Professional Documents
Culture Documents
I. MECHANIZED ASPECT
B.2 - DOZER
HORSE PRODUCTION (m3/hr) BANK VOLUME)
POWER Canal Structure
120 30 10
140 40 15
160 50 20
180 60 25
200 70 30
B.3 - BACKHOE
BUCKET PRODUCTION (m3/hr) BANK VOLUME)
(m3) Canal Structure Creek
0.50 20 15 15
0.75 30 20 20
1.00 35 25 25
1.25 40 30 30
1.50 50 35 35
C) QUARRYING
DOZER PRODUCTION (m3/hr) BANK VOLUME LOOSE EXCAVATED MATERIAL
(Horse Power) Common Aggregate Cobble/Boulder (m3)
140 40 30 10 70
160 50 40 15 80
180 60 55 20 90
200 75 70 25 100
D) LOADING
BUCKET PRODUCTION (m3/hr) BANK VOLUME
(m3) Common Aggregate Couble/Boulder
1.0~1.5 70 80 30
1.5~2.0 100 110 40
2.0~2.5 130 140 50
2.5~3.0 150 160 60
E) SPREADING
GRADER PRODUCTION (m3/hr) COMPACTED VOLUME
(Horse Power) Common Aggregate
80~100 60 70
100`125 70 80
125~150 90 100
150~175 100 110
H) EMBANKMENT COMPACTION
DOZER PRODUCTION (m3/hr) COMPACTED VOLUME
(Horse Power) Vibratory Static
3~5 60 40
6~10 70 50
11~15 80 60
K) DEMOLITION OF CONCRETE
CAPACITY (m3/day)
EQUIPMENT
Massive Concrete Slab & Wall
160cfm Compressor &
8.00 12.00
2-Pavement Breaker
L) DRIVING OF PILES
CAPACITY (m/hr)
EQUIPMENT
Steel Piles Concrete Piles Thick & Thin Concrete Piles
25 Tons Crane with
20.00
2 Tons Drop Hammer
25 Tons Crane with
2.00 4.00
7500 kgs-m Pile Hammer
& Thin Concrete Piles
4.00
ESTIMATING GUIDELINE
A) EXCAVATION
A.1 - COMMON MATERIAL
CAPACITY (m3/day) BANK VOLUME
TYPE
OF WORK DEPTH OF EXCAVATION
1.5m 1.6~2.5m 2.6m+
Farm Ditch 3.00 - -
Canal 2.50 2.00 1.75
Structure 2.00 1.75 1.50
Desilting 2.50 2.00 1.75
E) QUARRYING
MATERIALS CAPABILITY (m3/day/man)
Sand & Gravel 3.50
Cobbles 2.50
Boulder 2.00
F) DEMOLITION OF CONCRETE
MATERIALS CAPABILITY (m3/day/man)
Slab & Wall 0.40
Massice Conc. 0.25
G) SCREENING OF AGGREGATES
MATERIALS CAPABILITY (m3/day/man)
Gravel 4.00
Sand 6.00
H) MANUAL BACKFILL
MATERIALS CAPABILITY (m3/day/man)
Common 3.00
I) LAYING OF MATERIALS
MATERIALS CAPABILITY (m3/day/man)
Cobbles 2.00
Boulders 1.50
L) GROUTED RIPRAP
CAPABILITY (m3/day)
CREW
With Mixer Without Mixer
1-Foreman
2-Mason 5.50
7.50
10-Laborer
L.E Operator
M) CHB SETTING
Crew: 1-Mason, 2-Laborer
CAPABILITY (m2/day)
MATERIALS
Fence Building
4" CHB 14 10
6" CHB 10 8
N) CONCRETE LINING
CAPABILITY (m3/day)
CREW
With 1-Bagger Mixer
1-Foreman
2-Mason
4.50
10-Laborer
L.E Operator
P) CONCRETE WORKS
P.1 - FABRICATION, PLACING & DISMANTLING OF FORMS
Crew: 3-Carpenter & 5-Laborer Cap. = 3.50 m3/day for 3000psi
Crew: 1-Carpenter & 1-Laborer Cap.= 4.50 m3/day for Canal Lining
