You are on page 1of 5

Tolerances in concrete construction

We need greater clarity and realism in specifications and also


agreement on how tolerances are to be measured and what to do
in specific instances of noncompliance

By the Editorial Staff of precision in building, and the rela- wall may be small compared with the
Concrete Construction tion of all this to cost. surface of a dam to be viewed from a
The need to specify tolerances considerable distance. Within a

W hen a contractor finds that


something won’t fit, or when
the architect or owner thinks that the
From among the possible defini-
tions of tolerance the one we have
hydraulic structure tolerances must
be specified to ensure that friction
losses are not high enough to signif-
chosen to use in this article is given in
walls aren’t vertical or straight or icantly reduce hydraulic capacity or
Cement and Concrete Terminology,
that the floors aren’t flat or level efficiency. Tolerances in hydraulic
by American Concrete Institute
enough, someone is unhappy with the conduit must also ensure sufficiently
(ACI) Committee 116: “the permit-
degree of tolerance achieved. Maybe smooth surfaces to prevent serious
ted variation from a given dimension
the construction operations weren’t damage from erosion.
or quantity.” This variation can
precise enough. Maybe the specifi-
usually be in either of two directions Considerations that
cations weren’t tight enough or clear
and so can be regarded as positive or should determine tolerances
enough. Maybe the structure as de-
negative. Thus a tolerance in level of It is common for a specifier to pick
signed couldn’t actually be built to
a ceiling amounting to ¼ inch in 10 tolerances out of specifications
the requirements specified. In any
feet(1)* of length could represent con- previously used in the design office
case, some accommodation must be
crete that is up to ¼ inch(2) above the or from ACI or other published stan-
made—by repair, adjustment or just
target level or as much as ¼ inch dards. This practice can lead to ex-
plain acceptance of a bad situation.
below. cessive costs by specifying closer tol-
And, someone most likely will be
The immediate reason for specify- erances than needed. Some specifiers
disappointed.
ing tolerances is to establish the ease and designers have profitably found
Part of our present situation in
of construction without the necessity ways to confer with constructors dur-
construction is that we are not entire-
of later modifying parts to fit togeth- ing the design process so that con-
ly sure what degree of precision is
er. A more long-range reason is to structors can point out any unfore-
needed in each individual circum-
ensure that the structure will perform seen construction difficulties im-
stance, or what degree of precision
as needed, particularly with respect posed by the tolerances. Construc-
can be achieved at reasonable cost.
to safety. The parts of the structure tors can ask questions about the
There is a need for all members of
should have adequate strength and reasons for the degree of precision
the construction industry to compare
be of such shape and dimensions that specified and both parties can confer
notes on what we want, what we real-
there is no danger of structural about the possibility of alternative,
ly need, what practical considera-
failure through movement of the more economic designs and methods
tions affect any particular degree of
parts. Joints should be sufficiently of construction.
close to the design to perform prop- The tolerances achievable with
EDITOR'S NOTE: The following
erly and, where necessary, be capable precast concrete and cast-in-place
article is reproduced from Concrete
Construction Magazine. It originally of being sealed against intrusion of concrete are likely to be quite differ-
appeared in the October, I979 edi- water, wind, dirt and debris. Toler- ent. Similarly the tolerances achiev-
tion of the magazine (beginning on ances on the location of reinforcing able with fixed forms, sliding forms
page 659), and was compiled by the steel should be adequate to ensure and other types of forming systems
professional staff of Concrete Con- the placeability of concrete all can differ. If the specifier arbitrarily
struction Publications, Inc. Con- around the reinforcing cage. establishes a tolerance, he may be
struction Dimensions wishes to ex- The tolerance required for ap- unknowingly prescribing the con-
press its appreciation to Concrete pearance depends to a large extent struction method to be used and
Construction for its permission to upon the distance from which the possibly thereby increasing the cost.
reprint the article, which we felt to be Sometimes it is difficult to predict
structure will be viewed. The toler-
of vital interest to our own reader-
ance for an architectural concrete the tolerance achievable. For exam-
ship.
27
ple, the foreshortening of jobsite pre- construction superintendent, report ing obtained in the field or the toler-
cast concrete beams during prestress- that they had “asked around” to ances it is possible to get.
ing may not conform to the designer’s find out how the tolerance tables in For that reason Birkeland and
predictions. Also, the amount of ACI 301 (Specifications for Struc- Westhoff made extensive measure-
camber in prestressed concrete beams tural Concrete for Buildings), ACI ments on a building in which they
is difficult to predict. In some cases it 347 (Recommended Practice for were involved. Since the building
might be possible to design a pre- Concrete Formwork) and other stan- seemed to be satisfactory to the
stressed concrete structure to accom- dards had been arrived at. They owners and similar in quality to other
modate relatively large tolerances in came to the conclusion that the data acceptable buildings the investigators
foreshortening or camber. A more had “been compiled in the equivalent felt that the deviations measured
usual way of handling the problem is of smoke-filled rooms with no direct represented acceptable tolerances.
to make a minor adjustment in the relationship to reality. In the absence They found that the slopes and sur-
form after job experience with of hard data, these committees have face curvatures of the floors were
casting of beams has begun to show had to rely on their judgment” (Ref- generally greater than the ACI stan-
what dimensions are actually being erence 1). These tolerance tables ap- dards in effect at the time. ACI 347
achieved. pear to be the best the industry has permitted a tolerance of 1/16 inch
Realistic, practical tolerances but there seems to be a considerable per foot(3) in the slope of a floor but
Phillip Birkeland, a consulting en- lack of understanding of how closely the investigators concluded that a
gineer, and Leonard Westhoff, a they match either the tolerances be- more realistic tolerance might be

