Professional Documents
Culture Documents
8003 e PDF
8003 e PDF
By the Editorial Staff of precision in building, and the rela- wall may be small compared with the
Concrete Construction tion of all this to cost. surface of a dam to be viewed from a
The need to specify tolerances considerable distance. Within a
28
3/16 inch per foot(4). ACI 301 allow- It appears that no matter what sys-
ed a floor surface curvature of tem is used for specifying tolerances PROPOSED TOLERANCES
1/8-inch offset from a 10-foot (5)
there will always be some parts of a FOR PLANENESS OF FLOORS
straightedge. The investigators con- structure that are unacceptable. The AND OTHER FLATWORK
cluded that curvatures up to ½-inch number of these instances can be de- ACI Committee 302 is preparing a
(6)
offset from a 10-foot straightedge creased but frequently at consider- new “Guide for Concrete Floor and
might be acceptable. Other measure- able cost. It is simpler to plan to ac- Slab Construction.” This has not yet
commodate these by repair. been either published or adopted, SO the
ments on the building indicated that
proposed tolerances given here have no
the ACI 347 tolerance on intended Guidance for those who current authority and are still subject to
floor slab elevation was about the specify tolerances change. The new tolerances being sug-
same as they were measuring in the It should be possible for those gested by the committee are for the
building. Tolerances on distances directly concerned with construction maximum depressions between high
between columns required by ACI to clearly interpret the tolerance re- spots in a floor or slab for four classes
301 and 347 agreed fairly well with quirements in the construction speci- of finish:
what they measured. fications. Tolerances should be suffi- Class A finish
Although designers often specify ciently clear and specific not to give 1/8 inch below a 10-foot(23)
unrealistic tolerances without ques- straightedge*
trouble to:
tioning the lack of realism in the data • the contractor who prepares the Class A-2 finish
they have access to, they also often 3/16 inch below a 10-foot(24)
bid
accept the finished structure with all straightedge
• the job superintendent who
its deviations from the specified tol- Class B finish
determines materials requirements
erances. It is likely that neither 1/4 inch below a 10-foot(25)
and types of craftsmen needed
designers nor constructors know straightedge
• the shift foreman who is respon-
what tolerances are realistically ob- Class C finish
sible for setting lines and grades for
tainable; both think that the public is 1/4 inch below a 2-foot(26)
formwork and embedments straightedge
getting structures that are more ac- • the inspector who checks form-
curately built than they really are. * The Committee states that the tolerance
work for accuracy and strength for a Class A finish is “extremely difficult
In Europe, realistic tolerances before concrete is placed and expensive to achieve on large areas. [It]
have been established by statistical Several general guidelines can be should be specified only for critical areas
analysis of deviations. But in Europe stated for specifying tolerances. where such [a tolerance is] vital for the
operations that will take place in the area.”
considerable precasting is done, • Be certain that the design does
which makes it relatively easy to not demand tolerances that are
make dimensional measurements of unrealistic or unattainable.
elements and study them statistically. • Provide places where the in- Ambiguity is also caused by the
Another important factor is the in- evitable variations can be absorbed. practice of center-to-center dimen-
volvement of the design engineer in • Choose construction concepts sioning. The exact location of the
the selection of construction meth- that will ensure that critical dimen- center line of a column may be a
ods, a practice associated with in- sions are controlled directly and matter of opinion. The best practice
dustrialization of the European check these out with builders to be is to give dimensions to the face of
building industry. sure they are free of bugs. the concrete.
