Professional Documents
Culture Documents
SPE 25571
This paper was prepared for presentation at the SPE Middle East Oil Technical Conference & EXhibition held in Bahrain, 3-6 April 1993.
This paper was selected for presentation by an SPE Program Commillee following review of information contained in an abstract submilled by the author(s). Contents of the paper,
as presented, have not been reviewed by the Society of Petroleum Engineers and are sUbject to correction by the author(s). The material, as presented, does not necessarily reflect
any position of the Society of Petroleum Engineers, its officers, or members. Papers presented at SPE meetings are subject to publication review by Editorial Commillees of the Society
of Petroleum Engineers. Permission to copy is restricted to an abstract of not more than 300 words. Illustrations may not be copied. The abstract should contain conspicuous acknowledgment
of where and by whom the paper is presented. Write Librarian, SPE, P.O. Box 833836, Richardson, TX 75083-3836, U.S.A., Telex, 163245 SPEUT.
455
2 AN ALTERNATIVE METHOD OF INSTALLING ESP'S SPE 25571
Because some platforms are not ideally arranged for rig equipment is much more compact and modular than that
operations, a jack-up vessel may be required to support of a conventional rig.
the rig and the ancillary equipment. The cost and
additional mobilization time associated with this DESCRIPTION OF SYSTEMS
procedure can make the ESP economics less than
desirable. In many cases, the time required to mobilize The surface equipment for a cable and/or coiled tubing
the rig may cause the ESP to remain idle for a deployed ESP completion will include the following:
considerable period of time, and the loss of revenue
associated with this downtime may overshadow all other • Injector
costs. • Tubing reel
• Operator's console
The single-cable-deployed pumping system (COPS) has • BOP stack
demonstrated its effectiveness as a viable option to the • Crane (capable of lifting the spool of cable and the
rig-deployed system. The purpose-built cable is designed reel with coiled tubing)
to withstand the rigors of the downhole environment as • Cable reel
well as the loads imposed during installation and retrieval • Scaffolding to create a work window.
of the ESP. This method of deployment is the most • Diesel hydraulic power unit
straightforward of the current systems, offering the
following advantages: (1) There is no need to attach the Since the COPS cable uses the tubing storage drum in
cable to a base tubing; thus, installation speeds can be in this installation, one less drum is required than is shown
the range of 100-1 20 ft/min; (2) the flow area provides in Figure 1. This equipment is almost identical to the
sufficient capacity to consider rates as high as 30,000 standard package needed for normal coiled-tubing
B/O; (3) the surface equipment offers proven operations.
technology, being a modified coiled tubing injector; and
(4) the system can be easily transported because of its A purpose-built connector attaches the ESP to the coiled
modular design. tubing. The connector, as shown in Figure 2, features
metal-to-metal sealing and will withstand the torque
The concept of the coiled-tubing-deployed pumping produced by the ESP motor. Connector make-up does
system (CTOPS) for ESP's is now being looked upon as not require any preparation of the tubing other than
a viable, though untried, option. Enhancements in cutting to length and cleaning of the 00. This connector
continuous tubing technology and the increase in sizes of is relatively new and is considered a critical component
tubing offered have given this option even more of the ESP system. The availability of this device
credibility. At this time, 3-1 /2-inch-00 continuous tubing illustrates the attention this technology has attracted.
is available in lengths of up to 5,000 ft. In many
completions, this tubing could provide sufficient flow The downhole equipment for tubing flow, coiled-tubing-
area to allow production rates of 8 - 10,000 B/O. Annular deployed system is identical to the equipment used for a
flow completions are available to accommodate even conventional ESP installation. The power cable is
higher flow rates. Coiled tubing shares many of the supported along the 00 of the coiled tubing by protective
benefits of the jointed tubing such as: the capability to clamps or metal bands that grip and centralize the coiled
push the ESP into the well, a feature particularly useful tubing in the well. These devices are already in use in
in highly-deviated wells and/or when the dogleg severity jointed pipe installations and need only slight
poses a problem; the capability to provide a flowpath for modifications to enable them to work satisfactorily with
circulating fluids into the well if any cleanout is desired; coiled tubing. Because there are no connection
and the capability to immerse the power cable in a benign protuberances on the coiled tubing 00, there is less
completion fluid rather than in a corrosive well effluent. possibility of damage to the power cable during the
Additionally, with the CTOPS, the power cable is deployment. Additionally, because the coiled tubing is
attached to the 00 of the coiled tubing, and because continuous, it does not provide a site for corrosion to
there are no protuberances on the 00 of the tUbing, take place as in the case of threaded pipe.
