ID progress WorkOrder # TAG Location Shutdown Enact Hydrotest Task Name Start Finish Inspection Type Resource Names

Start Finish Inspection Type Resource Names Predecessors


Code Required Y/N
Y/N
2 0% TEG TAR 2013 15 Aug 08:00 19 Sep 12:00 TEG TAR 2013

19 0% TEG FF SHUTDOWN (15 DAYS) 15 Aug 08:00 29 Aug 12:00 TEG FF SHUTDOWN (15
DAYS)
20 0% 435903 L-VA-020001 FF Y Y VESSEL,INLET SEPERATOR PACKAGE 15 Aug 08:00 29 Aug 12:00 Enact/Hydrotest+DMI

21 0% 436079 L-VD-043001 FF Y Y VESSEL - HP FLARE KO DRUM 15 Aug 08:00 29 Aug 12:00 Enact/Hydrotest+DMI

38 0% 436072 L-FE-045001 FF Y Y HEATER, ELECTRIC - FUEL GAS HEATER 15 Aug 08:00 29 Aug 12:00 Enact/Hydrotest+DMI

39 0% 436112 L-VL-024005 FF Y Y K024-BDV-005 AIR RECEIVER (S.N.: 5480) 15 Aug 08:00 29 Aug 12:00 Enact/Hydrotest+DMI

40 0% 436082 L-VL-063001 FF Y Y VESSEL - AIR RECEIVER 15 Aug 08:00 29 Aug 12:00 Enact/Hydrotest+DMI

41 0% 436083 L-VL-063003 FF Y Y VESSEL - AIR RECEIVER 15 Aug 08:00 29 Aug 12:00 Enact/Hydrotest+DMI

42 0% 436080 L-VJ-045001A FF Y Y VESSEL, FUEL GAS FILTER / SEPARATOR 15 Aug 08:00 29 Aug 12:00 Enact/Hydrotest+DMI Enact/Hydrotest+DMI

43 0% 436081 L-VJ-045001B FF Y Y VESSEL, FUEL GAS FILTER / SEPARATOR 15 Aug 08:00 29 Aug 12:00 Enact/Hydrotest+DMI Enact/Hydrotest+DMI

3 0% TEG TRAIN 1 SHUTDOWN ( 10 DAYS) 30 Aug 08:00 09 Sep 17:00 TEG TRAIN 1
SHUTDOWN ( 10 DAYS)
4 0% 425500 L-HC-020101 TR1 Y Y EXCHANGER, HEAT,AIR COOLED - PRODUCTION GAS 30 Aug 08:00 09 Sep 17:00 Enact/Hydrotest DMI
COOLER
6 0% 436073 L-VB-024101 TR1 Y Y VESSEL, GLYCOL CONTACTOR 30 Aug 08:00 09 Sep 17:00 Enact/Hydrotest DMI

7 0% 436075 L-VD-024102 TR1 Y Y VESSEL - GLYCOL FLASH DRUM 30 Aug 08:00 09 Sep 17:00 Enact/Hydrotest DMI

8 0% 435895 L-VD-024105 TR1 Y Y VESSEL - FUEL GAS POT 30 Aug 08:00 09 Sep 17:00 Enact/Hydrotest DMI

10 0% 436242 L-VL-024107 TR1 Y Y K024-BDV-107 AIR RECEIVER (S.N.: 5481) 30 Aug 08:00 09 Sep 17:00 Enact/Hydrotest DMI

11 0% TEG TRAIN 2 SHUTDOWN (10 DAYS) 10 Sep 08:00 19 Sep 12:00 TEG TRAIN 2
SHUTDOWN (10 DAYS)
12 0% 435900 L-HC-020201 TR2 Y Y EXCHANGER, HEAT,AIR COOLED - PRODUCTION GAS 10 Sep 08:00 19 Sep 12:00 Enact/Hydrotest
COOLER
14 0% 436074 L-VB-024201 TR2 Y Y VESSEL, GLYCOL CONTACTOR 10 Sep 08:00 19 Sep 12:00 Enact/Hydrotest

15 0% 436807 L-VD-024202 TR2 Y Y VESSEL - GLYCOL FLASH DRUM 10 Sep 08:00 19 Sep 12:00 Enact/Hydrotest

16 0% 436263 L-VD-024205 TR2 Y Y VESSEL - FUEL GAS POT 10 Sep 08:00 19 Sep 12:00 Enact/Hydrotest

18 0% 436113 L-VL-024207 TR2 Y Y K024-BDV-207 AIR RECEIVER (S.N.: 5484) 10 Sep 08:00 19 Sep 12:00 Enact/Hydrotest

44 13% TEG ILI 2013 20 Sep 08:00 15 Dec 17:00 REG ILI 2013

45 13% 4TH QUARTER (OCT-NOV-DEC) 20 Sep 08:00 15 Dec 17:00 1ST QUARTER
(JAN-FEB-MARCH)
64 0% 454237 L-VK-063101A OL Y Y VESSEL - DRYER ADSORBER ( SN: S21753A/1A) 20 Sep 08:00 04 Oct 17:00 Enact/Hydrotest+DMI Enact/Hydrotest+DMI

65 0% 454240 L-VK-063101B OL Y Y VESSEL - DRYER ADSORBER ( SN: S21753A/1B) 20 Sep 08:00 04 Oct 17:00 Enact/Hydrotest+DMI Enact/Hydrotest+DMI

66 0% 454238 L-VK-063201A OL Y Y VESSEL - DRYER ADSORBER ( SN: S21753B/1A) 20 Sep 08:00 04 Oct 17:00 Enact/Hydrotest+DMI Enact/Hydrotest+DMI

Page 1
ID progress WorkOrder # TAG Location Shutdown Enact Hydrotest Task Name Start Finish Inspection Type Resource Names Predecessors
Code Required Y/N
Y/N
67 0% 454241 L-VK-063201B OL Y Y VESSEL - DRYER ADSORBER ( SN: S21753B/1B) 20 Sep 08:00 04 Oct 17:00 Enact/Hydrotest+DMI Enact/Hydrotest+DMI

68 0% ??????? L-VL-091001 OL Y Y TEG WORKSHOP AIR RECEIVER Fab Num: 67039 20 Sep 08:00 04 Oct 17:00 Enact/Hydrotest+DMI Enact/Hydrotest+DMI