Professional Documents
Culture Documents
FOR THE
LAYING OF CONVEYING MAIN TO CREEK OF
BUCKINGHAM CANAL FOR THE DISCHARGE OF
TREATED SEWAGE
FROM THE PROPOSED CONSTRUCTION OF 6 MLD STP
AT
S.NO: 45/1 OF NAVALUR VILLAGE, TIRUPORUR TALUK,
KANCHEEPURAM DISTRICT,
TAMIL NADU
PROJECT PROPONENT
PREPARED BY
INDEX
S.NO. CONTENTS PAGE NO
FORM I i - xiv
EXECUTIVE SUMMARY I-X
1. INTRODUCTION
1.1 Preamble 1
1.1.1 Expansion of City Limit 1
1.1.2 Status of Implementing Water Supply Schemes in the 2
Expanded City limit
1.1.3 Source of Water Supply 2
1.1.4 Sewerage System of Chennai 2
1.2 Need For the Study 3
1.3 Need for the Environmental Assessment Study 3
1.4 Scope of the Study 3
1.5 Methodology 4
1.6 Study Area 4
1.7 components of the study 5
1.8 Structure of the Report 6
2. PROJECT DESCRIPTION
2.1 Project Background 7
2.2 Environmental Settings And Salient Features Of Project Site 7
2.3 Navalur Sewage Treatment Plant 14
2.4 Project Cost 14
2.5 Road Connectivity 16
2.6 Manpower 16
2.7 Technical Description of the Project 18
2.7.1 Site Selection 18
2.7.2 Selection of treatment process 18
2.7.3 Description of Treatment Process 18
2.8 Legal, Policy & Administrative Frame Work 22
3. DESCRIPTION OF THE ENVIRONMENT
3.1 Introduction 27
3.2 Scope of Baseline Study 27
3.1 Sampling Locations 31
3.4 Micrometeorology 31
3.4.1 Temperature 31
3.4.2 Rainfall 31
3.4.3 Relative Humidity 33
3.4.4 Wind Speed & Direction 34
3.4.1 Cloud Cover 35
3.5 Air Environment 35
3.5.1 Monitoring Location and Methodology 35
3.2 Noise Environment 40
3.3 Water Environment 43
3.4 Land Environment 49
A JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 1
LIST OF TABLES
TABLE CONTENTS PAGE NO
NO
1.1 Availability of Treated Effluent with STP Details 2
2.1 Environmental Settings and Salient Features of Project Site 7
2.2 Project Cost Break up 14
2.3 Manpower 16
3.1 Baseline environmental components & their attributes, frequency 28
& monitoring methodology
3.2 Rainfall data for the Kancheepuram district form 1980 - 2015 32
3.3 Techniques used for baseline analysis 36
B JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 1
LIST OF FIGURES
FIGURE CONTENTS PAGE NO
NO
2.1 Satellite Imagery of the project site 8
2.2 Contour Map of the study area 9
2.3 Topo Map of the Project Site 10
2.4 Drainage map of the Project Site 11
2.5 Road network of the project site 12
2.6 Land Use Map of Project Site 13
2.7 Local Connectivity of Project Site 16
2.8 Overall Linkage to STP 17
3.1 Rainfall data for last five years (2010-2015) 33
3.2 Wind Rose Diagram (May 2015 To July 2015) 34
3.3 Ambient Air Monitoring Locations 39
3.4 Noise Monitoring Locations 41
3.5 Water Sampling Locations 45
3.6 Soil Sampling Locations 52
3.7 Population Details 57
C JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 1
LIST OF ANNEXURES
D JULY 2016
FORM I
EXECUTIVE SUMMARY
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
EXECUTIVE SUMMARY
EXECUTIVE SUMMARY
GENERAL
The estimated cost for the construction of 6 MLD capacity Sewage Treatment Plant is Rs.
6.505 crores, which has been proposed under the scheme of Jawaharlal Nehru National
Urban Renewal Mission. There are two STPs (STP capacity - 79 MLD, 72 MLD) at
Perungudi which has already been constructed as zone V. The land proposed for
construction belongs to CMWSSB. The available land area is 1.11.0 Hectares and the
I JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
EXECUTIVE SUMMARY
7. Topography Plain
8. National parks / Wildlife Aringar Anna Zoological Park - 14.2 km
Sanctuaries (WNW)
II JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
EXECUTIVE SUMMARY
(NNW)
Nanmangalam Reserve Forest - 10.2 km
(NW)
11. Seismicity Zone III (Moderate) as per Seismic Zone map of
India
The baseline environmental data was collected from 10 km radius around the site (study
area) to assess the impacts during the proposed activities of the project.
a) Meteorology
Meteorological data was collected during the period (May - July 2015). Wind speed, Wind
direction, Temperature and Relative humidity were recorded on hourly basis. The
minimum and maximum temperature during summer and winter vary between 34°C and
26°C. High relative humidity between 67 and 85% prevail throughout the year. Higher
rates of relative humidity are observed between November and January i.e., 83 to 85%.
b) Air Quality
Around 7 air quality locations were monitored for SO 2 , NOx, PM 2.5 and PM 10 in the study
area.
PM 10 : A maximum value of 57.2 µg/m3 was observed at Siruseri and next higher value
of 53.7 µg/m3 was observed at Semmancheri. The lower value of 38.4 µg/m3 was
observed at project site Navalur.
Sox & NOx: SO 2 was found to be high at Siruseri of 8.53 µg / m3 and below detection
limit at Kazhipathur and Thazhampur. NO X was found to be maximum value of 17.4 µg /
m3 at Siruseri and minimum value of 8.2 µg / m3 at the project site.
The observed air pollutants were within the limits as per NAAQ standards.
c) Water Quality
The water quality was assessed in seven locations.
Surface Water:
TDS values was found to be 8136 mg/l. Perusal on the ionic contents of the surface
water sources, the quality of surface resource are fresh to brackish in nature.
Based on the physic-chemical analysis, the surface water samples are unacceptable
for drinking purposes.
Dissolved oxygen levels of the surface water are more than 4.3 mg/l which indicate
that surface water source are good medium for aquatic life.
It was also noted that coliforms are observed in the surface water samples
(>2400/100ml)
Ground Water:
• The pH of ground water in the study area varies from 7.32 to 8.01.
• TDS values were found to be 446 to 1798 mg/l and Total Hardness is 80 to 1071
mg/l. This indicates that water in the study area were soft to moderately hard in
nature
• The concentration of sodium in the studied samples is 130 to 260 mg/l. The
potassium content is 2.2 to 64 mg/l.
• The chloride content in the studied area is 132 to 607 mg/l. The sulphate, nitrate
and fluoride content in the ground water are found to be within the IS standards in
all the samples.
d) Noise Quality
Noise levels during day time were observed during day time were found to be in the
range of 47.3 to 54.3 dB (A). Noise levels observed during night time fall in the range of
40.7 to 44.7 dB (A). The observed ambient noise levels were within the standards
prescribed by CPCB.
e) Soil Quality
The soil quality was assessed in eight locations. The results are as follows:
• The pH of the soil ranges from 7.24 to 8.61. The Electrical Conductivity was
observed in the range of 0.082 - 0.784 mS/cm.
• The nitrogen values were found to be in the range of 11 - 53.6 mg/kg indicating
that soils have very low Nitrogen levels.
• The Phosphorous values were found to be in the range 23.4 - 82.6 mg/kg
indicating that soils have an average Phosphorous levels.
• The Potassium values range between 183 - 344 mg/kg and the Organic matter
(%) values range between 0.46 - 1.92.
The soil from the study area shows that they were less fertile.
IV JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
EXECUTIVE SUMMARY
f) Socio-Economic
A sample survey has been conducted to collect qualitative information about socio-
economic environment of the area. The main occupation of the villages surrounding plant
and conveying main is agriculture and allied activities.
g) Ecological Environment
Ecological survey was done to understand baseline ecological status, important floristic
elements, fauna structure. As per baseline studies, there were no endangered,
threatened & protected plants and animal species were recorded in the study area.
Hence, no significant adverse impact was envisaged on ecology.
PROJECT DESCRIPTION
The sewer lines proposed along IT Corridor will receive sewage from the abutting
developments such as industries/IT firms, Educational institutions, etc. This sewer line
will convey the sewage to the sewage pumping stations proposed in each suburban
nodal area. The sewage generated in the segments of Kottivakkam and Perungudi will be
conveyed to Perungudi STP of Metro Sewerage System. Since the conveyance of sewage
from rest of the segments along IT Corridor to Perungudi STP is not cost effective due to
conveyance through long distance, it is proposed to construct 14 numbers of sewage
pumping stations and 3 numbers of STP for localized treatment and disposal. The STP
are proposed in the eastern segment of the suburban nodal areas for the disposal of
treated effluent to nearby Creek.
Receiving of Sewage
Raw Sewage will be received through sewage pumping main(s) from the
respective Pump Stations located abutting IT Corridor (i.e from Semmenchery (East),
Semmenchery (West), Navalur (East), Navalur (West), Ekkatur & Kazhipatur) and
terminated at the Inlet Channel.
PROCESS DESCRIPTION
The sewage treatment plant is based on conventional activated sludge process
with primary and secondary treatment and anaerobic sludge digestion according to the
CPHEEO. The removal of oil & grease will be achieved in various stages of the treatment.
V JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
EXECUTIVE SUMMARY
Inlet Chamber
An Inlet chamber provided to receive the raw Sewage from the pumping stations.
An overflow weir is provided to the bypass channel to balancing tank, which receives raw
sewage during peak flow. This sewage will be pumped back into the inlet chamber for
treatment during lean flow.
Screen Chamber
There shall be one number of manual bar screen chambers. The size of Screen
Chamber is 6m x 1 m x 2 m. The sewage is subjected to screening in the bar screens so
that the coarse material will be screened and the choked screen will be cleaned manually
and mechanically at regular interval.
Detritus Tank
The flow from the screen chambers shall be allowed into the detritus tanks for
removal of grit/inorganic matter. Two No’s Detritus Tanks each of size 2.5 m x 2.5 m x
1.0 m LO shall be provided. The detritus tanks shall be equipped with scraper
mechanism for collecting and scraping the grit into the grit washing channel. The grit
classifier shall lift the grit from the detritus tanks and drop it to the wheel barrow, kept
at the ground level.
Parshall Flume
The grit free sewage emerging from the detritus tanks shall be measured in a
Parshall flume of size 0.6m length, width 0.315m and 0.15m throat width, for the
monitoring of flow. The Parshall flume will be connected on the upstream side and
downstream side with channels
Primary Clarifier
Primary Clarifiers (Two nos.), each of size 15 m dia x 3.5 m shall be provided.
Each Primary clarifier shall receive the raw sewage and supernatant from the thickener
and digesters. The primary clarifier shall be in circular in shape and of radial flow type.
The flow shall be received from the distribution chamber at the bottom and flow through
the opening at the top, radially towards the periphery. The flow at the periphery of the
clarifier shall overflow over the weir and the clarified effluent shall be conveyed to the
VI JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
EXECUTIVE SUMMARY
inlet chamber of the aeration tank, through the central channel. The sludge which shall
be settling on the floor of the clarifier shall be scrapped to the central pit from where it
shall be conveyed, by pumping to the primary sludge sump and pumped to the inlet
chamber of sludge thickener. A scum box shall be provided to collect the surface scum
swept by the surface skimmer.
Aeration Tank
In each compartment, the sewage free from course and grit particles shall be aerated
with the help of Diffused aerators to maintain about 1.5 mg/L of dissolved oxygen in the
aeration tank. The organics undergo biological oxidation by maintaining required MLSS,
by recirculation of aerated sludge from the secondary clarifiers. The mixed liquor
overflows the adjustable type rectangular weir into a common channel, leading to the
distribution chamber, upstream of secondary clarifiers. The mixed liquor overflows the
adjustable type rectangular weir into a common channel, leading to the distribution
chamber, upstream of secondary clarifiers.
a) Construction Phase:
fire services. Also clearance should be obtained from Tamilnadu Coastal Zone
Management authority, as there is discharge of treated water to nearby Creek.
Reduction of fresh water consumption by industries and more fresh water shall be
made available for potable use in the city
The project will also be able to meet the industries increasing fresh water demands
in future. Meeting the growing needs of industries for fresh water supply by the
water supply authorities would also be difficult since the fresh water requirement of
the city also increases in time.
