Professional Documents
Culture Documents
Abstract: This article presents a comparative study of 55 concrete arch bridges built over the last century. For each bridge considered in the
study, section properties and geometrical ratios were determined and compiled into a database. These data were used to identify empirical trends
related to important attributes such as proportions, stiffness, slenderness, and efficiency. These trends were then expressed as functions of span
length. The database and empirical trends together provide a unique and comprehensive quantitative characterization of the state of the art of
concrete arch bridges. By situating new design concepts within the trends compiled by this study, designers of arch bridges can gain insight into
the implications of specific design decisions with regard to structural behavior and efficiency and will have a quick and reliable means of es-
timating the nature and extent of the effort required for validation. DOI: 10.1061/(ASCE)BE.1943-5592.0000537. © 2013 American Society of
Civil Engineers.
Author keywords: Bridges, arch; Bridges, concrete; Reinforced concrete; Comparative studies; Databases; Conceptual design; Deck-
stiffened arches; Slender arches; Shallow arches; Design aides.
Fig. 1. Elevation and section views of the 55 concrete arch bridges considered in this study
estimated for this bridge, comparisons with other bridges in the Flatness (Span-to-Rise Ratio)
database would not be meaningful for certain parameters because of
The span length L and rise f of the arch are usually the first two
differences in form and overall system behavior.
dimensions to be determined in the design process. The span-to-rise
ratio L=f not only provides a simple quantitative characterization of
Empirical Trends the overall visual form of the arch, it also plays an important role in
determining many aspects of structural behavior. Fig. 4 depicts L=f
This section presents observations on the design and structural be- as a function of span length L for the bridges considered in this study.
havior of concrete arch bridges arising from relationships among the The values of L=f range between 2.3 and 11.2. The mean value is 5.3
geometrical quantities collected in the database and parameters com- and the coefficient of variation is 0.37. All but three of the bridges
puted from these quantities. (95% of the sample) have L=f between 2.3 and 8.0.
© ASCE
04013010-5
J. Bridge Eng.
database, the Infant Henrique Bridge, allude to the fact that the
locations of the springing lines were determined by tight site con-
straints (Adão da Fonseca and Mato 2005). The significant varia-
tion in the observed values of L=f as a function of L thus appears
consistent with the important role played by aesthetic considerations
and given roadway and site geometry on the choice of the springing
lines.
Arch depth and girder depth are chosen early in the design process.
Both dimensions have a significant effect on the visual qualities of
a given bridge as well as structural response, since they are directly
related to the axial and bending stiffness of the respective mem-
bers. Leonhardt (1979) makes no specific quantitative recom-
mendations regarding member depth. Menn (1990) recommends
that girder depth be constant over the arch and approaches and that
girder span-to-depth ratio be chosen between 12:1 and 15:1 in the
Fig. 4. Span-to-rise ratio as a function of span length
approach spans. Menn makes no specific recommendations for
arch depth.
The upper two graphs of Fig. 5 plot average arch depth and girder
These observations are generally consistent with the recom- depth as functions of arch span length L. It is apparent that arch depth
mendations of Menn (1990), who proposed that L=f be chosen and girder depth both tend to increase with increasing values of L.
between 2 and 10. According to Menn, values of L=f below 2 are The bridges within the database can be divided into two groups:
visually awkward and difficult to build, presumably because of the those with arch depth greater than girder depth, referred to as deep-
need for the arch section to be completely enclosed by formwork arch systems, and those with girder depth greater than arch depth,
when it is cast in place. As L=f approaches 10, sensitivity to imposed referred to as deep-girder systems. The deep-arch systems, which
deformations due to creep, shrinkage, and change in temperature make up 43 of 55 bridges in the database, cover the entire range of
increases significantly. The data are also consistent with recom- spans. The deep-girder systems make up 12 of 55 bridges in the
mendations made by Leonhardt (1979). Recognizing the link be- database. With the exception of the Infant Henrique Bridge, which
tween stresses due to imposed deformations and the degree of has a span of 280 m, these bridges cover arch spans up to only 132 m.