T) BUILDING FACILITIES
WORK DESCRIPTION CREW MEMBERS CAPABILITIES
Installation of Ceiling Joist 2-Carpenter & 1-Labourer 100 bd.ft./day
Installation of Ceiling Board 2-Carpenter & 1-Labourer 15 pcs/day
Installation of GI Roofing 2-Carpenter & 1-Labourer 150 Lin.Ft./day
Installation of Panel Door 2-Carpenter & 1-Labourer 4 pcs/day
Installation of Flush Door 2-Carpenter & 1-Labourer 6 pcs/day
Installation of Flourescent Bulb 1-Electrician & 1-Laborer 16 pcs/day
Installation of Incandescent Bulb 1-Electrician & 1-Laborer 32 pcs/day
Installation of Panel Board 1-Electrician & 1-Laborer 1/2 unit/day
Installation of Electric Conduit 1-Electrician & 1-Laborer 32 pcs/day
Installation of # 4 Wire 1-Electrician & 1-Laborer 20 L.M./day
Installation of # 8 Wire 1-Electrician & 1-Laborer 40 L.M./day
Installation of # 14 Wire 1-Electrician & 1-Laborer 60 L.M./day
Painting 1-Painter 24 m2/day
Tile Setting 1-Mason & 1-Laborer 2 m2/day
Installation of GI Flushing 1-Lath. & 1-Laborer 16 pcs/day
Installation of GI Ridge Roll 1-Lath. & 1-Laborer 16 pcs/day
Installation of Down Spout 1-Lath. & 1-Laborer 12 pcs/day
Installation of GI Gutter 1-Lath. & 1-Laborer 8 pcs/day
Installation of Jalousie & Accs. 1-Carpenter & 1-Laborer 10 m2/day
Note:
1. Time of mixer per day = Total bags of cement x 10 min. per bag / 60 minutes per hour = ____ hrs/day
2. Labor Intensity: 1-Leadman per 10-Laborers
1-Foremen per 4-Leadman
1-Watcher per 4-Heavy Equipment
1-Mechanic per 4-Heavy Equipment
Lumber Plywood
(bd. ft./hr) (pcs/hr)
4000 250
Lumber Plywood
(bd. ft./hr) (pcs/hr)
4000 250
ESTIMATING GUIDELINE
B. Rubble Concrete
211 kgsc 4.50 0.225 0.45
OTHER MATERIALS
STRENGTH F. Lumber 1/2 Plywood
CLASS TYPE OF STRUCTURE
(kgsc) (bd.ft./m3) (pcs/m3)
"A" Bridge Flume 211 60 1.00
"A" Siphon / Box Culvert 211 25 1.00
"A" Other Structure @ MC 211 20 1.25
"A" Pther Str. T. Fac. 211 15 1.15
"A" Rubble Masonry 211 10 0.10
"B" Canal Lining 200 5 -
"A" Dam 211 20 0.50
"B" Dam 200 10 0.10
"A" Roads Pavement 211 5 -
INSTALLATION OF RC PIPES
FABRICATION MATERIAL PER PC.
DIAMETER
Cement Sand Gravel F. Lumber RSB
(inches) (bag) (m3) (m3) (Bd. Ft.) (kgs)
12 0.21 0.01 0.02 2.00 -
18 0.45 0.02 0.04 2.00 3.65
24 0.72 0.03 0.06 3.00 4.52
30 0.93 0.04 0.08 3.00 5.26
36 1.11 0.05 0.10 4.00 6.01
42 1.32 0.06 0.12 4.00 6.79
PLASTERING OF CHB
MATERIAL PER M2 (Two sides)
SIZE
Sand Cement
4" & 6" 0.034 0.41
LAYING OF CHB
CEMENT SAND
SIZE
(bag/m2) (m3/m2)
4" 0.55 0.046
6" 1.07 0.089
BOULDER
(m3/m3)
-
-
-
-
0.95
1.00
1.00
C.