Employment generation in terms of skilled and un-skilled manpower due to plant
construction and operation.
IX JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
EXECUTIVE SUMMARY
X JULY 2016
CHAPTERS
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 1 - INTRODUCTION
1. INTRODUCTION
1. 1 PREAMBLE
Chennai Metropolitan Area (CMA) spread over an area of 1189 sq.km and
comprises of Chennai City, Municipalities, Town Panchayats and Village Panchayats
comprised in Panchayat unions and one cantonment namely St. Thomas Mount. The city
population as per the 2011 census was about 4.681 million and that of the Chennai
Metropolitan area was 8.917 million. Rapid urbanization is taking place not only in the
city but also in the surrounding urban local bodies (ULBs), Municipal areas, and Town
Panchayats. Due to this rapid urbanization, it warrants for providing essential
infrastructures such as road, street lights. EB-cables, water supply, sewerage and solid
waste disposal etc., Chennai Metropolitan Water Supply and Sewerage Board (CMWSSB)
is a statutory responsible body for providing water supply and sewerage infrastructures
for the entire city and CMA. Though its present operation is limited to the Greater
Chennai Corporation City limit, the Board is extending its services to entire CMA
according to the need in phased manner.
Urban development schemes in the notified areas are governed by the Master
plan of Chennai Metropolitan Development Authority (CMDA). The respective Local
Bodies are responsible for the infrastructural facilities. Chennai Metropolitan Water
supply and Sewerage Board (CMWSSB) is the authorized agency to provide water supply
and sewerage - facilities to some of the Local Bodies around Chennai in the CMA and all
the areas within Chennai corporation limit. Chennai city sewerage system comprises of
12 Sewage Treatment Plants (STPs) which are located at Kodungaiyur (3 Nos - 270
MLD), Koyambedu (2 Nos - 94 MLD), Villivakkam (1 No - 5 MLD) Nesapakkam (3 Nos -
117 MLD) and Perungudi (2 Nos - 126 MLD) and Alandur (1 No - 12 MLD).
The city limit was expanded in the year 1978 by adding erstwhile 15 Panchayats
adjoining the City and extended to an area of 174 sq. km. CMWSSB covered of providing
water supply and sewerage infrastructures to the entire city since its formation in 1978.
Such infrastructures now being provided by the urban local bodies are insufficient.
Hence, it was felt essential to expand the city by annexing the deserving urban local
bodies contiguous to the Chennai City.
In view of the above, the Government vide G.O. (Ms) No: 256, MA&WS (Election)
Department, dated 26.12.2009 expanded the City by adding 9 Municipalities, 8 Town
Panchayats and 25 Village Panchayats. The extent of the expanded City limit is 426
sq.km. As directed in G.O. the basic activities such as zoning the area based on the
1 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 1 - INTRODUCTION
population etc., have been carried out for formation of new city by the Corporation of
Chennai.
1.1.2 Status of Implementing Water Supply Schemes in the Expanded City limit
CMWSSB is already implementing water supply schemes in few Local Bodies (LBs)
in Chennai Metropolitan Area under JNNURM etc., and they are in various stages of
completion.
The main source of water supply to the Chennai city is from surface water
sources such as Poondi, Cholavaram, Chembarambakkam, Veeranam lake near Neyveli
and Red hills reservoirs thorough pipelines to city besides ground water sources
from Araniar and Kortalaiyar basin. Chennai city does not have any perennial source of
water. The water supply has been augmented by Krishna Water Supply scheme with
supply of water from the State of Andhra Pradesh and by Chennai Water Supply
Augmentation Project with supply of water from Veeranam Tank.
The Sewerage System for Chennai City has been divided into 5 drainage zones.
These zones of macro systems covering the entire city have independent zonal
collections conveyance, treatment and disposal facilities. There are 12 plants in Chennai
city having a total treatment capacity of 732 MLD. Details of STPs available in Chennai is
given in the below
2 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 1 - INTRODUCTION
13. Alandur 12
Rapid urbanization has resulted in a significant impact on the environment. All the
concerned authorities have realized that development cannot be sustained unless the
environment is protected. Therefore, most of the governments in the world have made it
mandatory for project developers to carryout Environmental Assessment (EA) of their
development project(s) and prepare Environmental Management Plans (EMPs) so that
the environmental quality is protected. The proposed project of providing Sewage
Treatment Plant falls under E2 category of the Environmental and Social Management
Framework of TNSUDP and hence environmental assessment is to be carried out, and
necessary management measures are to be prepared for implementation.
To assess the effect on Land, Air, Water and Noise environment and measures
proposed and to take mitigation measure for any adverse effects.
To assess impact on wildlife (including birds) habitat in project area, if any;
Assessment of impact on flora and fauna which would possibly be affected by the
project and to suggest plans for their conservation.
To collect available water quality data; observe and analyze water quality at the
project area and to collect information on known pollution sources in the area
3 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 1 - INTRODUCTION
To evaluate the impact of the project on public health, quality of life etc. during
construction and after commissioning of the project.
To assess impact on human settlements in project area, if any. To assess impact
of project on existing and proposed infrastructure including roads and to identify
measures for overcoming the same.
Analysis of Census data for demographic profile.
Preparation of environmental monitoring plan for construction and operational
phases.
Identifying mitigatory measures.
Preparation of sound Environment Management plan (EMP) outlining additional
control technologies to be adopted for mitigation of adverse impacts, if any.
1. 5 METHODOLOGY
b. Conveying Main:
The conveying main will be laid to the Creek of Buckingham Canal with an 800 mm dia
CI pipeline and adequate length to discharge treated sewage by pumping. Moreover the
proposed conveying main will be laid below ground level hence there will be no
disturbance to the existing overhead electric lines. The conveying main will be laid in
4 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 1 - INTRODUCTION
such a manner that there won’t be any possibility of cross connection either with the
sewer line or water line.
A. Air Environment
The description of the existing air environment in and around the proposed
project site is based on actual monitoring during the month of May to July 2015. The
concentrations of important air pollutants like PM 10 , PM 2.5 , SO 2 and NOx at the study
area are well within the permissible limits prescribed by Central Pollution Control Board
(CPCB).
B. Noise Environment
The baseline noise levels in and around 10 km radius of the proposed Project Site
were established as per the Noise Pollution Level (Regulation and Control) Rules, 2000 in
line with the Ambient Air Quality monitoring stations.
C. Water Environment
The baseline water environment in and around 10 km radius of the proposed
Project Site were established in line with the ISO 19001 Standards. There is no major
river system in the 10 Km radius of the Project Site. Creek of Buckingham canal is at a
distance of 300 m away from the project site boundary. Discharge of treated water into
creek of Buckingham Canal requires CRZ clearance.
D. Land Environment
Soil samples were collected from the project site, not only at its immediate
vicinity but also in the surrounding villages in the study area. Physico-chemical
properties of the soils were determined; information on land use pattern in the study
area was also collected. The proposed STP site is located in the Urbanisable Use Zone
as per MLPA land use plan.
E. Ecosystem
Information on eco-system within the study area was collected from the State
Agricultural and Forest departments. The important floral species native to the project
area is enumerated and discussed in the Chapter 3. A physical survey was also
undertaken to validate the correctness of the data collected.
5 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 1 - INTRODUCTION
EXECUTIVE SUMMARY
CHAPTER 1 - INTRODUCTION
CHAPTER 2 - PROJECT DESCRIPTION
CHAPTER 3 - DESCRIPTION OF ENVIRONMENT
CHAPTER 4 - ENVIRONMENTAL IMPACT ASSESSMENT
CHAPTER 5 - ENVIRONMENTAL MANAGEMENT PLAN
CHAPTER 6 - SUMMARY & CONCLUSION
CHAPTER 7 - DISCLOSURE OF CONSULTANT
6 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 2 - PROJECT DESCRIPTION
2. PROJECT DESCRIPTION
PARTICULARS DETAILS
Site Location Navalur Village
Site Coordinate 12°50'39.00" N, 80°13'48.03" E
Laying of conveying main Latitude (Pipeline) - 12°50'42.15" N, 12°50'42.73" N
Longitude (Pipeline) - 80°13'48.98" E, 80°13'53.43" E
Discharge point Coordinate 12°50'42.77" N, 80°14'06.81" E
Topography Plain
Present Land use Urbanisable Use Zone (As per Mamallapuram Local
Planning Authority)
SOI Topo sheet 66 D/1 and 66 D/5
Above Mean Sea level in m 2.27
Population of the project village 767
Navalur Bus Stop - 0.38 km (W)
Meera Nagar Bus Stop - 1.2 km (E)
Nearest Bus Stand/stop
Kanathur Bus Stop - 1.4 km (NE)
Muttukaadu Bus Stop - 1.8 km (SE)
Velachery Railway Station - 13.7 km (NNW)
Nearest railway station
Perungudi Railway Station - 14.6 km (N)
Nearest Airport Chennai International Airport - 16.9 km (NW)
Semmancheri - 1.7 km (N)
Muttukadu - 2.7 km (SSE)
Nearest town / city
Kanathur - 2.9 km (NE)
Sithalapakkam - 5.5 km (NW)
7 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 2 - PROJECT DESCRIPTION
8 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
3.5
2.5
5.0
3.5
2.6 4.5
2.5
0.5
1.5
1.5
2.5 3.0
3.0 3.0
9 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
10 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
11 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
12 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
13 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
The total project cost is estimated as Rs. 650 Lakhs is shown in Table 2.2. The total
operation and maintenance cost for a period of five years is estimated as Rs. 650 Lakhs
is given in Table 2.3.
TABLE 2.2 PROJECT COST BREAK UP
S. AMOUNT
DESCRIPTION IN Rs.
NO
Lakhs
1. Construction of Inlet Chamber 1.87
2. Construction of Parshall flume (2 Nos.) 0.48
3. Construction of Screen Chamber including Electrical, Mechanical and
10.30
Instrumentation works complete.
4. Construction of Detritus Tank (2 Nos.) including Electrical, Mechanical
5.85
and Instrumentation works complete.
5. Construction of Balancing Tank including Electrical, Mechanical, and
10.54
Instrumentation works complete.
6. Construction of RC.C. Distribution chamber for Primary Clarifier
8.65
including Electrical, Mechanical and Instrumentation works complete.
7. Construction of Primary Clarifier (2 Nos) including Electrical, Mechanical
37.57
and Instrumentation works complete
8. Construction of RC.C. distribution chamber for Aeration Tank including
41.50
Electrical, Mechanical and Instrumentation works complete
9. Construction of Aeration Tank (2 Compartments) including Electrical,
122.50
Mechanical and Instrumentation works complete
10. Construction of RC.C. Distribution chamber for Secondary Clarifier
8.65
including Electrical, Mechanical and Instrumentation works complete
11. Construction of Secondary Clarifier (2 Nos) including Electrical,
51.26
Mechanical and Instrumentation works complete
12. Construction of Dilution water sump including Electrical, Mechanical
7.65
and Instrumentation works complete
13. Construction of Primary Sludge collection sump including Electrical,
14.10
Mechanical and Instrumentation works complete
14. Construction of Sludge Thickener including Electrical, Mechanical and
22.05
Instrumentation works complete 14.10
14 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
31. Construction of Compound wall around STP site for an average height
16.00
of 2.5 m above GL height of 2.5 m above GL
32. Provision for formation of Road 8.00
33. Provision for construction of storm water drain 4.00
34. Provision for Pavement for a width of 1.2 m 4.00
35. Provision for Electrical power supply 15.00
36. Lighting arrangement around STP 9.44
37. Provision for DG set 300 KVA (260 HP)and DG Room 32.34
38. Water Supply arrangement 0.70
39. Commissioning Test for the whole of the works for 12 weeks 7.95
TOTAL 621.72
PHYSICAL CONTINGENCIES 28.28
FOR 1 NO. STP @6MLD CAPACITY (SAY) 650.00
15 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
The proposed project site is been well connected with road ways. The project site is
situated along East direction on Rajiv Gandhi Salai IT Expressway - Old Mahabalipuram
Road (OMR) at distance of 0.37 km from the proposed site.
2.6 MANPOWER
During Construction phase, 100 persons will be employed in peak period and an average
of 50 persons in normal period.
The STP will have skilled and unskilled employees for its three shift operation. Table 2.3
shows the total manpower requirement for the STP.