TOLERANCES SUGGESTED BY ACI FOR Variation in cross-sectional dimensions of columns and


REINFORCED CONCRETE BUILDINGS*† beams and in the thickness of slabs and walls.
Minus . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1/4 inch(14)
Variations from the plumb. Plus . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1/2 inch (15)
In the lines and surfaces of columns, piers, walls and in ar- Footings.
rises Variation in dimensions in plan
In any 10 feet of length . . . . . . . . . . . . . . . . . 1/4 inch(1) Minus . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1/2 inch (16)
Maximum for entire length. . . . . . . . . . . . . . . . 1 inch (7) Plus . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 inches (17)§
For exposed corner columns, control-joint grooves and when formed or plus 3 inches(18) when placed against un-
other conspicuous lines formed excavation
In any 20 feet of length . . . . . . . . . . . . . . . . 1/4 inch (8) Misplacement or eccentricity
Maximum for entire length. . . . . . . . . . . . . 1/2 inch (9) 2 percent of the footing width in the direction of
misplacement but not more than . . . . . . . . . . 2 inches(19) §
Variation from the level or from the grades indicated on the Reductions in thickness
drawings. Minus . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 percent
In slab soffits, ‡ ceilings, beam soffits and in arrises of specified thickness
In any 10 feet of length . . . . . . . . . . . . . . . . 1/4 inch (1) Variations in steps.
In any bay or in any 20 feet In a flight of stairs
of length . . . . . . . . . . . . . . . . . . . . . . . . . . 3/8 inch (10) Rise . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1/8 inch (20)
Maximum for entire length . . . . . . . . . . . . 3/4 inch (11) Tread . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1/4 inch (2)

In exposed lintels, sills, parapets, horizontal grooves and In consecutive steps


other conspicuous lines Rise . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1/16 inch (21)
In any bay or in any 20 feet Tread. . . . . . . . . . . . . . . . . . . . . . . . . . 1/8 inch (20)
of length . . . . . . . . . . . . . . . . . . . . . . . . . 1/4 inch(12)
Maximum for entire length. . . . . . . . . . . . . . . 1/2 inch (9) * From Section 3.3.1 of ACI 347-78, Recommended Practice for
Concrete Formwork. The Standard also suggests other tolerances
Variations of distance between walls, columns, partitions not published here for precast and precast-prestressed members,
mass concrete structures, tunnel linings and cast-in-place con-
and beams. duits, slipformed structures, canal linings, siphons, culverts,
1/4 inch per 10 feet(1) of distance but not more than bridges and similar structures.
1/2 inch(9) in any one bay and not more than 1 inch(7)
total variation † Variations from plumb and linear building lines on upper stories
of high-rise structures (above 100 feet(22) high) are special cases
which may require special tolerances.
Variation of linear building lines from established position in
plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 inch(13) ‡ Variations in slab soffits are to be measured before removal of
supporting shores; the contractor is not responsible for variations
Variation in the sizes and locations of sleeves, floor openings due to deflection except when the latter are corroboratory
and wall openings. evidence of inferior concrete quality or curing, in which case only
the net variation due to deflection can be considered.
Minus . . . . . . . . . . . . . . . . . . . . . . . . . . . 1/4 inch (14)
Plus . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1/2 inch (15) § Applies to concrete only, not to reinforcing bars or dowels.

28
3/16 inch per foot(4). ACI 301 allow- It appears that no matter what sys-
ed a floor surface curvature of tem is used for specifying tolerances PROPOSED TOLERANCES
1/8-inch offset from a 10-foot (5)
there will always be some parts of a FOR PLANENESS OF FLOORS
straightedge. The investigators con- structure that are unacceptable. The AND OTHER FLATWORK
cluded that curvatures up to ½-inch number of these instances can be de- ACI Committee 302 is preparing a
(6)
offset from a 10-foot straightedge creased but frequently at consider- new “Guide for Concrete Floor and
might be acceptable. Other measure- able cost. It is simpler to plan to ac- Slab Construction.” This has not yet
commodate these by repair. been either published or adopted, SO the
ments on the building indicated that
proposed tolerances given here have no
the ACI 347 tolerance on intended Guidance for those who current authority and are still subject to
floor slab elevation was about the specify tolerances change. The new tolerances being sug-
same as they were measuring in the It should be possible for those gested by the committee are for the
building. Tolerances on distances directly concerned with construction maximum depressions between high
between columns required by ACI to clearly interpret the tolerance re- spots in a floor or slab for four classes
301 and 347 agreed fairly well with quirements in the construction speci- of finish:
what they measured. fications. Tolerances should be suffi- Class A finish
Although designers often specify ciently clear and specific not to give 1/8 inch below a 10-foot(23)
unrealistic tolerances without ques- straightedge*
trouble to:
tioning the lack of realism in the data • the contractor who prepares the Class A-2 finish
they have access to, they also often 3/16 inch below a 10-foot(24)
bid
accept the finished structure with all straightedge
• the job superintendent who
its deviations from the specified tol- Class B finish
determines materials requirements
erances. It is likely that neither 1/4 inch below a 10-foot(25)
and types of craftsmen needed
designers nor constructors know straightedge
• the shift foreman who is respon-
what tolerances are realistically ob- Class C finish
sible for setting lines and grades for
tainable; both think that the public is 1/4 inch below a 2-foot(26)
formwork and embedments straightedge
getting structures that are more ac- • the inspector who checks form-
curately built than they really are. * The Committee states that the tolerance
work for accuracy and strength for a Class A finish is “extremely difficult
In Europe, realistic tolerances before concrete is placed and expensive to achieve on large areas. [It]
have been established by statistical Several general guidelines can be should be specified only for critical areas
analysis of deviations. But in Europe stated for specifying tolerances. where such [a tolerance is] vital for the
operations that will take place in the area.”
considerable precasting is done, • Be certain that the design does
which makes it relatively easy to not demand tolerances that are
make dimensional measurements of unrealistic or unattainable.
elements and study them statistically. • Provide places where the in- Ambiguity is also caused by the
Another important factor is the in- evitable variations can be absorbed. practice of center-to-center dimen-
volvement of the design engineer in • Choose construction concepts sioning. The exact location of the
the selection of construction meth- that will ensure that critical dimen- center line of a column may be a
ods, a practice associated with in- sions are controlled directly and matter of opinion. The best practice
dustrialization of the European check these out with builders to be is to give dimensions to the face of
building industry. sure they are free of bugs. the concrete.
In the normal course of construc- • Dimension the drawing in such a Unfortunately it is all too easy for
tion the deviations of any set of mea- way that the inspector can measure a designer to assume that a building
surements from the intended value critical dimensions directly. can be built to zero tolerance and for
will fit the statistical normal distribu- • Emphasize or highlight critical him to design accordingly. The con-
tion curve. By calculating the stan- dimensions in drawing so that they struction of such a building may easi-
dard deviation from a large body of are forcefully called to the attention ly lead to trouble, cost everyone
measurements it can be determined of the constructor. more money than necessary and may
how many measurements are statisti- wind up in a lawsuit. The fact that
cally expected to fall within given The use of double dimensioning such a design may have been con-
limits. If tolerances were established on drawings inevitably leads to trou- structed successfully in the past can
in statistical terms, thus acknowledg- ble and should be avoided. This is the provide a false sense of security.
ing that a small number of measure- practice of showing both the individ-
Constructing within the tolerances
ments will fall outside an acceptable ual dimensions and the total dimen-
range, our tolerances might be more sion. It leads to uncertainty about Everything possible should be
realistic. which dimension can best be allowed done to avoid ambiguity. Much time
to float to meet all of the tolerance is wasted on the job over differences
requirements. This subject is well ex- about how to interpret tolerance re-
* Numbers in parentheses refer to metric
equivalents listed with this article. plained in Reference 1. quirements.
29
The constructor could wish that If he has underestimated the preci- cide to form the opening between
the specifications would supply all sion needed in any part of the job it is columns instead of the columns
the required tolerances. In practice, likely to cause trouble during con- themselves. This would lead to devia-
however, he must make his own deci- struction or later and cost him tions in the column width rather than
sion concerning most of them. This money. in the space between columns and the
involves study, to determine which A constructor would do well to tolerance would be taken up in the
tolerances are important; it calls for think out ahead of time the methods amount of concrete cover over the
both experience and intuition. The to be used in controlling tolerances. column ties.
constructor ultimately prices his job For example, in a situation where the Tolerances cannot be achieved un-
with his own particular concept of clear distance between columns is less they are controlled. The work
the tolerance requirements in mind. particularly important, he might de- begins at the time of surveying and
setting out the site and includes all
subsequent construction.
One recent advancement in the
control of dimensions, elevations,
plumbness, planeness and alignment
has been the introduction of lasers.
Their use in construction measure-
ment is discussed in the 7-page arti-
cle “Laser Construction Tools,”
Concrete Construction, September
1978, page 516.
Other methods of controlling tol-
erances are illustrated in the figures.
Figure 1 shows three simple meth-
ods of checking deviations of
angles. A template like that shown
in Figure 2 can be used to measure
warping. Warping of a vertical sur-
face can be measured with a stadia
rod equipped with leveling bubbles
and dial gages as shown in Figure 3.
The rod is set in Position 1 near one
vertical edge with the leveling bub-
ble in a fixed position and the dial
gages are adjusted to give a reading
of the distance between the rod and
the surface. The rod is then moved
to Position 2 and held with the level-
ing bubble in an identical position.
The distance that one dial gage has
to be moved in or out indicates the
amount of warping.
Bowing in a simple curve can be
measured by stretching wires tightly
over spacer blocks and measuring
down to the surface. Another meth-
od is to measure from the curve to a
straightedge.
Accepting out-of-tolerance work
Work rarely is rejected or tom
out simply because it is out of toler-
ance. This may be evidence that
specified tolerances are likely to be
more stringent than actually needed.
The type of out-of-tolerance work
that might require replacement are
slabs on grade that are intended to
30
drain but don’t, or concrete that is structure. This is simply a way of viation as descriptions of the
intended to accommodate installa- recognizing the fact that there is characteristic deviations allowable.
tion of machinery but does not pro- some economical limit to the degree Based on European experience toler-
vide sufficient room. of precision obtainable in concrete ances amounting to plus or minus 1.5
In precast work it is generally work. to 2.5 times the standard deviation
more economical to cast building Such a practice leads to an idea might be realistic. In the meantime
elements with a degree of precision that is now being considered in the everyone must do what they can to
that anticipates some out-of-toler- construction industry: describe tol- make tolerances realistic and to plan
ance elements. Then these elements erances in statistical terms, giving for efficient methods of meeting
are modified later for use in the both the mean and the standard de- tolerances during construction.