there is less likelihood of the cable becoming damaged
during installation or retrieval; installations are faster The downhole equipment for the COPS or the annular-
because there are no tubing joints; and the surface flow CTOPS differs slightly in that the pump is located
below the motor. The ESP suppliers refer to this
456
SPE 25571 CLARK E. ROBISON AND DON C. COX 3
arrangement as an inverted pump assembly. Terminating restriction to the deployment speed in a cable-deployed
the cable into the motor eliminates the motor flat, which ESP is the need to allow pressure equalization of the
is common to all ESP installations and thereby increases pump assembly, which may result in an upper limit
the reliability of the ESP assembly. In field tests, a constraint of 120 ft/min. With coiled tubing installations,
landing nipple was used in the production tubing to the attachment and removal of the protective cable
locate the ESP. A locking-module discharge head was clamps or metal bands slows the operations.
added to the ESP assembly between the pump and the
motor to facilitate location of the ESP assembly in the The coiled tubing system can be installed in wells with
wellbore. For field tests, the size of the production much higher deviation than the cable system. Coiled
tubing was 7-inch, which is required with 540 series tubing provides sufficient stiffness to push the ESP past
ESP's. The annular flow COPS is optimized for very high doglegs and where excessive friction of the ESP
flow conditions. assembly might present difficulties in reaching the
desired depth. In contrast, the cable-deployed system
COMPLETION EQUIPMENT must rely on the weight of the ESP assembly to pull the
system into the well, which typically results in an upper
The completion equipment for a COPS or CTOPS limit of 60 degrees. Most pump suppliers have set a
installation will vary, depending upon whether the limitation on dogleg severity of 12 degrees per 100 ft. 4
production is flowed up the coiled tubing or up the Any build angle greater than this could result in
annulus created by the production tubing and cable or the permanent deformation of the pump assembly, which
coiled tubing. In an annular flow (AF) system, an would render it inoperative.
inverted pump is the preferred ESP configuration, and
this requires some means of isolating the inlet of the Considerable effort has been expended to define a
pump from the outlet. In a tubing flow (TF) system, a calculation routine to assist in predicting the operational
conventional ESP is preferred, and much of the existing limits of the systems (Figure 4).5 The mathematical
ESP completion equipment is readily available. model used to prepare this graph is presented in the
appendix of this paper. With this "cookbook" calculation,
The live well test of the COPS was an annular-flow it is possible to predetermine the size of the pump and
system, and a landing nipple in the production tubing tubing, determine whether annular or tubing flow is
string (7-inch) was employed to locate the pump preferable and predict the maximum setting depth
assembly. The nipple served as a receptacle for the allowed. This tool is invaluable in facilitating the initial
locking module discharge head, which formed a seal planning for an ESP installation.
between the inlet and outlet of the pump, and provided
a flowpath for the production. The physical limitations SUMMARY
imposed by all of these functions resulted in the 7-inch
tubing string selection. There is a potential for this The use of a purpose-built power cable for installation of
mandrel to be reduced slightly, but in most COPS ESP's has been presented as a tested and proven viable
installations, a production tubing string of at least 6-5/8- option to deployment of ESP's with a conventional rig.
inch will be a requirement. The use of coiled tubing to deploy ESP's has been
presented as a logical extension of a proven technology,
In a tubing-flow installation (only CTOPS), the completion lacking only actual usage as proof of its viability. Both
equipment is very similar to a conventional ESP. A deployment techniques offer unique advantages to the
packer is typically required when the gas/oil ratio exceeds operator and may afford a significant cost improvement
the limits imposed by the pump supplier, and a downhole over conventional rig-deployed ESP's.
separator is employed; or when a regulatory requirement
must be met. In either case, proven completion The more significant features of both installations are
equipment is available in a wide range of tubing/casing compared in Table 1. A simplified calculation routine has
sizes and weights. been devised to predict the operational characteristics of
the coiled- tubing deployment system. In addition, a well
OPERATIONAL CHARACTERISTICS completion system that will satisfy many installations has
also been presented. A live well installation appears to
Cable-deployed ESP's are the fastest to install and be the only part of the coiled tubing picture that is
retrieve of any of the alternative methods. The only missing.