TABLE 0.3 MANPOWER
16 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
17 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
The Activated Sludge Process (ASP) sewage treatment process is selected as a major
process unit for the Proposed Sewage Treatment Plant. The sewage will be received from
the abutting developments such as Industries/ IT firms, Educational Institutions in the
following villages only along IT Corridor:
• Sholinganallur (Part)
• Semmenchery
• Navalur
• Egatoor
• Kazhipattur (Part)
Receiving of Sewage
Raw Sewage will be received through sewage pumping main(s) from the respective
Pump Stations located abutting IT Corridor (i.e from Semmenchery (East),
Semmenchery (West), Navalur (East), Navalur (West), Egatoor & Kazhipatur) and
terminated at the Inlet Channel.
PROCESS DESCRIPTION
The sewage treatment plant is based on conventional activated sludge process with
primary and secondary treatment and anaerobic sludge digestion according to the
CPHEEO. The removal of oil & grease will be achieved in various stages of the treatment.
Inlet Chamber
An Inlet chamber provided to receive the raw Sewage from the pumping stations. An
overflow weir is provided to the bypass channel to balancing tank, which receives raw
sewage during peak flow. This sewage will be pumped back into the inlet chamber for
treatment during lean flow.
18 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
Screen Chamber
There shall be one number of manual bar screen chambers. The size of Screen Chamber
is 6m x 1 m x 2 m. The sewage is subjected to screening in the bar screens so that the
coarse material will be screened and the choked screen will be cleaned manually and
mechanically at regular interval.
Detritus Tank
The flow from the screen chambers shall be allowed into the detritus tanks for removal
of grit/inorganic matter. Two No’s Detritus Tanks each of size 2.5 m x 2.5 m x 1.0 m LD
shall be provided. The detritus tanks shall be equipped with scraper mechanism for
collecting and scraping the grit into the grit washing channel. The grit classifier shall lift
the grit from the detritus tanks and drop it to the wheel barrow, kept at the ground
level.
Parshall Flume
The grit free sewage emerging from the detritus tanks shall be measured in a parshall
flume of size 0.6m length, width 0.315 m and 0.15 m throat width, for the monitoring of
flow. The parshall flume will be connected on the upstream side and downstream side
with channels
Distribution chamber (1 No.) shall be provided to divide the screened, de-gritted sewage
received from the parshall flume info the proposed primary clarifiers, equally. The
division of flow shall be controlled by means of penstock gates which shall facilitate
isolation of anyone or more clarifiers. The distribution shall have a bypass outlet with
penstock gate for diversion of sewage, when required.
Primary Clarifier
Primary Clarifiers (Two nos.), each of size 15 m dia x 3.5 m shall be provided. Each
Primary clarifier shall receive the raw sewage and supernatant from the thickener and
digesters. The primary clarifier shall be in circular in shape and of radial flow type. The
flow shall be received from the distribution chamber at the bottom and flow through the
opening at the top, radially towards the periphery. The flow at the periphery of the
clarifier shall overflow over the weir and the clarified effluent shall be conveyed to the
inlet chamber of the aeration tank, through the central channel. The sludge which shall
be settling on the floor of the clarifier shall be scrapped to the central pit from where it
shall be conveyed, by pumping to the primary sludge sump and pumped to the inlet
19 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
chamber of sludge thickener. A scum box shall be provided to collect the surface scum
swept by the surface skimmer.
Aeration Tank
The activated sludge process consisting of aeration tank (One no) 2 compartments with
fixed type diffused aerators for the secondary treatment. The size of each compartment
is 15 m x 15 m x 3.6 m to receive an average flow of 6 MLD plus return sludge shall be
provided. The flow into the aeration tank shall enter through a distribution chamber
before it enters the feed channel of Aeration Tank.
The capacity, size and design of the aeration tank are based on the following criteria:
In each compartment, the sewage free from coarse and grit particles shall be aerated
with the help of Diffused aerators to maintain about 1.5 mg/L of dissolved oxygen in the
aeration tank. The organics undergo biological oxidation by maintaining required MLSS,
by recirculation of aerated sludge from the secondary clarifiers. The mixed liquor
overflows the adjustable type rectangular weir into a common channel, leading to the
distribution chamber, upstream of secondary clarifiers. The mixed liquor overflows the
adjustable type rectangular weir into a common channel, leading to the distribution
chamber, upstream of secondary clarifiers.
The mixed liquor from the outlet channel of Aeration Tank shall be distributed to
secondary clarifiers through a distribution chamber provided with penstock gates.
Secondary Clarifier
Secondary clarifiers (Two Nos.), each of size 16 m dia x 3.5 m shall be provided. Each
secondary clarifier shall be designed for a capacity of 4.5 MLD average flows. The mixed
liquor shall enter the Secondary clarifiers where the aerated sludge settles down and
scrapped to the centre by a central driven mechanical scraper mechanism. The V-notch
overflow weir provided at the peripheral overflow launder of secondary clarifiers shall
ensure smooth overflow of the clarified treated sewage, reducing the chances of
carryover of solids.
20 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
One No. sludge recirculation sump of size 5.5 m dia x 3.5 m shall be provided to receive
the secondary bio sludge from the secondary clarifiers. The recycle bio sludge shall be
pumped to the distribution chamber of Aeration Tank. The flow of recycle sludge to
aeration tank shall be measured with the help of a flow indicator. The excess sludge shall
be sent to the inlet chamber of Sludge thickener.
The treated sewage shall overflow into the treated sewage channel which shall be
provided with a sump to house the submersible type dilution water pumps to pump the
treated sewage as dilution water to the inlet chamber of thickener.
Parshall Flume
The treated effluent shall be measured in a parshall flume of size 0.6m length, width
0.315m and 0.15m throat width, for the monitoring of flow.
Sludge from Primary clarifiers shall be distributed into gravity sludge thickeners through
1 No. inlet chamber. Sludge from the Primary clarifiers shall be received by pumping I
gravity to this chamber. The dilution water pumped from Dilution water pump house
shall also be received in this chamber. The sludge withdrawal from the primary clarifiers
will be staggered so that at any given time, only one primary clarifier will be taken up for
the withdrawal of primary sludge.
One No. sludge thickener of size 12 m dia x 2.5 m shall be provided to handle the
primary sludge along with excess activated sludge, from Primary clarifiers. The thickener
shall be of radial flow type and ensures the thickening of sludge to about 5%. The
dilution water will ensure no odour problem in the thickener. The supernatant from-the
thickener shall overflow V-notch weir at the periphery and shall be received in the
supernatant cum filtrate sump. The thickener shall be equipped with a mechanical solid
picket and fence type scraper mechanism to scrape the thickened sludge to the central
pit from where it is discharged into the thickened sludge sump, once a shift for a period
of 4 hours.
A thickened sludge sump of size 2.6 m dia x 2.5 shall receive the thickened sludge from
the thickener and then pumped to the digesters for about 4 hours, in a shift.
21 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
Sludge Digester
Sludge digester of size 18 m dia x 6.5 m shall be provided to receive the thickened
sludge. The thickened sludge will undergo anaerobic deco1nposition in the absence of air
in the closed dome type digesters, producing biogas. The pumping of thickened sludge to
the Digesters shall be staggered and, the supernatant from the Digester shall flow
directly to the distribution chamber of Primary clarifiers, by gravity. The digester shall be
fitted with flame arrestor and pressure cum vacuum relief valve.
One no. supernatant sump and pump of size 3.6 m dia x 2.5 m shall be provided to
receive the Supernatant from Thickener and sludge digest. The supernatant shall be
pumped to the distribution chamber of primary clarifiers.
A main bypass channel will be provided, starting from the inlet chamber and bypassing
the bar screen chambers; it will run between the detritus tanks. When raw sewage is
required to be by passed, it will be allowed to pass through the same channel.
This section reviews the policies, regulations and administrative framework within which
the project is to be implemented. The review includes the Environmental and Social
framework of TNUIFSL, operational policies / directions of the World Bank and sector-
specific environmental policies and regulations of the Govt. of India and Govt. of
Tamilnadu.
These laws seek to control pollution of water and enhance the quality of water. Under
this law, it is mandatory to obtain Consent to Establishment for the proposed plant and
the effluent to be treated to meet the discharge standards of inland surface water and
discharged as per the standards stipulated by TNPCB before discharge into the Canal or
on land for irrigation and pay consent fees as stipulated for local bodies viz., Town
Panchayat, Municipality, Corporation which are causing water pollution.
b) The Air (Prevention and control of pollution) Act, 1981 amended in 1987
This Act provides prevention, control and abatement of air pollution. With a framework
similar to the Water Act, the Air Act gave the central and State Board’s authority to issue
consents to industries operating within the designated air pollution control areas. The
State also prescribes emission standards for stationary and mobile sources.
22 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
In order to create national environmental legislation, the EPA articulates a policy for
environmental protection covering air, water and land and provide a framework for
Central Government to coordinate between Central and State Authorities established
under various laws, including the Water Act and Air Act. Under this umbrella Act, the
Central Government must set National Ambient and Emissions Standards, establish
procedures for managing hazardous substances, regulate industrial sites, investigate and
research pollution issues and establish laboratories and collect and disseminate
information.Among other relevant legislation, the Public Liability Insurance Act (PLIA) of
1991 mandates that business owners operating with hazardous substances take out
insurance policies covering potential liability from an accident and establish
Environmental Relief Funds to deal with accidents involving hazardous substances. The
National Environmental Appellate Authority Act of 1997 requires the Central Government
to establish an authority to hear appeals on area restrictions where operations will not
be carried out or will be carried out with certain safeguard measures.
The Ancient Monuments and Archaeological Sites and Remains Act, 1958 In order to
bring the legislation on par with constitutional provisions and providing better and
effective preservation to the archaeological wealth of the country, The Ancient
Monuments and Archaeological Sites and Remains Act 1958 (No 24 of 1958) was
enacted on 28th August 1958. This Act provides for preservation of ancient and historical
monuments and archaeological sites and remains of national importance, for regulation
of archaeological excavations and for protection of sculptures, carvings and other like
objects. Subsequently, the Ancient Monuments and Archaeological Sites and Remains
Rules 1959 were framed. The Act along with Rules came into force with effect from 15
October 1959. This Act repealed The Ancient and Historical Monuments and
Archaeological Sites and Remains (Declaration of National Importance) Act, 1951.
The Indian Treasure Trove Act, 1878 (Act No. VI of 1878) was promulgated to protect
and preserve treasure found accidentally but having the archaeological and historical
value. This Act was enacted to protect and preserve such treasures and their lawful
disposal. In a landmark development in 1886, James Burgess, the then Director General
succeeded in prevailing upon the Government for issuing directions forbidding any
person or agency to undertake excavation without prior consent of the Archaeological
Survey and debarring officers from disposing of antiquities found or acquired without the
permission of the Government.
23 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
The Antiquities and Art Treasures Act 1972 (No. 52 of 1972) is the latest Act enacted on
9th September 1972 for effective control over the moveable cultural property consisting
of antiquities and art treasures. The Act regulates export trade in antiquities and art
treasures, provides for prevention of smuggling of, and fraudulent dealings in,
antiquities, authorizes compulsory acquisition of antiquities and art treasures for
preservation in public places and provides for certain other matters connected therewith
or incidental or ancillary thereto. This Act was supplemented with The Antiquities and Art
Treasure Rules 1973. The Act and Rules have been in force with effect from 5th April
1976. This legislation repealed The Antiquities Export Control Act, 1947 (Act No. XXXI of
1947)
In order to curb the growing problems of noise pollution, the government of India
has enacted the noise pollution rules 2000 that includes the following main
provisions:
The state government may categorize the areas as industrial or commercial or
residential.
The Ambient air quality Standards in respect of Noise for different areas has been
specified.
The State government shall take measures for abatement of noise including noise
emanating from vehicular movement and ensure that the existing noise levels do
not exceed the ambient air quality standards specified under these rules.
Areas not less than 100 m around Hospitals, Educational institutions and Court is
declared as silence area under these rules.
A person found violating the provisions as to the maximum noise permissible in any
particular area shall be liable to be punished for it, under the provision of these
rules and any other law in force.
It defines the terms used in this context, and sets up an authority to inspect, once a
year, the industrial activity connected with hazardous chemicals and storage facilities.
24 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
This notification under Environment (Protection) Act; 1986 supplements the law on site
clearance by declaring certain zones as CRZ and regulates activities in these zones.
