Professional Documents
Culture Documents
Dilan Budak
ENGINEERING ETHICS
party in their atrium lobby. While many people who attended the event were standing and
dancing on the suspended walkways, connections supporting the ceiling rods which held up
the second and fourth-floor walkways along the atrium fell down, and both walkways
collapsed on the first floor crowd. The fourth-floor walkway collapsed onto the second-floor
structure remained intact. It has been one of the most destructive structural failure, regarding
to loss of life and injuries; Hyatt Regency,Kansas City walkways collapse resulted of 114
dead and more than 200 injured (About 1500 people attended the event at the hotel)
Havens Steel Company Professional Fabricator: who fabricated and erected the atrium steel
G.C.E. International, Inc. (1980 called Jack D. Gillum & Associates, Ltd. changed name to
G.C.E. in 1983): The engineering design team.. G.C.E. was responsible for preparing
structural engineering drawings for the Hyatt project: three walkways of the atrium area of the
hotel
Jack D. Gillum (the supervisor of the professional engineering of G.C.E.) and Daniel M.
Duncan (working under the direct supervision of Gillum, the engineer responsible for the
Almost for one year of investigation of the accident after the walkways collapse brought out
some facts:
1) In January and February, 1979, the design of the hanger rod connections was changed
by the fabricator from one-rod to a two-rod system for use at the fourth floor
walkways to make assembly easier. Doubling the load on the connector caused the
walkways collapse. The fabricator declared that his company (Havens SteelCompany)
firm) about change confirmation, but calls from Havens refused by G.C.E. Therefore
doubling the load on the connector, and controversial communications between the
Why did Haven make this change? Because of two issues: first, the Gillum design required
would be very expensive to fabricate and install. Second, the suspension rods would
determined this is going to be unacceptably costly to produce and install. For this
Corporation) called in the inspection team to investigate of the reason of the roof
collapse on-site inspection, but the inspection team stated that there is no task to
control any engineering or design work. However; in testimony, G.C.E. stated that
they asked on-site project representation from the owner during the construction stage;
yet, the owner did not fulfill these requests due to extra costs of providing on-site
inspection.
-Incorrect communication
-Leak of checking design, excessive trust in Duncan (result of inspection team’s investigation
report)
-Leadership
-Teamwork
- Improper design ( due to lack of consideration of all forces acting on a connection, mainly
those related with volume changes / lack of consideration of stresses of new size materials
CONCLUSION
The engineering profession is more complex with several uncertainties, several executable
and workable solutions. The Hyatt Regency walkways collapse is quite suited to multiple
human factors such as communication, risk adversity, and our ability to work with others
constructively. Ensuring the safety, health, and welfare of the public, ensuring clear
communication and providing quality in every step of the process are the basic principles that
G.C.E. was found responsible for the change from a one-rod to a two-rod system. Further, it
was found that even if Havens failed to review the shop drawings or to specifically note the
box beam hanger rod connections, the engineers could not do spot checks, and they were still
responsible for the final check. G.C.E had too much trust in Havens. This is the negligence in
A number of people lost their engineering licenses, and a number of firms went bankrupt. As
a result of the Hyatt Regency Walkways Collapse, the American Society of Civil Engineering
(ASCE) took a report that states structural engineers have full responsibility for design
projects. The Hyatt Regency Hotel project takes an important place about responsibility and
design steel-to-steel connections in construction. We must figure out the effects of negligence,
lack of comminication and the engineer's design responsibility to protect the public and
environment. The Hyatt Regency Walkways Collapse provides a clear example of the
importance of accuracy and rigour in engineering design and shop drawings (especially in the