In the normal course of construc- • Dimension the drawing in such a Unfortunately it is all too easy for
tion the deviations of any set of mea- way that the inspector can measure a designer to assume that a building
surements from the intended value critical dimensions directly. can be built to zero tolerance and for
will fit the statistical normal distribu- • Emphasize or highlight critical him to design accordingly. The con-
tion curve. By calculating the stan- dimensions in drawing so that they struction of such a building may easi-
dard deviation from a large body of are forcefully called to the attention ly lead to trouble, cost everyone
measurements it can be determined of the constructor. more money than necessary and may
how many measurements are statisti- wind up in a lawsuit. The fact that
cally expected to fall within given The use of double dimensioning such a design may have been con-
limits. If tolerances were established on drawings inevitably leads to trou- structed successfully in the past can
in statistical terms, thus acknowledg- ble and should be avoided. This is the provide a false sense of security.
ing that a small number of measure- practice of showing both the individ-
Constructing within the tolerances
ments will fall outside an acceptable ual dimensions and the total dimen-
range, our tolerances might be more sion. It leads to uncertainty about Everything possible should be
realistic. which dimension can best be allowed done to avoid ambiguity. Much time
to float to meet all of the tolerance is wasted on the job over differences
requirements. This subject is well ex- about how to interpret tolerance re-
* Numbers in parentheses refer to metric
equivalents listed with this article. plained in Reference 1. quirements.
29
The constructor could wish that If he has underestimated the preci- cide to form the opening between
the specifications would supply all sion needed in any part of the job it is columns instead of the columns
the required tolerances. In practice, likely to cause trouble during con- themselves. This would lead to devia-
however, he must make his own deci- struction or later and cost him tions in the column width rather than
sion concerning most of them. This money. in the space between columns and the
involves study, to determine which A constructor would do well to tolerance would be taken up in the
tolerances are important; it calls for think out ahead of time the methods amount of concrete cover over the
both experience and intuition. The to be used in controlling tolerances. column ties.
constructor ultimately prices his job For example, in a situation where the Tolerances cannot be achieved un-
with his own particular concept of clear distance between columns is less they are controlled. The work
the tolerance requirements in mind. particularly important, he might de- begins at the time of surveying and
setting out the site and includes all
subsequent construction.
One recent advancement in the
control of dimensions, elevations,
plumbness, planeness and alignment
has been the introduction of lasers.
Their use in construction measure-
ment is discussed in the 7-page arti-
cle “Laser Construction Tools,”
Concrete Construction, September
1978, page 516.
Other methods of controlling tol-
erances are illustrated in the figures.
Figure 1 shows three simple meth-
ods of checking deviations of
angles. A template like that shown
in Figure 2 can be used to measure
warping. Warping of a vertical sur-
face can be measured with a stadia
rod equipped with leveling bubbles
and dial gages as shown in Figure 3.
The rod is set in Position 1 near one
vertical edge with the leveling bub-
ble in a fixed position and the dial
gages are adjusted to give a reading
of the distance between the rod and
the surface. The rod is then moved
to Position 2 and held with the level-
ing bubble in an identical position.
The distance that one dial gage has
to be moved in or out indicates the
amount of warping.
Bowing in a simple curve can be
measured by stretching wires tightly
over spacer blocks and measuring
down to the surface. Another meth-
od is to measure from the curve to a
straightedge.
Accepting out-of-tolerance work
Work rarely is rejected or tom
out simply because it is out of toler-
ance. This may be evidence that
specified tolerances are likely to be
more stringent than actually needed.
The type of out-of-tolerance work
that might require replacement are
slabs on grade that are intended to
30
drain but don’t, or concrete that is structure. This is simply a way of viation as descriptions of the
intended to accommodate installa- recognizing the fact that there is characteristic deviations allowable.
tion of machinery but does not pro- some economical limit to the degree Based on European experience toler-
vide sufficient room. of precision obtainable in concrete ances amounting to plus or minus 1.5
In precast work it is generally work. to 2.5 times the standard deviation
more economical to cast building Such a practice leads to an idea might be realistic. In the meantime
elements with a degree of precision that is now being considered in the everyone must do what they can to
that anticipates some out-of-toler- construction industry: describe tol- make tolerances realistic and to plan
ance elements. Then these elements erances in statistical terms, giving for efficient methods of meeting
are modified later for use in the both the mean and the standard de- tolerances during construction.
31