Further Govt of TamilNadu has also issued orders regulating development within 500 mts
from the high water mark. The HTL of Buckingham Canal Creek is situated at a distance
of 2 Kms from the project site and this comes under CRZ-II as per CRZ notification
2011. So the conveying main to discharge of treated water into Creek of Buckingham
Canal requires CRZ clearance.
25 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 02 - DESCRIPTION OF ENVIRONMENT
i) The proposed project consisting of STP does not require any acquisition of private
land. This project also does not attract the provisions made under the right to fair
compensation and transparency in land acquisition, rehabilitation and resettlement
act, 2013 and The street vendors protection of livelihood and regulation of street
vending, Act 2014.
26 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 3 - DESCRIPTION OF THE ENVIRONMENT
3. 1 INTRODUCTION
27 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 3 - DESCRIPTION OF THE ENVIRONMENT
TABLE 3.1 BASELINE ENVIRONMENTAL COMPONENTS & THEIR ATTRIBUTES, FREQUENCY & MONITORING METHODOLOGY
Attributes Sampling Measurement Method Remarks
Network Frequency
1. Air Environment
Meteorological Data
• Wind speed At project site Weather Monitoring IS 5182 Part 1-20
• Wind direction (Site specific) Station Site-specific primary data
• Dry bulb temperature is essential Secondary
• Wet bulb temperature data from IMD-Regional
• Relative humidity Meteorological Centre,
• Rainfall Chennai
Ambient Air Quality
• Suspended Particulate Matter (SPM) Requisite locations 24 hourly twice a • Gravimetric (High - As per CPCB Standards
• Particulate Matter (PM 10 ) in the project week Volume) under November 18th
• Particulate Matter (PM 2.5 ) influence area • Gravimetric (High - 2009 Notification for
Volume with Cyclone) NAAQS
• EPA Modified West &
Gaeke method
• Sulphur Di-oxide (SO 2 ) 8 Hourly twice a • Arsenite Modified Jacob &
• Oxides of Nitrogen (NO X ) week Hochheiser
2. Noise Environment
Hourly equivalent noise levels Requisite locations One day Sound level meter IS: 4954-1968
in the project continuous on a
influence area working and non-
working day
28 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 3 - DESCRIPTION OF THE ENVIRONMENT
3. Water environment
Parameters for water quality: pH, temp, Set of grab Once Samples for water quality
turbidity, Total hardness, total alkalinity, samples At collected and analyzed as
chloride, sulphate, nitrate, fluoride, requisite locations per IS : 2488 (Part 1-5)
sodium, potassium, Electrical for ground and methods for sampling and
Conductivity, Ammonical nitrogen, surface water testing of Industrial
Nitrate-Nitrogen total phosphorus, , BOD, effluents Standard
COD, Calcium, Magnesium, Total methods for examination
Dissolved Solids, Total Suspended Solids of water and wastewater
analysis published by
American Public Health
Association.
4. Land Environment
• Soil quality Requisite soil Once Collected and analyzed as
• Particle size distribution samples be per soil analysis reference
• Texture collected as per book, M.L. Jackson
• pH BIS specification
• Electrical conductivity within project
• Caution exchange capacity influence area
• Alkali metals
• Sodium Absorption Ratio (SAR)
• Permeability
• Porosity
5. Land Use
• Location code - - • Global positioning Drainage within the plant
• Total project area system area and surrounding is
• Topography • Topo-sheets very important for storm
• Drainage (natural) • Satellite Imageries water impacts. From land
• Cultivated, forest plantations, water use maps sensitive
bodies, roads and settlements receptors (forests, parks
29 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 3 - DESCRIPTION OF THE ENVIRONMENT
30 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 3 - DESCRIPTION OF THE ENVIRONMENT
3. 3 SAMPLING LOCATIONS
Seven sampling locations are selected for Air, Water, Noise and Soil. All the
samples are analyzed and results are shown in below chapter. The Air, Noise, Water and
Soil Sampling locations were selected based on the following criteria. The Ambient air
quality monitoring locations have been designed keeping in view the available
Climatological norms of predominant wind direction and wind speed of the area.
The following points were also taken into consideration in designing the sampling
locations
Topography and terrain of the study area.
Populated areas within the study area.
Residential and sensitive area within the study area.
For noise monitoring locations the above factors has been considered. Water sampling
locations were collected based on the availability of the bore wells / open wells in the
area. Geological environment has been considered for the collection of Soil sample
collection.
3. 4 MICROMETEROLOGY
3.4.1 Temperature
The mean maximum and minimum temperatures during summer and winter vary
between 34°C and 26°C.
3.4.2 Rainfall
The project experiences rainfall in the southwest and northeast Monsoons. The annual
rainfall is in the range about 1230 mm. Rainfalls are characterized by heavy downpour
resulting in water logging in low-lying area. Gales and cyclones are experienced during
the northeast monsoon. The details of rainfall recorded from 1980 to 2015 is given below
31 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 3 - DESCRIPTION OF THE ENVIRONMENT
TABLE 3.2 RAINFALL DATA FOR THE KANCHEEPURAM DISTRICT FORM 1980 - 2015
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1980 0.6 0.0 1.0 4.7 35.1 25.0 89.1 136.5 54.3 100.1 292.3 113.3
1981 37.2 3.4 9.6 9.5 82.2 55.7 131.3 169.2 221.0 341.7 96.4 119.6
1982 0.3 0.0 4.4 15.0 28.7 55.8 78.3 55.9 104.5 109.3 323.3 70.9
1983 0.2 0.0 4.1 0.6 55.8 53.3 97.9 171.2 226.6 216.2 101.0 367.7
1984 32.6 78.8 58.1 29.7 4.2 24.8 178.7 41.9 157.2 182.4 249.3 134.3
1985 74.3 5.5 2.4 23.8 12.7 44.9 176.2 173.7 312.4 124.3 678.2 109.5
1986 82.4 48.7 0.9 1.4 12.8 20.9 86.6 54.6 118.0 332.5 153.6 116.5
1987 2.2 0.0 20.9 12.3 28.1 63.0 35.6 105.4 53.2 276.8 188.7 308.5
1988 0.1 0.0 2.5 46.6 62.0 63.5 123.5 360.3 263.8 90.0 317.8 103.7
1989 7.6 0.0 32.7 4.5 15.8 79.7 136.2 47.4 226.0 170.4 315.8 124.1
1990 18.2 10.9 23.9 1.6 72.3 39.4 47.9 79.5 188.8 387.5 175.3 70.0
1991 7.4 3.2 1.4 2.2 14.5 77.7 66.1 100.4 122.5 225.8 334.7 14.8
1992 17.7 0.0 0.0 0.8 52.6 27.3 70.6 145.3 80.6 131.7 330.9 120.0
1993 1.4 1.1 2.9 2.0 136.1 74.1 71.0 195.4 65.5 280.3 320.2 318.3
1994 2.4 63.5 1.1 3.8 83.5 32.3 55.3 117.6 45.3 320.2 329.0 40.7
1995 66.8 5.8 14.0 8.1 75.7 27.1 94.9 298.7 202.8 200.0 134.4 18.7
1996 2.1 2.4 0.0 37.1 39.2 141.0 63.8 93.8 206.1 277.3 246.1 347.0
1997 13.3 0.0 3.5 23.4 14.1 59.6 52.1 83.4 80.3 249.1 578.6 314.2
1998 4.5 0.1 0.0 14.2 55.2 21.0 116.7 173.0 69.0 123.5 289.2 255.4
1999 9.2 16.5 0.0 10.5 23.3 64.6 41.2 147.8 117.3 209.4 172.5 73.7
2000 5.4 60.9 0.4 16.2 31.4 60.4 86.6 155.8 238.4 235.8 140.0 75.1
2001 5.0 0.3 0.2 27.1 24.2 80.5 100.1 67.0 141.6 329.6 199.6 201.9
2002 36.0 4.3 0.0 0.7 68.9 22.3 38.8 125.5 123.1 300.9 330.9 53.7
2003 0.0 0.0 14.5 0.0 1.3 57.5 178.8 63.2 162.8 434.4 259.0 274.1
2004 14.2 0.0 7.7 16.4 222.1 41.8 29.2 32.8 313.2 253.2 195.0 3.6
2005 0.0 0.5 9.0 130.0 30.2 32.9 98.9 81.5 80.2 516.4 576.7 377.9
2006 16.1 0.0 26.5 3.7 14.7 87.2 64.7 32.6 129.6 414.5 232.3 57.7
2007 0.0 1.6 0.0 19.4 14.4 69.5 116.8 190.2 154.2 263.6 97.7 296.6
2008 28.8 18.8 150.9 13.5 18.6 52.2 42.0 99.7 117.8 312.4 505.7 36.3
2009 16.0 0.0 6.6 0.0 43.8 22.3 48.7 119.7 132.0 57.9 505.2 174.0
2010 1.0 0.0 0.0 4.4 91.3 107.9 93.3 209.3 116.1 192.0 291.9 260.9
2011 5.6 36.1 0.0 55.9 29.8 36.6 121.3 189.9 180.0 249.1 390.3 181.7
2012 7.9 0.0 0.0 0.1 5.9 31.6 75.1 141.9 93.8 318.4 95.3 132.6
2013 0.0 24.3 13.7 0.0 16.7 73.8 135.3 153.3 172.8 137.1 116.9 61.4
2014 1.02 0 0 0 4.31 103.64 32.02 88.64 29.72 103.12 29.22 123.45
2015 3.0 0.0 0.0 103.1 11.9 14.0 15.0 61.0 23.1 28.1 232.9 436.86
32 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 3 - DESCRIPTION OF THE ENVIRONMENT
FIGURE 3.1 RAINFALL DATA FOR LAST FIVE YEARS (2010 - 2015)
33 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 3 - DESCRIPTION OF THE ENVIRONMENT
Cloud Cover During the winter and the summer seasons, the skies are observed to be
generally very clear. In the post - monsoon season, generally light clouds were observed
in the evenings, with clear mornings. During the monsoon season, both in the mornings
and evenings, the skies were found to be overcast
3. 5 AIR ENVIRONMENT
The Ambient Air Quality (AAQ) status with respect to the study zone of 10 km radial
distance from the plant site formed the baseline information over which the predicted
impacts due to the proposed project were determined based on which the Environmental
Management Plan (EMP) was prepared. The baseline status of the ambient air quality can
be assessed through a scientifically designed ambient air quality-monitoring network
based on the following considerations:
a) Meteorological conditions on synoptic scale
b) Topography of the study area
c) Representations of regional background levels
34 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 3 - DESCRIPTION OF THE ENVIRONMENT
To establish the existing baseline status of air quality in and around the STP site a
network of seven AAQ sampling locations were selected within 10 km aerial distance. The
locations were decided on the basis of meteorological data and the topography of the
area. Further, a monitoring location was selected at the project site to get the baseline
status of the air quality within 10 km around the project site. The techniques used for
baseline analysis is given in Table 3.3. The AAQ sampling locations and their direction
with respect to the project site are given in Table 3.4.
35 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 3 - DESCRIPTION OF THE ENVIRONMENT
36 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 3 - DESCRIPTION OF THE ENVIRONMENT
Industrial
/Residential / Rural 100 60 80 80 400
and Other Area
37 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 3 - DESCRIPTION OF THE ENVIRONMENT
38 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 3 - DESCRIPTION OF THE ENVIRONMENT
The maximum value (PM 10 ) of 57.2 µg/m3 was observed at Siruseri (AAQ6) and next
higher value of 53.7 µg/m3 was observed at Semmancheri (AAQ6). The lower value of
38.4 µg/m3 was observed at Navalur (AAQ1) since it is a residential area. The maximum
value (PM 2.5 ) of 27.3 µg/m3 was observed at Siruseri (AAQ6). Similarly SO 2 and NO 2
were found to be high in Siruseri (AAQ6). However, all the ambient air quality levels are
found to be within the CPCB Standards
3. 6 NOISE ENVIRONMENT
The baseline noise levels in and around 2 km radius of the proposed project site were
established in-line with the Noise Standards. Noise monitoring was carried out at 6
locations. Noise levels were monitored using a calibrated portable noise level recorder on
an hourly basis for 24 hours, once at each location. Levels of noise monitored during 6
AM to 9 PM were considered for the day noise levels and those monitored during 9 PM to
6 AM were considered for night noise levels. The monitored locations and Day and night
Leq values were computed based on the monitored noise levels and are presented in
Table 3.6.