457
4 AN ALTERNATIVE METHOD OF INSTALLING ESP'S SPE 25571
REFERENCES
F = WT'll:x1jJ sin(90
180
-..t)
2
1. Bayh. Russell I.. III and Neuroth, David H.: "Enhanced
Production from Cable Deployed Electrical Pumping
Systems," paper SPE 19707 presented at the 1989
SPE Annual Technical Conference, San Antonio,
+~
IW':7tx1jJ
~80 COS(9o~1)-2[Wp+W~D]
3. Robison, Clark E. and Cox, Don C.: "Alternative then the pump and tubing in that portion of the well
Methods for Installing ESPs," paper OTC 7035 profile will no longer move by gravity alone but must be
presented at the 24th Annual Offshore Technology pushed down and along the wellbore. For such an angle
Conference, Houston, Texas, May 4-7, 1992. and coefficient of friction, there exists a length where the
frictional drag causes the tubing to buckle, first
4. Gallup, Robert: "ESP's in Horizontal Wells, paper
II
sinusoidally and then helically. A generally held opinion is
presented at the 1990 Society of Petroleum that helical buckling will result in a locked condition
Engineers Electrical Submersible Pump Workshop, wherein the tubing can no longer be forced to move
Houston, Texas, April 30-May 2, 1990. through the well. Actual field experience in coiled-tubing
well logging operations indicates that the tubing usually
5. Robison, Clark E. and Cox, Don C.: "Cookbook can be forced to considerable additional depths without
Calculations For Choosing an Alternative Method of damage.
Installing an Electric Submersible Pump (ESP), paper
II
presented at the 1992 Society of Petroleum Nevertheless, the onset of helical buckling is an important
Engineers Electrical Submersible Pump Workshop, criterion in setting maximum running depths in highly
Houston, Texas, April 29 - May 1. deviated wells. Equation 2 is based on work done by
Chen, Lin, & Cheatham on tubular buckling in horizontal
APPENDIX wells. 6 The equation calculates the length at which
helical buckling will occur for coiled tubing with an ESP
The following equations can be used to determine the attached.
required forces to deploy and retrieve the ESP, the LD = [(A x B) - C] 0.0833
running depths of the installation, and the production
flow capacities accommodated in coiled tubing ESP
completions. A = 1
~cos(90 - 1jJ) - sin(90 - 1jJ)
Each coiled tubing size has an allowable limit on the force . (2)
that can be pulled on the tubing; therefore, the force E(D 2 + ~)
B
needed to retrieve an ESP is the usual factor that limits PT(C - D)
the maximum running depth of an installation. Equation
1 is a readily-used, single equation that calculates this
force. It can be derived from the five equations illustrated
in Figure 3 by allowing for only one division of the total
build angle til. Although the results of Equation 1 are not
as accurate as the process described in Figure 3, the Flow Capacities
results are within 8% or less.
After using Equations 1 and 2 to calculate the running
In highly deviated wells, when the tangent of the depths and the required forces, then the flow capacities
wellbore angle exceeds the sliding coefficient of friction that the coiled tubing can accommodate must be
present between the ESP, the tubing, and the wellbore, determined. Production flow rates are often determined
458
SPE 25571 CLARK E. ROBISON AND DON C. COX 5
by the well productivity index (PIl, reservoir conservation 6. Electric power cable weight. .. 1.8 Ibm/ft
considerations, and the ESP selection. However, even 7. Electric power cable diameter .... 1.4 in.
with a well of limitless PI and an ESP of infinite capacity 8. Casing 7 in - 29 Ibm/ft
but limited discharge pressure, a maximum production 9. Specific gravity of produced fluid.. 1.016
rate exists that cannot be exceeded due to fluid friction. 10. Viscosity of produced fluid .. 1 centipoise
Equation 3, a surprisingly simple equation, which
11. Coefficient of friction 0.4
incorporates an explicit friction factor suggested by
12. Build radius 5.73°/100ft
Cheremisinoff, 7 gives reliable results for turbulent flow of
Newtonian fluids in commercial pipe and tubing.
Of course, different criteria will produce different
numbers; however, Figure 4 shows the capabilities and
Q = 12,822.86(l)2.83(AP)0.S43 ..... (3)
relationships for a family of typical completions.
P~467 v 0.087 LT
Sample calculations for the well profile of Figure 4 with
75° deviation and 2-3/8 x 0.198-inch wall coiled tubing
illustrate the use of these "cookbook" equations in Table
For laminar flow (Reynolds numbers less than 3,000),
No.1. Maximum depth is based on limiting the pulling
Equation 4 can be used to calculate tubing flow rates.
force on the tubing to 75% of yield.
459
Table 1.
