DESIGN ACTUAL

DATE OF POURING STRUCTURE LOCATION STRENGTH VOLUME

Second Lift
OCT. 2, 2019 A5,C7,D7,E7,F7,G7,G6 6,000 Psi 14 cu.m.
Column

OCT. 4, 2019 Elevator Pit Elevator Slab : G12 & J10 4,000 Psi 14 cu.m.

Second Lift
OCT. 4, 2019 A7,B7,A8,B8,E8,F8 6,000 Psi 15 cu.m.
Column

OCT. 5, 2019 Cistern Tank Bottom Slab GL.: H-J/11-12 4,000 Psi 253 cu.m.

Second Lift J6,H7,J7,C8,D8,A9,B9,C9 &


OCT. 7, 2019 6,000 Psi 19 cu.m.
Column & Pedestal D10(Pedestal)

OCT. 7, 2019 Elevator Pit Wall D10 4,000 Psi 8 cu.m.

OCT. 9, 2019 Slab On Grade GL.: 2-4/ E-J 4,000 Psi 352 cu.m.

OCT. 12, 2019 Slab On Grade GL.: 4-5/ E-J 4,000 Psi 300 cu.m.

OCT. 14, 2019 Elevator Pit Wall J10 & G12 4,000 Psi 30 cu.m.

Second Lift
OCT. 14, 2019 Column C6,G8,H8,J8,F9,J9,E10,F10 6,000 Psi 22 cu.m.

Second Floor
OCT. 15, 2019 Suspended Slab GL. : 1-2/A-C 6,000 Psi 170 cu.m.

OCT. 16, 2019 Slab On Grade GL. : 1-2/D-E 4,000 Psi 105 cu.m.

OCT. 19, 2019 Slab On Grade GL. : 2-5/A-C 4,000 Psi 377 cu.m.

OCT. 21, 2019 Cistern Tank Wall GL. : 11-12/H-J 4,000 Psi 94 cu.m.

Cistern Tank
OCT. 21, 2019 Column H11, H12, J11, J12 6,000 Psi 16 cu.m.

Escalator Wall
OCT. 23, 2019 GL.: D-E/3-4 4,000 Psi 25 cu.m.
(FTB)

Second Floor
OCT. 24, 2019 Suspended Slab GL.: C-F/1-2 6,000 Psi 278 cu.m.

Second Lift A10,A11,E11,F11,A12,B12,C12,D1


OCT. 26, 2019 6,000 Psi 20 cu.m.
Column 2,E12,F12
Second Floor
OCT. 29, 2019 GL.: F-J/ 1-2 4,000 Psi 346 cu.m.
Suspended Slab

Second Lift
OCT. 31, 2019 D9,E9,B10,C10,B11,C11 6,000 Psi 14 cu.m.
Column