Professional Documents
Culture Documents
Introduction.
The formwork system (FWS) provides the
geometry and strength required for the
reinforced concrete structure to produce the
desired form and structural design
characteristics of the cured concrete. In
addition, formwork-related operations such as
erecting the FWS, installing the rebar, pouring
the concrete, and disassembling the FWS are
performed continuously for the life of the Figure 1. Before Formwork Collapsed. Photo Guillermo Villareal
Background.
The Cultural Center Santa Teresita is located on
Costanera Avenue, Buenos Aires, Argentina. The
Multicultural Space will have more than 3,200
square meters and will be the largest space for
culture on the coast and throughout the region. Its
facilities will have a recording room, theater, and
specific rooms for different artistic expressions
that will be taught through the Municipal School Figure 2. After Formwork Collapsed. Photo: Guillermo
Villlareal
of Art.
The structure was a slab 20 meters wide by 30 meters long. It was more than 12 meters tall at the
point of the accident. On the afternoon of 2 March 2008 workers were ready to start pouring concrete.
Twelve workers were over the formwork slab when the temporary structure failed. Six workers died
in this engineering mistake. According to the site personnel, the slab formwork could not be used
because it was not totally stable. The base ground was too unstable, the soil was soft and the 12 m tall
had critical criteria to successfully do the labor.
Conclusion.
Construction work will always be constrained by many factors like time, cost, and space. It will be
more effective if hazards are considered upstream during design so that inherently safer methods of
work can be implemented during construction. All stakeholders must see safety as an important
aspect of their work. If not, safety regulations, risk assessment, and safety measures will have no
effect at all.