pavement work tips - No 3 November 2010

INTRODUCTION local irregularities and


Key Summary
Smooth riding asphalt pavements don’t just improving the ride
happen. There are at least five major areas of quality of existing
influence: surfaces. Joint matching This issue of
devices can be used to “pavement work
• JOB PLANNING tips” discusses
follow a kerb line or
• LEVEL CONTROL some of the
adjoining asphalt mat.
• UNIFORM SPREADING factors that affect
Manual control riding quality,
• JOINTS
The operator must and how to ensure
• COMPACTION. anticipate the depths a smooth riding
required and make asphalt pavement.
JOB PLANNING smooth, progressive
Shape Correction adjustments without the need for over-
correction. Anticipation and smooth screed
Asphalt placed over an irregular surface will
adjustment are key operator skills.
reflect some of the existing shape through
differential compaction. Significant UNIFORM SPREADING
irregularities should be removed using a
Continuous Paving
regulating layer or profiling prior to overlay.
The key to uniform spreading is a continuous,
New Pavements steady, forward speed of the paver. Paver speed
On new pavements, thick layers are good should be matched to plant production and
for achieving density, but tend to move more delivery rates. Stopping the paver allows the
screed board to settle slightly and can leave a
under rolling and make it more difficult to
small transverse ridge in the pavement. This
maintain the required shape. becomes more pronounced the thinner the mat
On the Job being paved.
Plan the location of joints to keep them to a If the paver is stationary for any length of time,
minimum and out of the wheel paths. Plan the asphalt in front of the screed can cool. The
extra resistance of the cooled asphalt causes the
asphalt delivery rates to maintain steady,
screed to rise as it moves forward again. Where
continuous paving without excessive standing there is a long delay between trucks, the screed
of mix prior to laying. Lay outwards from should be lifted and a proper transverse joint
fixed levels. constructed.
It is, therefore, essential that a sufficient
LEVEL CONTROL number of truckloads of asphalt are on site
The Floating Screed Paver before paving is commenced to avoid stop–start
The paver is designed to provide a smooth problems, but not so many that the mix can go
surface behind the screed with the least cold before being used.
amount of interference by the operator. Asphalt Delivery Trucks
Constantly adjusting the screed height, such Delivery trucks must not be allowed to bump
as chasing levels, can cause roughness in the the paver by directly reversing onto it.
finished surface.
The truck should stop short of the paver, in
Automatic controls neutral, with just enough brake pressure
Greatest precision is obtained from fixed necessary to prevent the truck rolling downhill,
string lines and laser lines, although these and allow the paver to push onto the truck and
should only be used when appropriate to the propel it forward while asphalt is tipped slowly
job conditions. into the paver hopper. Spillage between the truck
Travelling beams are useful for taking out and paver should be avoided.
continued on reverse

pavement work tips are produced by AUSTROADS in conjunction with AAPA


For more
page 2 information on any
of the construction
practices discussed
A materials transfer vehicle (see photo) may be Excessive speed of the steel roller can push in "pavement work
used to ensure paver speed is continuous, and the material out of shape. Five km/h is tips'', please contact
removes the need for trucks to load directly into the considered a suitable maximum speed for either your local
paver. The transfer vehicle also avoids spillage steel rollers. AUSTROADS
between the paver and delivery trucks. representative. or
If the mix is too hot or particularly tender, AAPA:
a bow wave may be created in front of the tel (03) 9853 3595;
Asphalt Flow through the Paver roller. fax (03) 9853 3484;
The paver must maintain a constant uniform Rollers with only one driven roll should be e-mail:
amount of asphalt in front of the screed. info@aapa.asn.au.
operated with the driving roll nearest the
paver. A complete list of
Asphalt Temperature “pavement work
Rolling normally commences with the first tips” issues is
Variations in asphalt temperature will also affect pass on the low side of the mat to avoid available on
flow under the screed. lateral movement of uncompacted asphalt AAPA’s website:
downhill away from the roller, except that www.aapa.asn.au
Mechanical Condition joints should always be compacted first. Issues may be
A paver in poor condition will not spread Each forward pass of the steel roller downloaded using
smoothly. should be in a straight line, reversing in the Adobe Acrobat
same path, with changes of direction or Reader. Copies may
lateral position only done on mix that has also be obtained
Hand Spreading from AAPA.
already been compacted by a previous pass.
Slightly more compaction allowance must be
Each pass should overlap the previous run Material may be
made for areas of handwork, compared to machine and finish at a different point to avoid a freely reproduced
laid work. Hand spreading and shaping must also be continuous dent being formed across the providing the
uniform and require skilled workmanship. source is
surface.
acknowledged.
On deep lift paving, a strip of about 300
JOINTS mm along the unsupported edge can be left
This edition was
prepared by
Proper construction of joints is essential. to be rolled last. members of the
Transverse joints should be kept to a minimum and Rollers should not remain stationary on a Austroads Asphalt
staggered between layers. They must be completed warm mat, as they may leave dents. Research Reference
Group.
correctly the first time, as correction is difficult and
tends to increase the problem by creating more SUMMARY
joints. Profiling of existing surfaces may be required Remember
in some cases to ensure a smooth transition at the
• Plan the job properly
ends of work.
• Apply the most suitable level control system
COMPACTION • Maintain smooth, steady paving
As with spreading, smoothness and uniformity of • Set up joints properly
rolling is the aim. • Compact the surface evenly.
Initial compaction is done with a steel roller.

Asphalt paving with a Materials Transfer Vehicle.