a. FOOTING 50 MM
b. COLUMN 40 MM
c. COPING,STAIR,LINTEL,ETC. 15 MM
d. BEAM 25 MM
e. SLAB 15 MM
17. ALL 9" & 14" BRICK WORK MUST BE IN CM(1:6) AND 4.5"
BRICK WORK MUST BE IN CM(1:4).
18. AS PER IS 4326 AND IS 13828 BANDS ARE PROVIDED AT
PLINTH LEVEL, SILL LEVEL AND LINTEL LEVEL AS PER
DESIGN.
19. AS PER IS 4326 HORIZONTAL BAR ARE PROVIDED IN ALL
4.5"THK. BRICK WORK AT EVERY 4TH LAYER
OTHERWISE SPECIFIED.
23. CHAIR OF APROOVED TYPES SHALL BE USED
TO SUPPORT THE SLAB STEEL WHERE NECESSARY
24. CURING MUST BE CARRY OUT AFTER NEXT DAY OF
EXECUTION OF CONCRETE , MASONARY , PLASTER
ETC. UP TO 10 DAYS CONTINUOUSLY THREE TIMES
IN A DAY