39 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 3 - DESCRIPTION OF THE ENVIRONMENT
40 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 3 - DESCRIPTION OF THE ENVIRONMENT
Direction Distance
Location Geographical with with respect Environmental Leq day Leq Night Leq
Sample location
Code location respect to to project Setting [dB(A)] [dB(A)] [dB(A)]
project site site ( km)
N-12º50’40.21”
N1 Project Site – Navalur - - Empty land 48.3 40.7 46.9
E-80º13’48.44”
N-12º50’34.50”
N3 Kanathur Reddikuppam ESE 1.03 Residential Area 47.3 41.6 46
E-80º14’21.62”
Residential Area
N-12º51’35.51”
N4 Semmancheri N 1.76 / Educational 52.8 43.5 51.2
E-80º13’41.92”
Institution
N-12º49’37.99”
N5 Siruseri SSW 2.15 IT Hub 53.7 44.6 52.1
E-80º13’14.32”
N-12º50’48.95”
N6 Thazhampur W 2.22 Residential Area 49.7 42.3 48.3
E-80º12’35.99”
41 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 03 - DESCRIPTION OF ENVIRONMENT
OBSERVATIONS
3. 7 WATER ENVIRONMENT
Surface water
Creek of Buckingham Canal lies very near to the project (0.300 km) and the treated
sewage will be discharged into the same. Sampling has been conducted and the study
report is given in Table 3.6
Ground water
Ground water table in the study area during pre-monsoon is about 1.5m BGL and about
2m BGL during post monsoon period. The project site located in Thiruporur block which
falls under safe zone (less than 70 %) as per G.O.Ms. No.:52, PWD dt 2.3.2012.
Detailed water quality assessment is necessary in areas where there is intensive ground
water development, Industrialization and urbanization as it is also subjected to
qualitative changes in the environment around. Quality of water is influenced
considerably by the quality of its source and occurrence. In order to describe and assess
the impact on water quality by the proposed project, ground water and surface water
samples at 7 locations were collected within the 10 km radius and tested for physical and
chemical parameters.
Initially, reconnaissance survey was carried out to identify suitable water sample
collection locations. During the reconnaissance survey on site, TDS and pH were tested
and the locations were captured using GPS. While selecting the sampling locations for
detailed hydro geochemical analysis the following were given much importance.
42 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 03 - DESCRIPTION OF ENVIRONMENT
Those water bodies on which human activities could have an impact, either by
utilizing water or by discharging effluents.
Water abstraction and utilization by domestic users.
Six water sources were selected for sampling for ground water and one surface water
sampling was done in Creek of Buckingham Canal during this period. The location and
source of water samples collected are given in Table 3.7 and results are given in 3.8 and
3.9.
Direction Distance
Location Geographical with with respect
Location Type of water
Code location respect to to project
project site site (km)
Navalur (Near N-12º50’42.27”
W1 WNW 0.19 Ground Water
Project Site) E-80º13’42.44”
Kanathur N-12º50’58.56”
W2 ENE 1.22 Ground Water
Reddikuppam E-80º14’24.54”
N-12º49’24.67”
W3 Kazhipathur S 2.32 Ground Water
E-80º13’55.95”
N-12º50’16.09”
W4 Siruseri WSW 1.42 Ground Water
E-80º13’07.79”
N-12º50’56.91”
W5 Thazhampur WNW 2.37 Ground Water
E-80º12’31.21”
N-12º52’18.03”
W6 Semmancheri N 3.04 Ground Water
E-80º13’38.97”
Creek of
N-12º50’37.44”
SW1 Buckingham ESE 0.35 Surface Water
E-80º13’59.59”
Canal - Navalur
43 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 03 - DESCRIPTION OF ENVIRONMENT
44 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 03 - DESCRIPTION OF ENVIRONMENT
S. Limit as per
Parameters Unit Test method W1 W2 W3 W4 W5 W6
No. IS 10500 :
2012
APHA 21st
1 Colour Hazen 5 Nil Nil Nil Nil Nil Nil
EDITION
Un
APHA 21st No Odour No Odour No Odour No Odour No Odour No Odour
2 Odour - Objectionabl
EDITION Observed Observed Observed Observed Observed Observed
e
IS : 3025
3 pH at 25°C - Part 11- 1983 6.5-8.5 7.42 8.01 7.56 7.32 7.32 7.83
(Reaff: 2002)
IS : 3025
Electrical
4 μS/cm Part 14- 1984 Not Specified 1763 1388 2950 1392 1256 760
Conductivity,
(Reaff: 2002)
IS : 3025
BDL BDL BDL
5 Turbidity NTU Part 10-1984 1 0.7 1.0 0.6
(<0.5) (<0.5) (<0.5)
(Reaff: 2002)
Total IS : 3025
6 Dissolved mg/l Part 16-1984 500 950 740 1798 828 708 446
Solids (Reaff: 2003)
Total
IS : 3025
7 Hardness as mg/l 200 230 300 1071 387 94 80
Part 21-2009
CaCO 3
Total IS : 3025
8 Alkalinity as mg/l Part 23 1986 200 320 208 670 430 70 44
CaCO 3 (Reaff:2003)
IS : 3025
Chloride as
9 mg/l Part 32-1988 250 295 132 607 161 245 201
Cl
(Reaff: 2003)
Sulphate as APHA 21st
10 mg/l 200 95 105 82 53 54 42
SO 4 EDI-4500-
45 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 03 - DESCRIPTION OF ENVIRONMENT
SO 4 2- E
APHA 21st
BDL
11 Fluoride as F mg/l EDI-4500-F 1.0 0.27 0.28 0.75 0.42 0.29
(<0.1)
B&D
APHA 21st
Nitrate as
12 mg/l EDI-4500- 45 2 92 30 18 37 27
NO 3
NO 3 - B
APHA 21st
Ammonia as BDL(<0.05 BDL(<0.05 BDL BDL BDL BDL
13 mg/l EDI-4500- Not Specified
NH 3 ) ) (<0.05) (<0.05) (<0.05) (<0.05)
NH 3 B&C
IS : 3025 Part
Phosphate as
14 mg/l 31-1988 Not Specified 0.15 0.08 0.20 0.03 0.05 0.02
PO 4
(Reaff:2002)
IS : 3025 Part
Sodium as
15 mg/l 45-1993 Not Specified 215 130 260 150 225 132
Na
(Reaff:2003)
IS : 3025 Part
Potassium as
16 mg/l 45-1993 Not Specified 64 40 2.5 50 60 2.2
K
(Reaff:2003)
IS : 3025 Part
Calcium as
17 mg/l 40-1991 75 71 94 247 119 18 36.8
Ca
(Reaff:2003)
Magnesium APHA 21st
18 mg/l 30 12 15.5 111 22 12 9.7
as Mg EDITION
IS : 3025 Part BDL(<0.05 BDL BDL BDL BDL
19 Iron as Fe mg/l 0.3 0.12
53-2003 ) (<0.05) (<0.05) (<0.05) (<0.05)
Chemical
IS:3025:Part-
20 Oxygen mg/l Not Specified 10.6 12.2 8.0 BDL(<4) 4.7 BDL(<4)
58:2006
Demand
BDL - Below Detectable Limit
46 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 03 - DESCRIPTION OF ENVIRONMENT
47 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 03 - DESCRIPTION OF ENVIRONMENT
OBSERVATIONS
The pH of ground water in the study area varies from 7.32 to 8.01 and Conductivity
varies from 760 to 2950 µS/cm.
TDS values were found to be from 446 to 1798 mg/l and Total Hardness varied from
80 to 1071 mg/l. This indicates that water in the study area were soft to moderately
hard in nature. The Total alkalinity also varies from 44 to 670 mg/L.
Sodium and potassium are naturally occurring elements of groundwater. Industrial
and domestic wastes also add sodium to groundwater. It is one of the major
contributors to salinity of water. The concentration of sodium in the studied samples
varied from 130 to 260 mg/l. The potassium content ranged from 2.2 to 64 mg/l.
The chloride content in the studied area ranged from 132 to 607 mg/l. The sulphate,
nitrate and fluoride content in the ground water are found to be within the IS
standards in all the samples.
Surface Water
3. 8 LAND ENVIRONMENT
It is essential to determine the type & quality of soil in the study area and identify the
current impacts of urbanization on soil quality and also predict probable impacts due to
the proposed plant. Accordingly, a study of assessment of the baseline soil quality was
carried out.
For studying soil quality of the region, sampling locations were selected to assess the
existing soil conditions in and around the 'Project area based on various land use
conditions. The physical and chemical concentrations were determined. The samples were
collected from different specified depths viz., 30cm, 60cm and 100cm
The present study of the soil quality establishes the baseline characteristics and this will
help in future in identifying the incremental concentrations if any, due to the operation of
48 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 03 - DESCRIPTION OF ENVIRONMENT
the proposed plant. The sampling locations have been identified with the following
objectives
To determine the baseline soil characteristics of the study area.
To determine the impact of proposed project on soil characteristics and
To determine the impact on soils more importantly loss of fertility from
agricultural productivity point of view.
Various locations within 10 km radius of the plant site were selected for soil sampling. At
each location, soil samples were collected from three different depths viz., 30cm, 60cm,
and 100cm below the surface. The samples were analyzed for physical and chemical
characteristics. The samples have been analyzed as per the established scientific
methods for physio-chemical parameters.
Soil Characteristics
Soil Type
Soil type and its fertility of an area are essential to plan for cropping. Soils are primarily
derived from parent rocks. The colour, texture and mineral content are normally used to
classify the soil. The soil in the study area is classified into 3 types. They are as follows.
S. No Soil Classification
Soil quality
To assess the soil quality in the study area, soil sample was collected and analyzed for
physical and chemical parameters as per the standard methods. The sampling locations
are given in Table 3.10.
49 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 03 - DESCRIPTION OF ENVIRONMENT
RESULTS
The existing ambient soil quality at the identified locations is given in Table 3.11
50 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 03 - DESCRIPTION OF ENVIRONMENT
51 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 03 - DESCRIPTION OF ENVIRONMENT
5 Available Potassium, mg/kg FAO Chapter 3/SOP 7 344 216 272 241 183 264
6 Exchangeable Calcium as Ca, m.eq / 100g FAO Chapter 3/SOP 4 10.22 4.19 8.27 9.36 5.74 8.16
7 Exchangeable Magnesium as Mg, m.eq/100g FAO Chapter 3/SOP 4 5.83 3.08 6.12 4.75 4.32 5.14
8 Exchangeable Sodium as Na, m.eq / 100g FAO Chapter 3/SOP 6
1.78 1.92 1.37 0.92 0.45 1.24
IS 2720 Part 22:1972
9 Organic matter (%) 1.92 0.46 1.36 1.02 0.82 1.51
(Reaff:2010)
Robinson Pipette Sandy
Loamy Sandy
10 Texture Classification Method Clay Clay Clay Clay
Sand Clay
Loam
11 Sand (%) 21.4 72.3 36.4 43.7 53.7 28.4
52 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 03 - DESCRIPTION OF ENVIRONMENT
Chemical Ranking
Parameters
Very Low Low Moderate High Very High
pH <4, very 4-5, 5-8, Ideal for 8-9 Strongly >9 Very
Strongly Strongly
Plant Growth Basic Strongly
Acidic Acidic Basic
Electrical <2000, 2000- 4000-8000 8000-16000 >16000
conductivity Non 4000 Moderately Highly Extremely
(μS/cm) saline SalineSaline Saline Saline
Total Nitrogen (%) <0.05 0.05-0.15
0.15-0.25 0.25-0.5 >0.5 Very
Very Low Low Moderate High High
Total Phosphorous <5 5-10 Low
10-30 30-60 High >60 Very
(mg/kg) Very Low Moderate High
Sodium (mg/kg) - <200 Non 200-500 >500 Sodic --
Sodic Moderate
Potassium (mg/kg) - <150 150-250 250-800 >800 Very
Low Moderate High High
Calcium (mg/kg) - <1000 1000-2000 >2000 High -
Low Moderate
Magnesium <40 Very 40-100 100-300 >300 High -
(mg/kg) Low Low Moderate
% Organic Matter 0.5-1.0 1.0-2.0 2.0-3.0 3.0-5.0 High >5 Very
Very Low Low Moderate High
Discussion:
The pH indicates that the soils in the study areas are basic in nature, with the pH varying
in the range of 7.24 to 8.61. The Electrical Conductivity was observed in the range of
0.084 - 0.784 mS/cm.
