1. Executive Summary
Item Description Amount
1 This week executed amount 513, 624.2
2 This week planned amount 1,184,246.58
3 Executed Vs. Planned (%) 43.37%
In fact, the overall project progress had been under a delay due to the poor
performance of the contractor.
The primary purpose of this report is to indicate the contractor is trying get on track. On
this week, it seems the performance of the contractor is hopeful and increasing
gradually. Actually, if the rate of progress continue increasingly as it is, the project
significantly will become healthy.
2. Progress During the Reporting Week
a. Bulk excavation in ordinary soil
b. Mild steel reinforcement work preparation
c. Concrete mixing plant construction
d. Construction material delivering.(galvanized steel pipes for shoring work, stone, sand
and aggregate)
3. Construction Equipment
Excavator(1), Loader(1) and Truck(3)
Generator(1), water pump(2) and grinder(1)
4. Problems Encountered
a. Medium intensity rainfall
Page 1 of 4
ACUTE ENGINEERING P.L.C.
5. List of Attachment
5.1. Photographs
Page 2 of 4
ACUTE ENGINEERING P.L.C.
Page 3 of 4
ACUTE ENGINEERING P.L.C.
Page 4 of 4