DATE : APRIL 2, 2018

LOCATION : JUBAIL
SUBJECT : FENCE AND TRENCH WORKS - JUBAIL

Item BOQ DESCRIPTION QTY UNIT LABOR MATERIAL RATE AMOUNT REMARKS
JUBAIL SCOPE

1 Anti Vehicle Barrier ,Installation only 1384 m


Please Refer the
Note

2 Upgrade of exisitng fence to HCIS category-1 fence 576 m As above

Removal and replacement of the existing fence incl. Installation,


testing & Commissioning Work for new Antipersonnel fence
reinstatement (CLASS-1 fence) - HCIS SEC-02, including
3 2077 m As above
Development of ground by filling structural fill along SWC fence and
Construction of drain channel at lowest place to avoid water
stagnant.

Removel and replacement of the existing fence incl. Installation,


testing & Commissioning Work for new Antipersonnel fence
reinstatement (CLASS-4Froad fence) - HCIS SEC-02, including
4 324 m As above
Development of ground by filling structural fill along SWC fence and
Construction of drain channel at lowest place to avoid water
stagnant.

Removal and replacement of the existing fence incl. Installation,


testing & Commissioning Work for new Antipersonnel fence
reinstatement (CLASS-4Froad fence) - HCIS SEC-02, including
5 25548 m As above
Development of ground by filling structural fill along SWC fence and
Construction of drain channel at lowest place to avoid water
stagnant.
Removal and replacement of the existing fence incl. Installation,
testing & Commissioning Work for new Antipersonnel fence
reinstatement (CLASS-4Froad fence) - HCIS SEC-02, including
6 1826 m As above
Development of ground by filling structural fill along SWC fence and
Construction of drain channel at lowest place to avoid water
stagnant.

Concertina Fence Installation, testing & Commissioning Work for Installation of


7 Razor wire fence as per HCIS SEC-02 and Compliance Matrix for 314 m Removable concertina
Water Intake Area (Removable)

OPTIONAL ITEMS (SUPPLY & CONSTRUCTION)

Mechanical /Manual Main Cable Trench Excavation, Ducts supply


and installation , Laying of Red tiles, Warning tape, Backfilling with
8 5928 m As per Drawings
compaction and approved Cable markers post with plate (TRENCH
TYPE 1)

Mechanical /Manual Main Cable Trench Excavation, Ducts supply


and installation , Laying of Red tiles, Warning tape, Backfilling with
9 23040 m As per Drawings
compaction and approved Cable markers post with plate (TRENCH
TYPE 3)

*DRAIN CHANNEL (600MM (W) x 150MM (D) - APPROXIMATELY


10 6000 m As per Drawings
6000/LM
Construction of duct banks for cable routing crossing under the
11 410 m As per Drawings
roads (TRENCH TYPE 1)

Construction of duct banks for cable routing crossing under the


12 400 m As per Drawings
roads including pipe ducts and reinstatement. (TRENCH TYPE 3)

13 Manhole 1500x1500x1500 as per drawing 9 Nos As per Drawings

14 Handhole 850x850x850 as per drawing 128 Nos As per Drawings


Supply and installation of Pipe 75mmØ HDPE pipe, steel andchor
15 706 Lm As per Drawings
and necessary grouts to complete the job.

* PLEASE NOTE: ALL MATERIALS RELATED TO CIVIL SCOPE OF WORKS WILL BE SUPPLIED & CONSTRUCTED BY SUB-CONTRACTOR, CLIENT WILL SUPPLY
NOTE MATERAILS RELATED TO FENCE ONLY & INSTALLATION OR FIXING OF FENCE SUB-CONTRACTOR