The Nitrogen values are in the range of 11.0 - 53.6 mg/kg indicating that soils have very
low Nitrogen levels. The Phosphorous values are in the range of 23.4 - 82.6 mg/kg
indicating that soils have high Phosphorous levels. The Potassium values range between
183 - 344 mg/kg, which indicate that the soils have better quantity of Potassium. The
Organic matter (%) values range between 0.46 - 1.82.
3. 9 BIOLOGICAL ENVIRONMENT
The existing Flora and Fauna in the study area is mentioned below. As per Botanical
Survey of India records and available published literature pertaining to the study area
and current detailed study of project site, no threatened, endangered and rare plant
species were observed from the study area. No reserve forest, protected forest, turtle
breeding ground, elephant and /or tiger reserve is within 10 km radius of the project site.
53 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 03 - DESCRIPTION OF ENVIRONMENT
Flora
Some of the common plant species found in the study area are listed in the Table below:
TABLE 3.5 FLORA FOUND IN AND AROUND PROJECT SITE (10 KM RADIUS)
Field studies conducted to assess fauna in study area. On the basis of field studies and
secondary sources, there are no endangered animal species present in the study area.
TABLE 3.64 FAUNA FOUND IN AND AROUND PROJECT SITE (10 KM RADIUS)
54 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 03 - DESCRIPTION OF ENVIRONMENT
3. 10 SOCIO-ECONOMIC ENVIRONMENT
Review of secondary data (District Census Statistical Handbooks - 2011) with respect to
population, occupation structure and infrastructure facilities available for 10 km radius
study area. As per 2011 census the study area had a total population of 15,557. Socio-
Economic status of the population is an indicator for the development of the region. Any
developmental project of any magnitude will have a bearing on the living conditions and
on the economic base of population in particular and the region as a whole. Similarly, the
proposed activities will have its share of socio-economic influence in the study area. The
section delineates the overall appraisal of society relevant attributes. The data collection
for evaluation of impact of proposed project on socioeconomic aspects in the study area
has been done through primary household survey method and through the analysis of
secondary data collected for the given study area.
55 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 03 - DESCRIPTION OF ENVIRONMENT
56 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 03 - DESCRIPTION OF ENVIRONMENT
SCHOOLS:
1. Parent Choice International School - 5.5 Km (N)
2. Government High School, Sithalapakkam - 7 Km ( NW)
HOSPITALS:
1. Global Hospital - 5 Km (SSW)
2. Chettinad Health City - 5.7 Km (SSW)
3. Radial Orthoclinic - 8 Km (NW)
4. Sri Isari Velan Mission Hospital - 3.4 Km (W)
FIRE STATION:
1. SIPCOT Fire Station - 1.64 Km (SW)
57 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALLUR
CHAPTER 03 - DESCRIPTION OF ENVIRONMENT
58 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
4.1 INTRODUCTION
Every activity and operation has either adverse or beneficial impacts on the
environmental. The environmental impact identification has been done based on
proposed project activities. All the activities from construction phase to operational
phases of the project have been broadly covered, which is given in Table 4.1 and 4.2.The
activities and operations are considered on the basis of proposed process as described in
the Project Description Section 2.
59 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
TABLE 4.1 ACTIVITY - IMPACTS IDENTIFICATION MATRIX FOR CONSTRUCTION PHASE OF THE PROPOSED PROJECT
Construction phase Potential impacts
/Ground water
Ambient Noise
Resource use
Water Quality
Agriculture in
environment
Solid waste
generation
Traffic and
Air Quality
Landscape
Main Activities Sub Activities
economic
Land/Soil
transport
Land use
(Energy)
Heritage
Culture/
Ecology
Surface
Socio –
level
the
Site Site Clearing & Cleaning
Preparation Ground leveling
Waste handling and its
transportation Soil
Compaction
Labour Construction of Labour sheds
deployment to accommodate labour
camp siting Supply of water
Supply of fuel/ Energy
Waste handling & its
disposal
Sewage disposal
Excavation Moving of Heavy Machinery
Soil Extraction and Slacking
Soil Loading and
Transportation for Disposal
Various Tools Like Crow Bar
Foundations for heavy
machinery installation
Construction Power through
onsite Diesel Generators
60 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
61 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
TABLE 4.2 ACTIVITY - IMPACT IDENTIFICATION MATRIX FOR OPERATION PHASE OF THE
PROPOSED PROJECT
Ecological
resources
resources
economic
Land and
Land use
Cultural
hazards
tourism
cultural
Surface
pattern
volume
Ground
quality
quality
quality
quality
impact
Traffic
Onsite
Water
water
water
risks-
Noise
Socio
Potential
Agri
soil
Air
Activities
62 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
63 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
Based on activity - impact interaction matrix for construction and operation phase of the
proposed project as shown in Table 4.1 & 4.2 respectively, following impacts have been
identified:
i. Construction phase of proposed project would have impacts on the followings:
• Topography, Land use pattern and Landscape
• Land / Soil Environment
• Surface / Ground Water Resources
• Water Quality
• Ambient Air Quality
• Ambient Noise Quality
• Traffic and Transport
• Ecology
• Socio-economic
ii. Operation phase of the project would have likely impacts on the following
• Air Quality
• Water Quality
• Ground water Resources & Surface water Resources
• Land and Soil Quality
• Noise Quality
• Traffic Volume
• Ecological
• Socio-economic
• Onsite Risks - Hazards
The proposed facility is being developed at Navalur Village, Tamil Nadu. The development
period for the initial phase is considered as 1 to 2 years.
The likely temporary and permanent changes on the topography of the site would be
following:
• Temporary - Construction of temporary shed or camps for construction workers
during construction phase, which will be for 12-16 months of the construction
phase;
• Temporary - Movement of construction vehicles like excavators, pay loaders,
trucks, other vehicles for bringing construction material and construction work
64 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
may bring minor temporary change in the land use in and around the site by
parking the vehicles on the open spaces and roads near the site.
• Permanent - Erection and installation of the various plant structures and
establishment of plant building (manufacturing block, warehouse, office etc.,) and
utilities will bring permanent change to the local land use of the site.
Air quality in and around the project site would be impacted to some extent due to
construction and construction related activities. The main impact will be
• During site leveling, excavation, construction material handling etc., the likely
emissions from construction activities would include the following:
• Fugitive dust emissions from excavation work, digging, stacking of soils, filling,
handling of construction material, transportation of material, emission due to
movement of tyre and plying of heavy construction machinery etc.,
• Traffic movement at the site and also increase in traffic volume on the connecting
roads will rest in increase in vehicular emissions.
• Gaseous emissions from operation of diesel generators for power requirement
during construction phase.
• However, the fugitive and other emissions due to the construction activities will
most likely remain localized and confined to the project area, but adequate
mitigation measures would be required to reduce the pollutant concentration and
prevent their spread around the site.
• The impact of emissions both from tyre movements and vehicular exhaust
emissions required to be minimized by proper maintenance of vehicles, sprinkling
of water on unpaved roads at the construction site and planned movement of
vehicles.
• The emissions from diesel generators need to be controlled to minimize impacts of
air emissions by optimized operations, orientation at the site and providing
adequate stack height for wider dispersion of gaseous emissions.
• Drawn conclusion is that no significant impact on air quality is envisaged due to
construction and related activities. Any impact on air quality will likely be
restricted within the localized area. Application of adequate mitigation measures
by the Construction Management Contractors will further reduce the intensity of
such impacts.
• Construction of Proposed Project would be carried out. However, construction dust
from Proposed Project was not considered as a key issue and therefore dust
impact from the proposed project is considered insignificant. In addition, no other
65 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
dust emitting activities has been identified to be carried out concurrently with the
proposed Project.
66 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
67 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
mainly contain suspended solids from excavation or dredging and/or oil and grease from
mechanical equipment operation. Such runoff may pollute the receiving waters when
entering the river environment.
Runoff water has to be properly diverted, collected, settled, and returned to the inlet of
the sewage treatment works as much as practicable for further settling and treatment.
The anticipated impact from the construction of terrestrial components would be
insignificant. Nevertheless, for good site practice and appropriate mitigation measures
are recommended to be implemented during construction of new facilities.
The following solid wastes are likely to be generated during the initial construction phase:
Materials and equipment used on site would produce packaging and container wastes.
Mitigation measures should include provision of a collection area where waste can be
stored and loaded prior to removal from the site. The volume of general site wastes
generated will be dependent on the Contractor’s operating procedure and practices and
cannot be quantified. With the implementation of the recommended mitigation measures
(including site practices), the potential environmental impacts resulting from the storage,
handling and transportation of general site wastes would be minimal.
Workforce Wastes
Throughout construction, the workforce would generate general refuse, comprising food
scraps, paper, empty containers etc., Rapid and effective collection of site wastes will be
required to prevent waste materials being blown around by wind, flushed or leached into
the environment, and odour nuisance. The amount of general refuse which is likely to
arise cannot be quantified at this time as it will be largely dependent on the size of the
workforce employed by the contractor. Though with the implementation of waste
management practices at the site, it is not expected that there would be any adverse
environmental impacts arise from the storage, handling and transportation of workforce
wastes.
Construction plant and equipment will require regular maintenance and servicing, which
would generate waste. Substances generated are likely to include some chemical wastes
such as cleaning fluids, solvents, lubrication oil and fuel. Equipment maintenance
68 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
activities would also involve the use of a variety of chemicals, oil and lubricants, including
heavy-duty cleaners, organic solvents, degreasers, brake fluids, battery acid and
soldering fluids.
Chemical wastes arising during the construction phase may pose serious environmental,
health and safety hazards if not stored and disposed of in an appropriate manner as
outlined in the Chemical Waste Regulations (CWR). These hazards include:
• Toxic effects to workers;
• Adverse impacts from spills on water gathering ground and other ecological
sensitive areas and
• Fire hazards.
Materials classified as chemical wastes will need special handling and storage
arrangements before removal for appropriate treatment at the chemical waste treatment
facility. Wherever possible opportunities should be taken to reuse and recycle materials.
Provided that the handling, storage and disposal of chemical wastes are in accordance
with these requirements, adverse environmental impacts should not result.
e) Ecology
f) Socio-economic
As the proposed project is located in the Navalur Village, no negative impact is envisaged
on the socio-economic status of the area in terms of acquisition of agriculture land or
displacement of people etc., however, the construction phase will require construction
workers, which will largely be drawn from the local population and nearby towns. Thus, it
will provide temporary employment to number of families and that will be a positive
impact due to the proposed project.
The proposed project will also employ skilled people and that may be sought from
outside. These people will largely be based in nearby small towns. Overall, the
construction phase will have positive impact on socio-economic condition of the people in
the area, as it will provide direct and indirect revenues of income generation.
69 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
The major noise generating equipment during operational phase is the air blowers,
ventilation fans, water pumps and DG Sets.
The Proposed STP aims at improving overall ground water quality of Chennai. Raw
sewage from Chennai households would be collected, treated and discharged via the
proposed river outfall. After primary & biological treatment process, the pollution load
entering into the river environment would be almost nil compared with the existing
70 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
conditions. The impact from the proposed Project is considered to be positive. The
environmental impacts identified during operational phase are the chemical species of
concern which exists in the sewage effluent.
d) Chlorination
Chlorination will be used in Proposed STP for disinfection purpose in the effluent.
e) Emergency Overflow
The emergency overflow events are anticipated in case of pump failure, the electrical
power supply interruption, mechanical failure of primary, secondary and tertiary
treatment units, disinfection units, as well as blockage of river outfall. These emergency
overflow events is expected to be in-frequent and of short duration. The emergency
overflow due to electrical power supply interruption will be prevented by using DG Set.
Sludge will be produced from the primary and secondary biological treatment of the
sewage. The arrangements of sludge dewatering and disposal, namely on site centrifuge
dewatering scheme would be adopted. The sludge disposed from STP will be utilized for
green belt development and excess will be utilized for Agriculture purpose by NGO of Self
Help Group. The wet-sludge would be stored on site temporarily and would be barged for
further treatment at regular intervals to prevent any excessive odour emission. The
storage container would be covered to minimize the potential odour nuisance. The grit
collected from the pumping stations will be utilized for filling the low lying areas. The
screenings removed from the pumping stations &process will be given to concerned local
body for disposal into Solid Waste Management Facility.