RSB CW Nails
(kgs) (kgs)
5.28 0.10
7.72 0.20
9.77 0.30
23.22 0.10
50.43 0.50
60.84 0.60
CW Nails
(kgs)
0.20
0.20
0.30
0.30
0.40
0.40
HAULING COST ANALYSIS
1. HAULING OF CEMENT
Ave. Haul. Dist. = 20 km (from Source to Jobsite)
Utilized: 6~7 Tons Cargo Truck with 5-Laborers
Base Cost of Cement: UC/bag
Capacity of Cargo Truck: 150 bags per trip
CYCLE TIME:
With Load: 20km/trip x 60min/hr / 25 km/hr = 48 min/trip
Without Load: 20km/trip x 60min/hr / 30 km/hr = 70 min/trip
Manual Loading Capability of 5-Laborers, Loading & Unloading = 300 bags/hr
Loading: 150bags/trip x 60min/hr / 300bags/hr = 30 min/trip
Unloading: 150bags/trip x 60min/hr / 300bags/hr = 30 min/trip
LABOR COST:
Driver: 1 x Rate/day x 2.47hrs/trip / 8hrs/day x 150bags/trip = ____/bag
Laborer: 5 x Rate/day x 2.47hrs/trip / 8hrs/day x 150bags/trip = ____/bag
EQUIPMENT
Fuel: 10lit/hr x 1.47hrs/trip x UC/lit / 150bags/trip = ____/bag
Rental: Rate/hr x 2.47hrs/trip / 150 bags/trip = ____/bag
Spare Parts: Rate/hr x 2.47hrs/trip / 150bags/trip = ____/bag
(Note: The travel Time on with & without load were only considered and the loading & unloading time were excluded on
SUMMARY:
Base Cost = UC/bag
Labor Cost = ____/bag
Fuel Cost = ____/bag
Rental Cost = ____/bag
Spare Part Cost = ____/bag
Total = ____/bag
HAULING COST ANALYSIS
CYCLE TIME:
With Load: 25km/trip x 60min/hr / 25 km/hr = 60 min/trip
Without Load: 25km/trip x 60min/hr / 30 km/hr = 50 min/trip
Manual Loading Capability of 5-Laborers, Loading & Unloading = 250pcs/hr
Loading: 250pcs/trip x 60min/hr / 250pcs/hr = 60 min/trip
Unloading: 250pcs/trip x 60min/hr / 250pcs/hr = 60 min/trip
LABOR COST:
Driver: 1 x Rate/day x 3.83hrs/trip / 8hrs/day x 250pcs/trip = ____/pc
Laborer: 5 x Rate/day x 3.83hrs/trip / 8hrs/day x 250pcs/trip = ____/pc
EQUIPMENT
Fuel: 10lit/hr x 3.83hrs/trip x UC/lit / 250pcs/trip = ____/pc
Rental: Rate/hr x 3.83hrs/trip / 250pcs/trip = ____/pc
Spare Parts: Rate/hr x 3.83hrs/trip / 250pcs/trip = ____/pc
(Note: The travel Time on with & without load were only considered and the loading & unloading time were excluded on
SUMMARY:
Base Cost = UC/pc
Labor Cost = ____/pc
Fuel Cost = ____/pc
Rental Cost = ____/pc
Spare Part Cost = ____/pc
Total = ____/pc
HAULING COST ANALYSIS
CYCLE TIME:
With Load: 25km/trip x 60min/hr / 25 km/hr = 60 min/trip
Without Load: 25km/trip x 60min/hr / 30 km/hr = 50 min/trip
Manual Loading Capability of 5-Laborers, Loading=6,000kgs/hr & Unloading=7,000kgs/hr
Loading:6000kgs/trip x 60min/hr / 6000pcs/hr = 60 min/trip
Unloading:6000kgs/trip x 60min/hr / 7000pcs/hr = 51.4 min/trip
LABOR COST:
Driver: 1 x Rate/day x 3.69hrs/trip / 8hrs/day x6000kgs/trip = ____/kg
Laborer: 5 x Rate/day x 3.69hrs/trip / 8hrs/day x 6000kgs/trip = ____/kg
EQUIPMENT
Fuel: 10lit/hr x 3.69hrs/trip x UC/lit / 6000kgs/trip = ____/kg
Rental: Rate/hr x 3.69hrs/trip / 6000kgs/trip = ____/kg
Spare Parts: Rate/hr x 3.69hrs/trip / 6000kgs/trip = ____/kg
(Note: The travel Time on with & without load were only considered and the loading & unloading time were excluded on
LABOR COST:
Driver: 1 x Rate/day / 8hrs/day x 80m 3/hr = ____/m3
Laborer: 1 x Rate/day / 8hrs/day x 80m 3/hr = ____/m3
EQUIPMENT:
Fuel: 10lit/hr x UC/lit / 80m3/hr = ____/m3
Rental: Rate/hr / 80m3/hr = ____/m3
Spare Parts: Rate/hr / 80m3/hr = ____/m3
CYCLE TIME:
With Load: 10km/trip x 60min/hr / 25 km/hr = 24 min/trip
Without Load: 10km/trip x 60min/hr / 30 km/hr = 20 min/trip
Loading, Spot & Manuever, Unloading & Delay = 12 min/trip
LABOR COST:
Driver: 1 x Rate/day x 0.93hrs/trip / 8hrs/day x 4.50m 3/trip = ____/m3
Laborer: 1 x Rate/day x 0.93hrs/trip / 8hrs/day x 4.50m 3/trip = ____/m3
EQUIPMENT
Fuel: 15lit/hr x 0.93hrs/trip x UC/lit / 4.50m 3/trip = ____/m3
Rental: Rate/hr x 0.93hrs/trip / 4.50m 3/trip = ____/m3
Spare Parts: Rate/hr x 0.93hrs/trip / 4.50m 3/trip = ____/m3
SUMMARY:
Base Cost = UC/m3
Labor Cost = ____/m3
Fuel Cost = ____/m3
Rental Cost = ____/m3
Spare Part Cost = ____/m3
Total = ____/m3