SAMPLE CALCULATIONS FOR THE WELL PROFILE OF FIGURE 4
F = 72,700 lb
WT = 4.709 + 1.8
= 6.509 lb/ft
r = 1,000 ft
= 75°
'"
Wp = 4,000 lb
p. = 0.4
H =500
Substituting into equation 1 and back-solving for 1.0:
+ 0.41
6 50911
• ~180ooo)(75) cos(9O -1i) -2(4,000 + 6.509Lol[O.4cos(9O - 75) + s1n(90 - 75)]SI~~)1
+ (4,000 + 6.509Lol(O.4cos(90 - 75) + 31n(9O -75] + 6.509(500)
L D = 11,652
Since the deviation from vertical is 75°, this is a "highly deviated" well. The tangent of the angle from horizontal is
0.268, which is less than the coefficient of friction of 0.4. Helical buckling may, therefore, be the limiting factor on
depth. Using equation 2,
2
1 3Oxl(jl(2.375 + 1.96g2} 4(4,000) )0.0833
L
D
= [ 0.4<:os(90 - 75) - sln(90 - 75) 0.284(6.184 - 2.375) 'It (0.284)(2.3752 -1.96g2)
= 9,767ft
1VD = 5OO+1,OOO(sin75)+9,767(cos75)
= 3,994ft
These numbers are less than the amounts for Equation 1; therefore, maximum depth of deployment may be limited by
helical buckling when running in rather than tubing tension when pulling out.
460
SP£25511
Table 1. (Continued)
Flow rates for tubing flow from the 4,482 TVD can be calculated from Equation 3. The pressure available to create flow
is the pump discharge pressure minus the wellhead pressure and static head pressure. The total length of tubing is
and
Substituting,
R = 1.4758(3,568)(63.4)
N 1.969(1)
= 169,549
For annular flow, four times the hydraulic radius is 3.077 inches.
Reynolds Number is
R = 1.4758(11,545)(63.4)
N 3.077(1)
= 351,062
461
TUBING STORAGE DRUM
/ ' (POWERED)
END SUB
SLIP SEGMENT
MIDDLE SUB
~ METAL-TO-METAL SEAL
BACK-UP RING
Fig. 1
The Installation of a Tubing
Deployed ESP
SPE25571
the drag force of the pump & installation string moving
up the inclined section of the wellbore is: F = [Wp -+- WtL ] [lLcosa + sina] _
o p
The normal force between the string & wellbore
through the radius section is: nmm_mm Kn = ~t;~a cos [a + a (N-.5)]- 2F(N_1) sin ~ n m • • __ n n n m n m m n n n 2
If K is (+) the string is in contact with the lower side of
the wellbore. If K is (-) the string is in contact with
the upper side of the wellbore.
The increase in force needed to move upward in the
radius section is: If K is positive (+) n __ Fn = ~t;~a sin [a + a (N-.5)] + ILK(N) + F(N.1) . m _ n n n n n m n n n m 3
,~~ If K is negative (-) _n_ Fn =180 sin ~:: (N-.5)] + IILKI + F(N-1) m m m . __ m m m n m n m _ m 4
1
The drag forces through the radius section are summed for as many divisions (N) as desired for accuracy.
H (5 divisions are usually adequate.)
The "rtaoe to"e " ..dod '0 ",,';eve the pump ;"stalla,;O" ;" F" = WH + ~F" .5
F2 = Wrrrra
180 sm. [a + 3a] + IL K2 + F1 If K'IS (+)
2"
If K is (-)
Pump Weight, Ib
String Weight, Iblft
Radius, ft
IL Coefficient of Friction
K Normal Force, Ib
K1 = Wrrrra cos [aa
+ -] - 2Fa sin
. -a
180 2 4
F1 = Wrrrra sin
180
[a +~]2 + ILK1 + Fa If K1 is (+)
1K
2K
3K
4K
5K
Coiled Tubing
Depth Limits Due
.j:>.
0)
.j:>.
-E'>c 6K
7K
to Helical Buckling
Vs Angle of Deviation
ן-
12K
!~ngle of De"ation in
10 Degrees from Vertical
7 Electric Power Cable Diameter -------------- 1.4 in
8 Casing -------------------------------------------- 7" 291b
9 Specific Gravity of Produced Fluid ---------- 1.016
10 Viscosity of Produced Fluid ---------- 1 Centipoise
11 Coefficient of Friction ------------------------------- 0.4
13K...l.. 0° 12 Build Radius ------------------------------- 5.73°/1 OOft
Fig. 4
Maxiumum Depths and Flow Rates for a Family of ESP Completions