statical indeterminacy, Leonhardt proposed the following ranges for Regression lines for girder depth and average arch depth were
L=f : 5 to 12 for three-hinged arches, 4 to 12 for two-hinged arches, computed separately for the two groups of bridges. The lines and
and 2 to 10 for fixed-end arches without internal hinges. Neither respective equations are given in Fig. 5. (The Pitan Bridge, a clear
author provides detailed quantitative justification for the proposed outlier, was excluded from these calculations.) The regression lines
ranges of L=f . The highest span-to-rise ratio from the database, 11.2, for the deep-arch and deep-girder systems present a relatively strong
exceeds the proposed upper limits of both Menn and Leonhardt for reciprocal relationship, in the sense that the regression line for girder
fixed-end arches, demonstrating that feasible solutions can be de- depth for the deep-arch systems is similar to the regression line for
veloped outside these recommended ranges. The data indicate, arch depth for the deep-girder systems, just as the regression lines for
however, that designers have generally not ventured into the upper arch depth for deep-arch systems and girder depth for deep-girder
ranges of span-to-rise ratios proposed by these two authors. systems bear strong similarities. This suggests that there may be
No obvious relation defining span-to-rise ratio as a function of significance to the sum of girder depth and average arch depth. This
span length can be identified from Fig. 4. This observation is con- quantity will be called system depth, dsys .
sistent with the negligible coefficient of determination (0.082) of the The bottom graph of Fig. 5 shows system depth plotted as
linear regression line. The lack of correlation of L=f with L can be a function of span length. The regression line and its equation are
understood in relation to the factors considered in the selection of given. (The Pitan Bridge was again excluded from the linear fit.) The
L=f in design. For given profiles of roadway and terrain to be relatively high coefficient of determination of the regression line,
crossed, the choice of arch span length generally leads to a relatively 0.88, confirms that it is a faithful representation of the data.
small number of possibilities for the rise (and sometimes only The strong correlation of dsys with L stands in contrast to the lack of
a single credible possibility). This is a consequence of the common correlation of L=f with L. In the previous subsection, it was proposed
practice of setting the chord joining the springing lines to be parallel that site-specific geometrical constraints severely limited the range of
to the roadway and of locating the crown of the arch as close as possible choices for arch rise once the location of the springing lines
possible to the girder. The bridge elevations of Fig. 1 are generally had been determined. In contrast, site-specific geometry has relatively
consistent with these principles. For a given site, therefore, suitable little impact on primary member depth. This gives designers con-
values of arch rise can generally be expressed as a single-valued siderable freedom to select these dimensions based on considerations
function of arch span length. related to structural efficiency and economy. This is consistent with
The choice of a suitable (L, f ) pair within this set depends on the much stronger relationship between member depth and span
a number of factors. Although lower values of L=f reduce the forces length observed from the data.
in the arch for a given load and minimize the effects of shortening in The strong empirical relationship between dsys and L can help
the arch, it is clear from the observed data that these simple statical designers select a suitable system depth once arch span has been
considerations are not the primary factor driving the choice of L=f . In determined. The data also indicate that designers have considerable
many cases, the given topography can suggest locations of springing freedom to apportion dsys to arch and girder, at least for spans up to
lines that are clearly better than any others. For example, the about 130 m, i.e., for the range of spans in which there is good
designers of the arch with the greatest span-to-rise ratio in the representation from both deep-arch and deep-girder bridges.
Fig. 5. Arch depth, girder depth, and system depth as functions of span length
incomplete picture of stiffness. Two sections of identical width and that the designers chose a thin arch to minimize these effects.
depth, for example, can have significantly different moments of A suitable explanation of the dominance of self-stiffened arches
inertia depending on whether the section is solid or hollow. It is for long spans requires consideration of the load path of the partially
therefore important to consider bending stiffness explicitly. completed bridge during construction. The temporary structure used
Total bending stiffness of the system is characterized mathe- to support arches before they can carry load on their own is a sig-
matically by Isys . It is helpful to express this parameter in terms of nificant component of construction cost. For long spans, this cost
effective stiffness depth, deff , defined as follows: can be minimized by building arches in two halves, proceeding
qffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi outward from each of the springing lines. Until the two cantilevers
deff ¼ 3 12Isys =bdeck (2) meet at the crown, they must be supported with temporary stays.