71 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
The impacts during the construction phase on the environment would be basically of
transient nature and expected to reduce gradually on completion of the construction
activities. In order to mitigate them, the following measures are proposed.
• The construction site would be provided with sufficient and suitable toilet facilities
for workers to maintain proper standards of hygiene. These facilities include
provision of septic tank followed by soak pit and maintained to ensure minimum
impact on nearby water bodies and environment.
• The diesel generators (DG Sets) to be installed will be in conformance with recent
requirement of acoustic enclosure to achieve 75 dB (A) level at 1m from its
enclosure. It is also advisable that on site workers using high noise equipment
adopt noise personal protective devices.
Some good practices in construction facilitate waste reduction, easy collection and
segregation as given below.
1. The explosive for blasting and excavation should be stored in a standard
container. Hazardous materials must not be stored near surface waters and should
be stored near plastic sheeting to prevent leaks and spills. The handling of
explosives should be strictly according to the guidelines as prescribed by the
Department of Explosives.
2. Delivery of material on site must be done over a durable, impervious and level
surface, so that first batch of material does not mix with the site surface.
Availability of covered storage should be assured. Mobile and covered storage
boxes with easy drawing and filling mechanism can be used, which can be used
over a number of sites.
3. Demolished brick masonry and concrete is a good material for filling. Steel from
RCC must be carefully segregated and rest of the material should be crushed on
site only. Crushed masonry and concrete is even good for manufacture of
synthetic aggregate.
4. The recyclable items like metal, plastic should be sent to recyclable industry, and
rest of this scrap should be stored in a covered area.
5. Dry processes of construction are effective for reduction of water requirements
and even the waste generation. Use of Interlocking bricks, pre-cast roofing and
wall panels etc. will be suitable for this purpose.
72 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
6. Materials, which are durable and do not require frequent maintenance, should be
used. Exposed brickwork in hot and dry climate with Class I bricks requires
minimum maintenance. Instead of using stone masonry, stone cladding is a better
way to minimize the maintenance.
7. Wherever materials (aggregates, sand, etc.) are more likely to generate fine
airborne particles during operations, nominal wetting by water could be practiced.
Workers / labour should be given proper air masks and helmets.
8. Skilled labour and good workmanship is must for judicial utilization of materials
and minimizing the waste.
9. Construction is more of management. Proper estimate of material is a very first
measure to minimize the undue wastage.
10. Contaminated runoff from storage should be captured in ditches or ponds with an
oil trap at the outlet. Contaminated plastic sheeting should be packed and
disposed off site.
11. Communities nearby the blasting site should be consulted before deciding blasting
timings / durations and they should be informed / evacuated as required with the
knowledge of the district collector’ office.
12. Bitumen emulsion should be used wherever feasible. Contractors should be
encouraged to heat with kerosene, diesel or gas to gradually substitute fuel wood.
Fuel wood usage for heating should be limited to unsound log i.e. dead and fallen
trees.
13. Bitumen should not be applied during strong winds to avoid danger of forest fire.
Bitumen emulsion should not be used in rains. No bitumen must be allowed to
flow into the side drain. The bitumen drums should be stored in a designated
place and not be scattered along the roadside.
14. Rubbish, debris and bitumen wastes remaining after blacktop works should be
cleaned and disposed off in a safe place.
15. Materials wasted on site should be reused at the same place. For example, use of
excavated earth in landscaping, or use of waste pieces of floor tiles in floor of
porch or outdoor spaces, or use of remaining pieces of glass from window panes
into ventilators, skylights and boundary wall, or reuse of ply and other timber
pieces into furniture etc.,
These practices suggest the measures for reduction of waste. However, each type of
waste needs special attention and specific kind of management, as the wastes from
different activities poses different characteristics.
73 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
The Air Pollution Control (Construction Dust) Regulations shall be implemented during the
construction activities to minimize the dust impact. It is recommended that typical dust
control methods including the following good site practices should be incorporated during
construction phase:
74 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
Filtering of pollutants is most effective when plants are close to the source of pollution.
The design of shelterbelts against pollution is similar to those for protection from wind.
They should be permeable to encourage air turbulence and mixing within the belt. There
should be no large gaps. The profile should be rough and irregular and should present a
tall vertical leading edge to the wing. Spaces should be left within the shelterbelt to allow
gravity settlement of particles.
B. Applying Dust Suppressants - There are many types and brands of chemical
dust suppressants which work by binding lighter particles. Biodegradable suppressants
may be applied as a surface treatment to "seal" the top of an area, or may be applied
using a mixing method that blends the product with the top few inches of the land
surface material. It is important to note that used oil may NOT be used as a suppressant.
C. Graveling- Applying locally found gravel to access roads and lots adds a
protective layer over the exposed soil and helps control dust generation in some
situations. It is important that gravel contain a minimal percentage of fines and clean
gravel be added periodically, as the fines migrate to the surface and create dust.
D. Using Water Sprays - Water spray through a water truck for large projects, is an
effective way to keep dust under control. Misting systems and sprinklers are
75 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
76 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
Noise limits for DG sets- The maximum permissible sound pressure level for new diesel
generator (DG) sets with rated capacity up to 125 KVA, manufactured on or after the 1st
July, 2003 shall be 75 dB(A) at 1 meter from the enclosure surface.
The Canopies are must for DG sets and must meet CPCB norms of government of India
for noise Pollution effective July 2004 and Environment protection Rules, 1986 schedule
1, by Ministry of Environment and Forests.
• Measures for quality control of various water source such as fresh water,
underground water, municipal, tankers, rainwater and recycled water.
To minimize the potential water quality impacts from construction site runoff and various
construction activities. Perimeter channels are to be installed in the works areas to
77 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
a) AIR ENVIRONMENT
The gaseous pollutants will be generated mainly from Diesel Fuel combustion from diesel
generators, material handling and also from operation of transportation vehicles.
Following measures should be taken up for control of gaseous emissions:
The emission' source i.e., diesel generators will have adequate stack height with
conformance to the set norms of GPGS as
Diesel generators will be operated only for emergency power backup. Regular
maintenance of diesel engines has to be ensured
Apart from the above, the possible sources of dust emission will be the transportation
vehicles. These will mainly contribute to NOx and Carbon Monoxide. Since the truck trips
are less, vehicular emissions will be insignificant. However, management will ensure that
all the private and commercial vehicles entering into the site are in proper condition and
there is no visual sign of major emissions from the vehicles. Also it is to be ensured that
78 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
all the vehicles are regularly holding valid Pollution under Control Certificates. The
recommended mitigation measure to minimize potential odour impact is to enclose all the
major odour sources. The sludge should be carried by enclosed container during sludge
transportation.
To minimize the impact of noise from proposed operation within the plant as well as noise
impact on the nearby areas from road traffic following measures would be adopted:
• The specifications for procuring major noise generating machines / equipment
such as DG Sets , Exhaust fans, Motors and Pumps for various other purposes
would include built in design requirements to have minimum noise levels meeting
OSHA Standards.
• Equipments like diesel generators would be installed with designed attenuation
system/control measures like acoustic enclosure and insulation etc.,
• Whenever no control equipments are possible, increase the distance between
source and receiver and by altering the relative orientation of the source and
receiver. Noise level at the receiver end reduces in inverse proportion to the
square of the distance between the receiver and the source.
• Workers working near to high noise generating machinery to be provide with ear
mufflers/ear plugs.
• Enclosures of noisy equipment are proposed as noise mitigation measures for
operational phase.
Discharge of treated effluent will be diverted to the emergency overflow pipe if the case
of damage of river outfall pipe. Under normal circumstance, each process unit will be
backed up with a standby unit. The standby generator will ensure the continuous
electricity supply for the STP. From the water quality point of view, the discharge of
treated effluent from the emergency overflow pipe will likely meet the minimum effluent
standard for this project. As such, the emergency overflow pipe serves as a standby unit
for the river outfall pipe from this perspective.
For conditions where damages occurred in any of the STP unit, standby unit will be
operated and the designed treatment capability would be restored immediately to ensure
that water quality of the effluent can meet the discharge requirement. Hence, no
observable impact to both the creek of Buckingham Canal outfall and the emergency
79 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 4 - ENVIRONMENTAL IMPACT ANALYSIS
overflow pipes is anticipated. Under abnormal conditions where any treatment units fail
to achieve the targeted effluent quality, the impact to the receiving water body can be
alleviated through the dilution after discharging from the creek of Buckingham Canal
outfall or emergency overflow pipes. Notwithstanding that the chance of such failure is
unlikely to occur, the impact is considered acceptable as the effect will only happen in
short-run.
In the case of STP overflow, raw sewage may also be diverted to emergency overflow
outfall although discharge through river outfall is more preferable for dilution and
dispersion. In an extreme situation where no electricity supply is available (including the
failure of the standby generator), the impact from the untreated raw sewage can also be
alleviated through the initial dilution after discharging from river outfall for emergency
overflow pipes. Although the level of E coli. may be over the acceptable range, this
approach is considered as the best option in view of the low chance of discharging the
raw sewage directly to the receiving body in a long run.
Based on the above, it is extremely unlikely that major duty and standby units of the
STP, the river outfall pipe and electricity supply would have problem simultaneously.
Besides, it is very rare that the event will last for a long time. Hence, the probability of
diverting the discharge via emergency overflow is quite low.
The Sludge would be dewatered on site by centrifuge and utilized as manure in the later
stage of STP operation when necessary. The grit collected from the pumping stations will
be utilized for filling low lying areas. The screenings removed from the pumping stations
& process will be given to concerned local body for disposal into Solid Waste Management
Facility. It is also recommended to cover the storage container before disposal to
minimize the potential odour nuisance.
e) SOCIO-ECONOMIC ASPECT
The proposed project will be established in Navalur Village, therefore no land acquisition
and other social impact of any form is envisaged from the project. The project will
provide employment to local people during both construction and operation. The
employment would be in form of permanent and temporary as well as in contract form.
The management would abide by all legal requirements for hiring of temporary and
permanent employment for the project.
80 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 5 - ENVIRONMENTAL MANAGEMENT PLAN
5.1. OBJECTIVES
81 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 5 - ENVIRONMENTAL MANAGEMENT PLAN
A. Precautionary Measures
There is no activity of tree cutting for the proposed STP. Hence, no need to implement
the precautionary measures to mitigate the impacts due to clearing of vegetation during
the construction phase.
B. Compensatory Measures
Green belt of 1.110 Hectare is proposed to implement in the project site and around 80
trees of native species will be planted.
82 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 5 - ENVIRONMENTAL MANAGEMENT PLAN
Responsible
S.No Activity Mitigation measures Time frame
agencies
1. Clearances 1. Consent to Establish (CTE) from TNPCB, Before CMWSSB
2. Consent to Operate (CTO) from TNPCB, construction
3. CRZ Clearance from DCZMA/TNSCZMA/MoEFCC
4. NOC for the disposal into Creek of Buckingham Canal from Public
Works Department, Tamil Nadu,
STP laying activities will be initiated after obtaining relevant clearances
as applicable.
2. Tree cutting There is no tree cutting activity envisaged in the site or in laying line of Pre-construction --
treated water conveyance. In case of any tree cutting compensatory & construction
plantation shall be done at ten times the number of trees cut. phase
3. Utility Relocation 1. Identify the common utilities to be affected such as: telephone Pre-construction Prospective
cables, electric cables, electric poles, water pipelines, public water & construction Contractor
taps, etc phase
2. Affected utilities shall be relocated with prior approval of the
concerned agencies before construction starts.
4. Baseline Baseline parameters have been recorded during the EIA study and Construction & Prospective
parameters monitoring would be carried out as per plan provided. Operation phase Contractor
5. Planning of 1. Temporary diversion will be provided with the approval of the Pre-construction --
temporary engineer. Detailed traffic control plans will be prepared and & construction
traffic submitted to the engineers for approval, one week prior to phase
arrangements commencement of works.
2. The traffic control plans shall contain details of temporary diversion,
details of arrangements for construction under traffic, details of
traffic arrangement after cessation of work each day, Signages,
safety measures for transport of hazardous materials and
arrangement of flagmen.
83 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 5 - ENVIRONMENTAL MANAGEMENT PLAN
3. Conveying main will be laid only in the right of way of Navalur village
road.
