Doc. No.

Page No.

DAILY PROGRESS REPORT Revision No.

Mahesh Gas Limited


ZONE /GA: PUNE Outer GA DATE 19-Sep-2019

Daily Progress Report -Pipeline Construction


Laying in Meters Laying in Inch KM Commissioning in Meters
Sr. No. Name of Contractor Name of the Site/Area
Today This month Cumulative Today This Month Cumulative Today This Month Cumulative

PE Pipeline Projects

1 Jayam Infratech Sanaswadi 0.00 1511.50 9463.77 0.00 3.353 33.43 0.00 0.00 0.00

2 Rudra Gas Ranjangaon MIDC 0.00 0.00 32662.50 0.00 0.000 154.04 0.00 0.00 0.00

3 Rudraksh Enterprise Sanaswadi 0.00 0.00 2373.57 0.00 0.000 11.68 0.00 0.00 0.00

4 Shree Polkaji Wagholi 127.00 2324.60 7825.10 0.45 8.929 27.54 0.00 0.00 0.00

5 Shailee Projects Wagholi 0.00 406.00 3375.00 0.00 1.998 9.18 0.00 0.00 0.00

6 Cortech Int Pvt Ltd. Khed City 0.00 0.00 1593.40 0.00 0.000 7.84 0.00 0.00 0.00

7 Rajesh Power Services Pvt LWagholi 0.00 443.00 2844.00 0.00 2.067 8.66 0.00 0.00 0.00

8 Spur Infratech PE Shikrapur 0.00 400.00 550.00 0.00 1.969 2.71 0.00 0.00 0.00

TOTAL 127.00 5085.10 60687.34 0.45 18.31 255.07 0.00 0.00 0.00
Steel Pipeline Projects

Jategaon-Shikrapur- 60.85 1854.63 13177.09 0.73 16.587 109.16 0.00 0.00 0.00
1 Spur
Ranjangaon

Jategaon-Kendur-Khed 0.00 649.46 6495.84 0.00 5.196 53.52 0.00 0.00 0.00
2 Corrtech
City

CGS Nhavare to 72.00 1260.96 2948.68 0.58 10.09 23.59 0.00 0.00 0.00
3 Chandrama Service
Chophula

TOTAL 132.85 3765.05 22621.61 1.31 31.87 186.26 0.00 0.00 0.00
TOTAL 259.85 8850.15 83308.95 1.76 50.185 441.33 0.00 0.00 0.00
Remarks: