Professional Documents
Culture Documents
CORDOVA, ZHANE M.
COMPUTATION SHEET
REBAR WORKS
ITEM TO BE CALCULATIONS MATERIALS AND ESTIMATED QUANTITIES REQUIRED
ESTIMATED 10mm RSB 12mm RSB 16mm RSB G.I. Tie
Wires
Footing bars Total L of footing bars 25 3.328
(F1) = {1𝑚 - 0.07𝑚(2)} 14
= 12.04𝑚
Total L of Stirrups
=918m
Total Pieces of 6m-10mm RSB
= 918𝑚/6
=153 pcs.
Total L of Stirrups
=1297.8m
Total Pieces of 6m-10mm RSB
= 1297.8𝑚/6
=216.3 pcs.
Total L of Stirrups
=604.8m
Total Pieces of 6m-10mm RSB
= 604.8𝑚/6
=100.8 pcs.
Total L of Stirrups
=67.25m
Total Pieces of 6m-10mm RSB
= 67.2𝑚/6
=11.2 pcs.
Total connections
=224
Total G.I. Tie Wires
=(224)(0.3)/53
=1.27 Kg #16 G.I. Wire
Column 1 Total L of Column (Length of hooks 118 120 15.76
included)
= 89.7m
Total L of 16mm RSB
=89.7m (8)
=717.6m
Total Pieces of 6m-16mm RSB
= 717.6𝑚/6
=119.6 pcs.