The cost of these stays can be minimized by ensuring that the arch
alone can carry the weight of spandrel columns and girder at all
The quantity deff is thus the depth of a solid rectangle with width stages of construction. This would not cause a problem if these
equal to that of the bridge deck and moment of inertia equal to Isys . components could all be constructed in a single operation, since
The use of deff removes the effect of bdeck and thus provides a arches are normally dimensioned to carry the entire dead load of the
consistent basis for comparing total stiffness across a diverse set of structure. When the girder is built in stages from one side of the span
bridges. to the other, however, a significant nonuniform load is applied to the
Fig. 6 shows computed values of deff plotted as a function of L for arch. If the bending capacity of the arch is insufficient, the capacity
bridges in the database, together with a linear regression line. (The (and hence the cost) of the temporary structure must be increased
Pitan Bridge was not included in the regression calculation.) The accordingly.
coefficient of determination is 0.91. The strong linear trend is not For long-span arches, the area of concrete required to carry dead
a direct mathematical consequence of the strong linear relationship load is generally large enough to enable a cross section of high
between dsys and L observed in Fig. 5. Two arch/girder systems with bending capacity (i.e., a box) to be provided with minimal increase
identical dsys , for example, can have values of deff that differ by in permanent materials. Self-stiffened systems thus provide rela-
a factor of 2 or more. tively economical solutions with regard to the permanent structure.
For a given value of Mtot , Maillart’s equations are independent of The high bending strength of the arch also enables it to carry non-
arch span L. This implies that, at least with regard to load path for live uniform loads during construction on its own, thus minimizing the
load, there is essentially no restriction on the relative bending cost of the temporary structure. On the basis of this reasoning,
stiffness of arch and girder, for any given value of L. On this basis, therefore, it is reasonable to conclude that long-span deck-stiffened
therefore, one would expect to find values of Iarch =Isys well dis- arches are likely to be less economical than self-stiffened options
tributed between deck-stiffened and self-stiffened over the full range when the cost of temporary structures is considered.
of spans. Fig. 7, a plot of observed values of Iarch =Isys as a function of
L, shows, however, that this is not the case. It is apparent from this
pression (slightly simplified for this article) for estimating teff (in rsys ¼ Isys =Aarch (6)
meters) for posttensioned concrete girder bridges:
where Aarch 5 cross-sectional area of arch (taken as an average value
teff ¼ 0:35 þ 0:0045l (3) for variable depth arches). This formulation of rsys is reasonable,
since it accounts for the entire bending stiffness of the system (Isys )
where l 5 girder span length in meters. This equation is a linear but includes only the area of the arch, since the girder does not resist
regression line corresponding to data obtained from a set of com- axial compression. Austin (1971) proposed the following values for
pleted bridges in Switzerland. k: 0.35 for fixed arches, 0.50 for two-hinged arches, and 0.54 for
A similar parameter can be defined for arch bridges using the three-hinged arches.
following equation: System radius of gyration is plotted versus span length for the
bridges in the database in Fig. 9, together with a regression line,
teff ¼ V=ðL × bdeck Þ (4) which was computed excluding the Pitan Bridge. The coefficient of
determination is 0.90.
where V 5 total volume of concrete in the arch, girder, and spandrel System slenderness ratio l is plotted as a function of L for the
columns; bdeck 5 width of deck; and L 5 arch span length. bridges in the database in Fig. 10. The two lines plot values of l
Computed values of teff are plotted as a function of L in Fig. 8 for calculated for fixed arches based on values of rsys computed from the
the bridges in the database. Menn’s regression line for posttensioned regression equation for rsys . The upper and lower lines represent L=f
girders is also drawn, for spans up to 250 m, beyond which concrete of 3 and 8, respectively.
girders are extremely rare. Values of teff for the arch bridges tend to For short spans, observed values of l are reasonably well dis-
increase with L, although the scatter is significant. Although most of tributed between the minimum of 14 and the maximum of 99 for the
the arch points lie above Menn’s line for girders, a small number of Nanin Bridge. As L increases, the distribution of the points tends to
points lie below. This implies that although it is possible to design tighten from above and below toward the computed lines, i.e., an
concrete arch bridges that consume less concrete than girder bridges, average value of about l 5 61. Although the arch of the Infant
most concrete arch bridges have consumed significantly more con- Henrique Bridge appears slender when considered on its own, the
crete than girder bridges. This would imply that it is not only the cost of combined slenderness ratio of the arch/girder system, 54, is about
temporary structures that has hampered the competitiveness of arch one half that of the Nanin Bridge.
bridges in recent years, but also a high consumption of materials. The graph reveals that although arches of considerable slender-
ness have been built, designers of long-span arches have tended
Slenderness toward structures of more modest slenderness. The relatively broad
distribution of l for short-span arches deviates significantly from the
Menn (1990) discussed the importance of second-order effects in the lines computed on the basis of the regression equation for rsys . This
calculation of bending moments in arches under the combined action
Fig. 8. Effective slab thickness as a function of span length Fig. 9. System radius of gyration as a function of span length
of Highways, Sacramento, CA. Podolny, W., and Muller, J. M. (1982). Construction and design of pre-
CALTRANS. (1932b). “Bridge across Rocky Creek (as built plans).” Doc. stressed concrete segmental bridges, Wiley, New York.