References (6) Recommended Practice for Concrete Formwork (ACI 347-78),


This article is based almost entirely on information from the follow- American Concrete Institute, Detroit, Michigan 48219.
ing sources:
(1) Birkeland, Philip W., and Westhoff, Leonard J., “Dimensional Metric Equivalents
Tolerances in a Tall Concrete Building,” Journal of the American (1) 6 millimeters in 3 meters (14) minus 6 millimeters
Concrete Institute, August 1971, pages 600-607. (2) 6 millimeters (15) plus 12 millimeters
(2) Stevens, Alan, “How Accurate is Building?” BRE News, Building (3) 0.5 percent (16) minus 12 millimeters
Research Establishment, Garston, Watford, United Kingdom, (4) 1.5 percent (17) plus 50 millimeters
Number 36, Summer 1976, pages 11-13. (5) 3-millimeter from 3-meter (18) plus 75 millimeters
(3) Holbeck, Kai, and Andersen, Povl R., “European Concepts of (6) 12-millimeter from 3-meter (19) 50 millimeters
Construction Tolerances,” Journal of the American Concrete In- (7) 25 millimeters maximum (20) 3 millimeters
stitute, March 1977, pages 101-108. (8) 6 millimeters in any 6 meters (21) 1.5 millimeters
(4) Stephan, Dean E., Jr., and Murk, Alan, “Establishing Tolerances (9) 13 millimeters maximum (22) 30 meters
in Concrete Construction,” Journal of the American Concrete In- (10) 9 millimeters in any bay or in (23) 3 millimeters below a 3-meter
stitute, May 1977, pages 208-211. any 6 meters (24) 5 millimeters below a 3-meter
(5) Graham, J.R., and Lindholm, E.A., “Concrete Tolerances—Im- (11) 19 millimeters maximum (25) 6 millimeters below a 3-meter
portance and Achievement in the Bureau of Reclamation Construc- (12) 6 millimeters in any bay or (26) 6 millimeters below
tion,” Journal of the American Concrete Institute, February 1978, in any 6 meters a 0.6 meter
pages 49-54. (13) 25 millimeters

31

You might also like