1.STRUCTURAL EXCAVATION Common excavation Hand 6 MH/M3 Machine 0.5 MH/M3 Rock excavation 8 MH/M3 Hauling of spoils 1 MH/M3 2.STRUCTURAL BACKFILL By hand 5 MH/M3 By machine 2 MH/M3 3.TRENCHING By hand 6 MH/M3 By machine 0.5 MH/M3 EXCAVATION- MANUAL Common earth 8 MH/M3 Loam of sand 1.31 MH/M3 Clay or heavy soil 1.64 MH/M3 Rock 2.63 MH/M3 EXCAVATION- MECHANICAL Common earth 6.67 MH/M3 Rock with jack hammer 16.67 MH/M3 BACKFILLING Common manual 0.82 MH/M3 Gravel fill manual 5 MH/M3
TRENCHING & BACFILLING OF UNDERGROUND PIPING USING
EXCAVATION MATLS MANUAL FROM:
0 – 2m Depth 1.25 MH/LM
2 – 3m Depth 1.67 MH/LM 3 – 4m Depth 2.5 MH/LM 4 – 5m Depth 3.33 MH/LM Placing binder gravel 0.11 MH/M3 Escombro backfilling 0.21 MH/M3 Spreading,tamping & grading 0.48 MH/M2 Mechanical compaction, plate 0.06 MH/M3 compaction MANUAL CLEARING & GRUBBING Clearing under growth & trees – 0.05 MH/M2 12″ Clearing under growth & shrubs 0.03 MH/M2 Disposal of soil 1.69 MH/M3 Hauling of soil 1 MH/M3 Gravel fill 2.07 MH/M3 EXCAVATION – CRANE & CLAMPSHELL With 8 men & 2 carpenters 1.07 MH/M3 5.ROOFING AND SIDING Roofing Metallic 0.97 MH/m2 Non-Metallic 1.51 MH/m2 Siding Metallic 1.29 MH/m2 Non-Metallic 1.51 MH/m2 CONCRETE WORKS 4.CONCRETE WORKS Grade members Formworks 2.54 MH/M2 Concreting 8.54 MH/M3 Rebar 0.07 MH/kg Finishing 0.4 MH/M2 Suspended members Formworks 3.28 MH/M2 Concreting 16.7 MH/M3 Rebar 0.08 MH/kg Finishing 0.8 MH/M2 Embeded metal 0.27 MH/kg Water proofing 1.82 MH/M2 Joint filler 0.3 MH/lLm PLACING CONCRETE Slab on Fill 5 MH/M3 Slip Form 25 MH/M3 Floor Finish Unhardened 1 MH/M3 Concrete finished hardened 1.43 MH/M3 REBAR WORKS Ground floor installation 0.07 MH/M3 Upper floor installation 0.08 MH/M3 Fabrication 0.1 MH/M3 Mixing manual 16 MH/M3 Mixing machine 1.8 MH/M3 MORE THAN 1.8 M3 POUR Chute from truck 7 MH/M3 Crane & bucket 14 MH/M3 Wheeling 27 MH/M3 Finishing 2.8 MH/M3 FORMWORKS & CARPENTRY WORKS
FORM WORKS INSTALLATION
Wall on ground 2 MH/M2 Wall above ground 2.35 MH/M2 Beams 3.08 MH/M2 Columns 2.35 MH/M2 Suspended slab Suspended slab 0 – 18″ 1.67 MH/M2 Suspended slab 10 – 36″ up 3.33 MH/M2 Elevated & shored slab forming Forming only 8.6 MH/M2 Forming & Shoring 11 MH/M2 Wood wall & Partition 0.5 MH/M2 FORM WORKS FABRICATION Form works fabrication 1 MH/M2 STRIPPING OF FORMS Wall on ground 0.25 MH/M2 Wall above 10″ 1.29 MH/M2 Beams 1.03 MH/M2 Columns 0.85 MH/M2 Suspended slab Suspended slab 0 – 18″ 0.83 MH/M2 Suspended slab 10 – 36″ up 1.08 MH/M2 Elevated & shored slab forming 3.5 MH/M2 – strip of forms Floor slab at grade – strip of 2.8 MH/M2 forms INSTALLATION OF CARPENTRY WORKS Plywood partition 1 MH/PC T & G Flooring and Siding 0.14 MH/B.F. Ceiling & frame work 0.36 MH/B.F. Siding frame work 0.27 MH/B.F. Flooring framing 0.97 MH/B.F. Wooden post errection 0.43 MH/B.F. Truss Fabrication 0.35 MH/B.F. Truss Installation 0.8 MH/B.F. Girt Installation 0.21 MH/B.F. Plates Installation 0.13 MH/B.F. Purlins Installation 0.27 MH/B.F. Fascia board Installation 0.46 MH/B.F. 1/4″ or 3/4″ thk. plywood Cutting by manual 1 MH/PC Assembly 0.42 MH/M2 ARCHITECTURAL SPECIALTIES DOORS Wooden 2.37 MH/M2 Steel 7.64 MH/M2 Aluminum 8.07 MH/M2 Cyclone wire 7.64 MH/M2 WINDOWS Glass 3.23 MH/M2 Louver 4.63 MH/M2 Steel 32.29 MH/M2 PARTITIONS single wall 2.48 MH/M2 Wooden wall 3.44 MH/M2 Wooden Louver 3.44 MH/M2 cyclone Louver 5.38 MH/M2 PAINTING ( 3 coats ) Equipment 0.24 MH/f2 Pipes 0.3 MH/f2 Miscillaneous 0.24 MH/f2 STRUCTURAL STEEL WORKS 7. STRUCTURAL STEEL Fabrication Light 110-130 MH/MT Heavy 60-90 MH/MT Errection Light 70-100 MH/MT Heavy 40-60 MH/MT WELDING ( one pass only ) 1- Welder and 1- Helper ( 16 40-50 Lf/day total mh ) G.1 STRUCTURAL STEEL Fabrication Heavy weight 50-90 MH/MT Light weight 100-125 MH/MT Grating 1 1/4″ x 3/16″ 3.0 – 3.5 MH/SF Star threat grating 4.0 – 5.0 MH/SF Errection Heavy Structural teel 30 – 60 MH/MT Light Structural steel 60- 90 MH/MT Stacks ( Inc. full welding ) 250 – 300 MH/MT Tanks ( Inc. full welding ) 200 – 275 MH/MT