No. 50001081, State of California Department of Public Works Division Radic, J., Bleiziffer, J., and Tkalcic, D. (2005). “Maintaining safety and ser-
of Highways, Sacramento, CA. viceability of concrete bridges in Croatia.” Bridge Struct., 1(3), 327–344.
CALTRANS. (1937). “Bridge across Big Creek (as built plans).” Doc. No.
Radic, J., Savor, ^
Z., Bleiziffer, J., and Kalafatic, I. (2008a). “Sibenik Bridge—
50001093, State of California Department of Public Works Division of Design, construction and assessment of present condition.” Proc., Chinese-
Highways, Sacramento, CA. Croatian Joint Colloquium: Long Arch Bridges, Univ. of Zagreb, Zagreb,
CALTRANS. (1996). “Bridge across Russian Gulch.” Earthquake Retrofit Croatia, and Univ. of Fuzhou, Fuzhou, China.
Project No. 714.0, State of California Department of Public Works
Radic, J., Savor,
Z., Prpic, V., Friedl, M., and Zderic, (2008b). “Design
Z.
Division of Highways, Sacramento, CA. and construction of the Maslenica Highway Bridge.” Proc., Chinese-
Chen, B. (2007). “An overview of concrete and CFST arch bridges in Croatian Joint Colloquium, Univ. of Zagreb, Zagreb, Croatia, and Univ.
China.” Proc., 5th Int. Conf. on Arch Bridges, Multicomp, LDA Pub- of Fuzhou, Fuzhou, China.
lishers, Madeira, Portugal. Salonga, J., and Gauvreau, P. (2010). “Span-to-rise ratios in concrete arches:
Cheng, K. M. (1994). “The Pitan Bridge, Taiwan.” Struct. Eng. Int., 4(4), Threshold values for efficient behavior.” Proc., 6th Int. Conf. on Arch
231–234. Bridges, SECON HDGK, Croatia.
“Communications techniques Belges 8.” (1978). Annales des travaux publics
Savor, Z., and Bleiziffer, J. (2008). “Long span concrete arch bridges of
de Belgique, no. 1–2, Fédération Internationale du Béton (fib), Lausanne, Europe.” Proc., Chinese-Croatian Joint Colloquium Long Arch Bridges,
Switzerland. Univ. of Zagreb, Zagreb, Croatia, and Univ. of Fuzhou, Fuzhou, China.
Dajun, D., and Weiqing, L. (1999). “Neue Entwicklungen bei Hochhäusern
Savor, Z., Mujkanovic, N., Hrelja, G., and Bleiziffer, J. (2008). “Re-
und großen Brücken aus Beton in China.” Beton- und Stahlbetonbau, construction of the Pag Bridge.” Proc., Chinese-Croatian Joint Col-
94(4), 178–185. loquium: Long Arch Bridges, Univ. of Zagreb, Zagreb, Croatia, and
Eilzer, W., Schmidtmann, W., and Jung, R. (2005). “Die Wirrbachtalbrücke.” Univ. of Fuzhou, Fuzhou, China.
Beton- und Stahlbetonbau, 100(3), 236–240. Schlaich, J., and Scheef, H. (1982). Concrete box-girder bridges, In-
Ewert, S. (1999). “Betonbogenbrücken: Mehr als 200 m Spannweite.” ternational Association for Bridge and Structural Engineering, Zurich.
Beton- und Stahlbetonbau, 94(9), 377–388. Schwaab, E., and Gattner, A. (1953). “Straßenbrücke über das Tiefe Tal bei
Fritzell, G. (1960). “Deflection measurements on the Sandö Bridge 1942- Rosshaupten, Allgau.” Beton- und Stahlbetonbau 11.
1958.” Proc., 6th Congress of the IABSE, International Association for Sinotech. (2007). Drawings of Wunshuei, Lianlao, Nan Ke Bridges.
Bridge and Structural Engineering (IABSE), Stockholm, Sweden. Sinotech Engineering Consultants, Inc., Taipei, Taiwan.
Galambos, T. V. (1998). Guide to stability design criteria for metal State of Nevada Department of Transportation (Nevada DOT). (2000).
structures, Wiley, New York. B-1948-N/S Galena Creek Bridge, Carson City, NV.
