in site and relevant environmental responsibilities are detailed in the
PROJECT HSE Plan and in the Construction Environmental Procedure.
Responsibilities of the site key functions concerning the provisions of the present
procedure are outlined
6.1.1 Responsible in ensuring the compliance with environmental requirements for local and
international laws and meeting Company’s requirements
6.1.2 Actively participate in and chair any meeting to discuss spill control measures
6.2.1 Plan construction works in a manner that avoids or minimizes impact on the
environment.
6.3.1 Overall responsibility is for the implementation of the environmental matters of the
project.
6.3.2 Ensures environmental risks of the project or identified and appropriate remediation
measures are implemented on site.
6.4.1 Ensuring there is sufficient and appropriate spill response supplies in their area.
6.4.2 Ensuring that an adequate number of persons are trained in chemical spill response for
their area.
6.4.3 Take all necessary steps to minimize the chance of spills when working with chemicals
6.4.4 Cooperate with the Area Manager and the HSE Department to implement a spill
program in their area.
SPILL PREVENTION Doc. No. : P1-CON-A03-420
Job No. : 2011020
AND RESPONSE Rev. No. :0
PROCEDURE Page : 3 OF 8
6.4.5 Shall arrange for containment and control of the spill based on the requirements of the
relevant MSDS.
6.4.6 To Report the spill in case it was beyond the quantity stated in attachment 1.
6.5.1 Maintain records regarding inspections conducted, training conducted and spill kit
maintenance.
6.5.2 Provide assistance for developing site specific spill response procedures.
6.6 Subcontractors
6.6.1 Subcontractors are responsible to CONTRACTOR for respecting the provisions of this
Procedure and are subject to CONTRACTOR supervision.
6.7.1 Subcontractors are responsible to CONTRACTOR for respecting the provisions of this
Procedure and are subject to CONTRACTOR supervision.
During response operations, priority shall be given to the protection of health and
safety of the personnel involved. Therefore, appropriate PPE shall be worn during the
response activities.
The pollutant materials, arisen by clean-up actions, shall be disposed of in compliance
with Waste Management Plan and Construction Environmental Procedure.
9 DISPOSAL
11 SPILL REPORTING
Any spill above the relevant quantities stated down in Attachment- 1 shall be reported
according to INCIDENT REPORTING INVESTIGATION AND PREVENTION
PROCEDURE AS an Environmental Release Incident for which Preliminary
Incident Report must be filled in and distributed according to the above procedure
SPILL PREVENTION Doc. No. : P1-CON-A03-420
Job No. : 2011020
AND RESPONSE Rev. No. :0
PROCEDURE Page : 8 OF 8
12 ATTACHMENT
Spill Quantities beyond which the spill must be reported as “ENVIRONMENTAL
RELEASE “according to Incident Reporting Investigation and Prevention Procedure.
Oil
5 liter
(including oil emulsions)
Chemicals 5 liter
(Including water based solutions)