6. Treated water 1. Performance standards will always be maintained, ensuring efficient Pre-construction CMWSSB
quality and working condition of Sewage treatment plant to meet the outlet & post
disposal of rejects quality specified. construction
2. The quality of outlet water will be complying with the discharge phase
standards prescribed by CPCB for disposal into inland water body.
7. Storage of Pipes and other construction materials would be stored in the shed with During Prospective
materials asbestos roofing at vacant portion available in the STP site. construction Contractor
8. Construction of 1. Contractor shall follow all relevant provisions of the Factories Act, During Prospective
labour camps 1948 and the Building and the other Construction Workers construction Contractor
(Regulation of Employment and Conditions of Service) Act, 1996 for
construction and maintenance of labour camp.
2. The location, layout and basic facility provision of each labour camp
will be submitted to Engineer prior to their construction.
3. The construction will commence only upon the written approval of the
Engineer.
4. The contractor shall maintain necessary living accommodation and
ancillary facilities in functional and hygienic manner and as approved
by the Engineer.
5. All temporary accommodation must be constructed and maintained in
such a fashion that uncontaminated water is available for drinking,
cooking and washing. The sewage system for the camp must be
planned. Adequate health care is to be provided for the work force.
The layout of the construction camp and details of the facilities
provided should be prepared and shall be approved by the engineer.
84 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 5 - ENVIRONMENTAL MANAGEMENT PLAN
85 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 5 - ENVIRONMENTAL MANAGEMENT PLAN
4. Engineer will certify that all arrangements comply with the guidelines of
PCB/ MoEF or any other relevant laws.
4. Informatory Signs and Hoardings The contractor shall provide, erect and maintain informatory/safety signs,
hoardings written in English and local language, wherever required or as
suggested by the Engineer.
5. Risk from Electrical Equipments 1. The Contractor shall take all required precautions to prevent danger from
electrical equipment and ensure that -
i) No material will be so stacked or placed as to cause danger or
inconvenience to any person or the public.
ii) All necessary fencing and lights will be provided to protect the public in
construction zones.
86 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 5 - ENVIRONMENTAL MANAGEMENT PLAN
10. Establishment of the Environmental Lab For Monitoring of Air, Water, Noise and Soil quality of STP Outlet.
CONVEYING MAIN
1. Disposal of construction debris and excavated 1. A suitable site should be identified for safe disposal, in relatively low lying
areas, away from the water bodies, residential and agricultural fields etc.,
87 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 5 - ENVIRONMENTAL MANAGEMENT PLAN
88 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 5 - ENVIRONMENTAL MANAGEMENT PLAN
89 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 5 - ENVIRONMENTAL MANAGEMENT PLAN
90 JULY 2016
EIA REPORT FOR OBTAINING CRZ CLEARANCE
CHAPTER 5 - ENVIRONMENTAL MANAGEMENT PLAN
91 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 05 - ENVIRONMENTAL MANAGEMENT PLAN
The potential impacts on the Noise environment envisaged from the proposed facility are
outlined below:
TABLE 5.4 POTENTIAL IMPACTS ON NOISE ENVIRONMENT DUE TO THE
PROPOSED FACILITY
Phase Potential Noise Sources
Construction • Site Preparation
• Heavy Earth moving equipment at site
• Soil compaction by vehicles
• Construction Activity
• Vehicle Movement
Operation • Vehicle movement
• Proposed STP operations
a) CONSTRUCTION PHASE
Sources of noise pollution during the construction of the facility is from the plant and
machinery comprising of mainly bull dozers, Front end loaders, standby generators, and
other heavy earth machinery used in construction in addition to the vehicular movement
within the project boundary.
b) OPERATION PHASE
The major noise generating equipment during operational phase is the air blowers,
ventilation fans, water pumps and DG Sets. All equipments are likely to be operated
simultaneously during operational phase except 'DG Set, which is used as a power
backup during power failure at pump station. However most of these equipments will be
enclosed and noise impact would be reduced. The construction of STP plant buildings and
other facilities like enclosure reduce the level of noise for identified noise sensitive
receivers. The noise impact on the surrounding areas from the pumping station is not
expected to be significant since it is to be enclosed in a concrete structure. Noise
generation due to plying of vehicles on the roads bringing raw material and taking
finished products can be reduced by proper time scheduling and planning.
92 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 05 - ENVIRONMENTAL MANAGEMENT PLAN
The acoustic enclosure will be of free standing, floor mounting type integral with the DG
set. The enclosure will be provided with rugged heavy-duty structural steel base frame
with checked plate flooring on which the DG set is to be mounted. The enclosure will be
93 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 05 - ENVIRONMENTAL MANAGEMENT PLAN
Accessories:
Silencer suitably optimized to meet stringent sound emission standards laid down
by MoEFCC / CPCB
Base rail with integral fuel tank will be provided with drain plug, air vent, inlet
and outlet connection, level indicator, manhole etc.
Dry and uncharged batteries with connecting leads and terminals
Acoustic enclosure:
Specially designed to meet stringent MoEFCC/ CPCB norms of 75 dBA @ 1 m at
75% load under free field conditions designed to have optimum serviceability.
Air inlet louvers specially designed to operate at rated load even at 500C air inlet
temp Made on special purpose CNC machines for consistency in quality and
workmanship.
Powder coated for long lasting service life and superior finish With UV resistant
powder coating, can withstand extreme environments.
Use of stainless steel hardware Insulation material meets exacting IS 8183 specs
for better attenuation.
94 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 05 - ENVIRONMENTAL MANAGEMENT PLAN
Construction activities and the consequent transportation activities add to the air
pollution in the region. Impact of the air pollution will be moderate and short term at
sewage pumping stations, STPs and while laying sewer lines.
Precautionary Measures
Planning of labour camps needs to be done with adequate water supply, sanitary
facilities and drainage in temporary colonies of the construction workers, necessary
transportation facilities to the labourers will be provided.
95 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 05 - ENVIRONMENTAL MANAGEMENT PLAN
96 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 05 - ENVIRONMENTAL MANAGEMENT PLAN
Apart from the above mentioned monitoring requirements, any major accidents/spillage
during bulk transport of hazardous materials will also be monitored. Depending on the
type of spillages/accidents the parameters to be monitored will be decided by the
engineer and will be carried out through approved monitoring agencies and supervised
by the implementing agency at their own cost.
97 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 05 - ENVIRONMENTAL MANAGEMENT PLAN
98 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 05 - ENVIRONMENTAL MANAGEMENT PLAN
Greenbelt will be effective in containing the pollutants due to the plant operations. The
main purpose of green belt development is to contribute to the following factors:
To attenuate noise level generated from the plant;
To improve the aesthetics of the plant area;
To trap the vehicular and fugitive dust emissions;
To act as a pollution sink for gaseous emissions;
To maintain ecological balances;
To prevent soil erosion and to protect the natural vegetation;
To utilize the treated effluents.
The total trees after the implementation of this plant will be around 80 trees (1.11 ha
Sq.m). This will serve the important environmental objectives of the dust and fumes
capture, noise attenuation and wind barrier while also improving the aesthetics.
The proposed green belt will be implemented with locally available and sustainable
species will only be chosen for plantation.
While selecting the plant species for the proposed green belt, the following points have
been taken in to consideration:
99 JULY 2016
EIA CRZ REPORT FOR CMWSSB - NAVALUR
CHAPTER 05 - ENVIRONMENTAL MANAGEMENT PLAN
The below mentioned species not only resist water stress but also covers the ground
quickly and also have wider soil adaptability. For protecting the environment from dust,
temperature, chemicals, and emissions the following species have been recommended.
The above given suitable trees will be planted in consultation with the local body at the
time of implementing green belt operation.
Planting will be carried out in vacant space wherever possible using shrubs and ground
covers. Planting will be aimed to create a conductive microclimate and a visual impact.
TABLE 5.2 COST ESTIMATE FOR ENVIRONMENTAL MANAGEMENT PLAN
Operational Cost
Approximate Capital
S.No. Description (Rs. lakhs per
Cost (Rs. In lakhs)
annum)
1. Air Pollution Control measures 4.0 1.0
2. Sewage Treatment Plant (STP) & Rain 630.0 20.0
water harvesting measures
3. Environment Monitoring and - 2.5
Management
4. Solid and Hazardous Waste Management 3.0 1.0
(Membership & Facility development)
5. Energy Management 3.0 0.4
6. Occupational Health & Safety 2.0 4.0
7. Green belt Development 2.5 2.0
8. Environment Management Cell - 3.5
TOTAL 644.5 34.4
sss
The main source of water supply to the Chennai city is from surface water sources such
as Poondi, Cholavaram, Chembarambakkam, Veeranam lake near Neyveli and Red hills
reservoirs thorough pipelines to city besides ground water sources from Araniar and
Kortalaiyar basin. Chennai city does not have any perennial source of water. The water
supply has been augmented by Krishna Water Supply scheme with supply of water from
the State of Andhra Pradesh and by Chennai Water Supply Augmentation Project with
supply of water from Veeranam Tank.
A desalination plant of capacity 100 MLD is commissioned near Kattupalli village, Minjur.
Another 100 MLD capacity desalination plant is commissioned at Nemmili at the southern
outskirts of Chennai.
Proposed construction of 6 MLD Sewage Treatment Plant (STP) along IT Corridor based
on Activated Sludge Process (ASP) at Survey Number 45/1 of Navalur village, Thiruporur
Taluk, Kancheepuram District by Chennai Metropolitan Water Supply and Sewerage Board
(CMWSSB), Chennai.
ASP Technology is fully automated using Programmable Logic Controllers (PLC), various
transmitters and analyzers, Variable Frequency Drives (VFDs) and automated valves.
The entire treatment process including incoming flows, cycle duration and regulation
between aeration basins, process parameters, Dissolved Oxygen levels, air flow rates to
basin, growth of micro-organisms, decanting rates, etc. are controlled, monitored online
arid are adjusted automatically based on varying incoming flow and organic load
conditions . This offers consistent and optimized performance of plant with excellent
outlet quality even under varying incoming conditions.
The proposed STP is an Activated Sludge Process that will produce quality effluent after
the treatment, before discharge into the Creek of Buckingham Canal. The nature of the
proposed system will prevent the production of odour and sludge thus, making the
facility little nuisance to the surrounding communities. The entire STP project has been
conceived, planned and developed as a pollution control-cum-resources recovery
measure following the direction of TNPCB. The project will therefore contribute
significantly positive impact on the prevailing environment. In addition, this project
envisages the following:
I. The clean and healthy environment of the town and the socio economic health
conditions of the public will improve by the implementation of such project.
II. Downstream of the Creek of Buckingham Canal after the STP will get improved
and it will be more useful for cultivation.
III. The project envisages more cost benefit ratio due to least maintenance and more
revenue to the CMWSSB by selling the sludge cakes as manure used for
agricultural purposes.
All possible environmental aspects have been adequately assessed and necessary control
measures have been formulated to meet statutory requirements. Thus, implementing
the proposed project will not have any appreciable negative impacts. With proper
maintenance and environmental monitoring, the facility is not expected to have any
adverse effects on the surrounding communities.
7. DISCLOSURE OF CONSULTANTS
This chapter presents the details the environmental consultants engaged, their
background and the brief description of the key personnel involved in the project.
7.1 INTRODUCTION
ABC Techno Labs India Private Limited is an ISO 9001, ISO 14001 & OHSAS 18001
Certified Company & leading Environmental Engineering & Consultancy Company. ABC is
the first firm to be accredited by NABET (National Accreditation Board for Education and
Training), Quality Council of India, as an EIA Consultant. ABC is equipped with in-house,
spacious laboratory, accredited by NABL (National Accreditation Board for Testing &
Calibration Laboratories), Department of Science & Technology, Government of India and
MoEFCC under Environmental Protection Act, 1986.
We are having a well experienced team of Scientists & Engineers who are looking after
our well equipped analytical laboratory with a facility including analysis of physical,
chemical and biological parameters as per the requirements of the State Pollution Control
Board and our clients.
A. ENVIRONMENTAL SERVICES
B. TURNKEY PROJECTS
C. MULTILAB DIVISION
Chemical Testing
Environmental Testing
Microbiological Testing
Food Testing
Metallurgical testing
Mechanical Test
Chemical Testing
Corrosion Testing
13.01.2016
13.01.2016
153
13.01.2016
13.01.2016
154
ANNEXURE IX
CONCURRENCE FROM
WATER RESOURCES
DEPARTMENT OF PWD
155
156
157
158
159
160