Goodyear, D., Smit, N., Heacock, J., and Starkey, S. (2001). “Respect for Standfuß, F. (1990). “Nationalbericht: Brücken in der Bundesrepublik
tradition: The New Crooked River Gorge Bridge.” Troisième Confer- Deutschland.” Beton- und Stahlbetonbau 85(5), 106–113.
énce Internationale sur les Ponts en Arc, Presses des Ponts, Paris. Stellmann, W. L. O. (1966). “Brücke über den Rio Paraná in Foz Do Iguaçú,
Hünleim, W., and Ruse, P. (1985). “Ein neues Verfahren für den Bau von Brasilien.” Beton- und Stahlbetonbau 61(6), 145–149.
Bogenbrücken dargestellt am Bau der Argentobelbrücke Würgau.” Der Taiwan Area National Expressway Engineering Bureau (TANEEB). (1999).
Bauingenieur, 60(12). The second freeway: An anthology of particular bridges, Ministry of
Igarashi, T. (1976). “Die Hokowazu-Brücke in Japan, ein Stahlbetonbogen Transportation, Taiwan District, Taipei, Taiwan (in Mandarin).
im freien Vorbau.” Der Bauingenieur, 51(8), 281–284. Tandon, M. (1995). “Arch Bridge at Dodan Nallah.” Proc., 1st Int. Conf. on
Inaudi, D., Rüfenacht, A., von Arx, B., Noher, H. P., Vurpillot, S., and Arch Bridges, Thomas Telford, London.
Glisic, B. (2002). “Monitoring of a concrete arch bridge during con- Tanner, P., and Bellod, J. L. (2005). “Widening of the Elche De La Sierra
struction.” Proc., SPIE 4696, Smart Structures and Materials 2002: Arch Bridge, Spain.” Struct. Eng. Int., 15(3), 148–150.
Smart Systems for Bridges, Structures, and Highways, International Tonello, J., and Dal-Palu, P. (2001). “Le Pont du Triple Saut (the Triple Jump
Society for Optical Engineering (SPIE), Bellingham, WA. Bridge).” Troisième Conferénce Internationale sur les Ponts en Arc,
Kamimura, K., Kouno, M., Okada, K., and Tsuka, T. (2001). “Design and Presses des Ponts, Paris.
construction of the Tensho concrete arch bridge.” Troisième Conferénce Viet Tue, N., Dehn, F., Schliemann, T., Reintjes, K. H., and Tauscher, F.
Internationale sur les Ponts en Arc, Presses des Ponts, Paris. (2005). “Anwendung von Hochleistungsbetonen bei der Bogenbrücke
Koppel, A. J., and Walser, R. (1991). “Hundwilertobelbrucke: Ein bemer- Wölkau im Zuge der BAB A17.” Beton- und Stahlbetonbau 100(11),
kenswerter Neubau.” Schweizer Ingenieur und Architekt, 109(11), 931–938.
250–256. Wang, J. J., and Au, F. T. K. (2001). “Modong Hongshui River Bridge,
Leonhardt, F. (1979). Vorlesungen über Massivbau. Sechster Teil: China.” Struct. Eng. Int., 11(2), 101–103.
Grundlagen des Massivbrückenbaues, Springer-Verlag, Berlin, Hei- Wößner, K., Gebhardt, H., Schnabel, R., and Wörner, H. (1979). “Die Tal-
delberg, New York. brücke Rottweil-Neckarburg.” Beton- und Stahlbetonbau 74(10), 237–243.
Liebenberg, A. C., and Latimer, M. G. (2001). “Bloukrans Bridge.” Troisième
Zderic, Runjic, A., and Hrelja, G. (2008). “Design and construction of
Z.,
Conferénce Internationale sur les Ponts en Arc, Presses des Ponts, Paris. Cetina Arch Bridge,” Proc., Chinese-Croatian Joint Colloquium on
Ministry of Transportation of Ontario (MTO). (1935). Bronte Creek Long Arch Bridges, Univ. of Zagreb, Zagreb, Croatia, and Univ. of
Bridge. As-built plans. Ontario Department of Highways, Toronto. Fuzhou, Fuzhou, China.
Menn, C. (1979). Brückenbau I, ETH Abteilung für Bauingenieurwesen, Zimmermann, W., and im Gailtal, N. (1999). “Der Bau der Stampf-
Zurich. grabenbrücke.” Beton- und Stahlbetonbau 99(4), 304–310.