CASE STUDY

Use of Deswik.CAD
for underground surveying

Company: Independence Group NL, Nova Project | Mining Method: Underground Metals | Country: Australia

OVERVIEW
In May 2015, Stephen Rowles and Luke Waller from Independence
Group NL began work at the new Nova Project in Western Australia.
They were tasked with setting up best of breed systems for the
survey department. As Deswik was already in use by the planners,
its survey functionality was reviewed and found to show potential.
Working in conjunction with the Deswik development team, their
core CAD platform was enhanced to suit the site needs and simplify
the typical surveying processes.

SOLUTION
• It was paramount that Deswik Survey to the polylines (floor, shoulders,
integrate with the total stations used backs, etc.), updating the drive solids is
underground. Deswik Survey has the now simply a case of refreshing the
ability to read and write the native Leica wizard. While this creates one layer for
DBX files to transfer data between the whole mine, filtering by the ‘level’
Deswik.CAD and the instruments. attribute allows the user to inspect any
Other file types are also supported. level or area they wish.
• By adding the survey tools into Deswik. • In September 2015, the decision
CAD, these survey functions are built was made to begin transferring all
upon an already robust mining specific underground work from the existing
CAD platform and can take advantage software to Deswik.CAD. In the weeks
of existing CAD functionality including a preceding this, advice was sought from
powerful solids handling engine. Deswik and the onsite engineering
team to build the most robust system
• One example of this is the creation of possible. This needed to fulfil all the
drive solids from the survey as-builts. requirements of the survey department
With the previous software on site, the while at the same time allowing the
process had to be performed manually attributes and filters to follow the rules
or have a script written to automate that had already been created by the
it. Deswik.CAD has a process in place engineers. This ensured continuity
called the Tunnel As-Built wizard. By throughout the mining sequence.
using some simple attributes linked

IMPACT
• One of the highlights has been the the survey team will focus their
plotting setup within Deswik.CAD. attention to making sure that the
The interactive nature of the plotting production side of Deswik Survey
windows allows changes to be made works just as well as the current
in the model viewport which then release. While the tools will already
modifies the plot. This represented be in place to facilitate this, they will
a major shift from the previous be coordinating with Deswik for ways SEAMLESS INTEGRATION
software and has allowed a significant to improve the process and make the
improvement in the quality of plots. platform even more impressive than it
• Because of the ease of use and is already.
presentation of the plotting, the • The survey functions in Deswik.CAD
decision was made to produce the now enable data generated by the
statutory plans required by the engineers and surveyors to be used
governing body in Western Australia in by each other without the need for file INTERACTIVE PLOTTING
Deswik.CAD. conversions. This has allowed seamless
• As the Nova Project transitions from integration when transferring data
lateral development to full production, between the mining departments.