You are on page 1of 6

SANTOS, JOHN PAUL O.

CORDOVA, ZHANE M.
COMPUTATION SHEET
REBAR WORKS
ITEM TO BE CALCULATIONS MATERIALS AND ESTIMATED QUANTITIES REQUIRED
ESTIMATED 10mm RSB 12mm RSB 16mm RSB G.I. Tie
Wires
Footing bars Total L of footing bars 25 3.328
(F1) = {1𝑚 - 0.07𝑚(2)} 14
= 12.04𝑚

Total Length of footing bars x 12pm


= 144.48𝑚 16mm  RSB

Total Pieces of 6m-16mm  RSB


= 144.48𝑚/6
=24.08 pcs.

Total connections for tie wires


=588
Total G.I. Tie Wires
=(588)(0.3)/53
=3.328 Kg #16 G.I. Wire
Footing bars Total L of footing bars 33 3.62
(F2) = {1.5𝑚 - 0.07𝑚(2)} 16
=21.76𝑚

Total Length of footing bars x 10pcs


= 217.6𝑚 16mm  RSB

Total Pieces of 6m-16mm  RSB


= 217.6𝑚/6
=32.27 pcs.

Total connections for tie wires


=640
Total G.I. Tie Wires
=(640)(0.3)/53
=3.62 Kg #16 G.I. Wire
Footing bars Total L of footing bars 17 0.826
(F3) = {{(1.5𝑚 - 0.07𝑚(2)} 28} + {(1.25) (9)}
= 49.33𝑚

Total Length of footing bars x 2pcs


= 98.66𝑚 16mm  RSB

Total Pieces of 6m-16mm  RSB


= 98.66𝑚/6
=16.44 pcs.
Total connections for tie wires
=146
Total G.I. Tie Wires
=(146)(0.3)/53
=0.826 Kg #16 G.I. Wire
Tie beams Total L of Tie Beams (Length of hooks 153 107 18.725
included)
= 106.59m
Total L of 16mm  RSB
=106.59m (6)
=639.54m
Total Pieces of 6m-16mm  RSB
= 639.54𝑚/6
=106.59 pcs.

Total L of Stirrups
=918m
Total Pieces of 6m-10mm  RSB
= 918𝑚/6
=153 pcs.

Total connections for tie wires


=3308
Total G.I. Tie Wires
=(3308)(0.3)/53
=18.725 Kg #16 G.I. Wire
Beam 1 Total L of Beams (Length of hooks 217 151 22.98
included)
= 129.28m

Total L of 16mm  RSB


=129.28m (7)
=904.96m
Total Pieces of 6m-16mm  RSB
= 904.96𝑚/6
=150.83 pcs.

Total L of Stirrups
=1297.8m
Total Pieces of 6m-10mm  RSB
= 1297.8𝑚/6
=216.3 pcs.

Total connections for tie wires


=4060
Total G.I. Tie Wires
=(4060)(0.3)/53
=22.98 Kg #16 G.I. Wire
Beam 2 Total L of Beams (Length of hooks 101 89 10.32
included)
= 59.05m
Total L of 16mm  RSB
=59.05m (9)
=531.45m
Total Pieces of 6m-16mm  RSB
= 531.45𝑚/6
=88.58 pcs.

Total L of Stirrups
=604.8m
Total Pieces of 6m-10mm  RSB
= 604.8𝑚/6
=100.8 pcs.

Total connections for tie wires


=1824
Total G.I. Tie Wires
=(1824)(0.3)/53
=10.32 Kg #16 G.I. Wire
Beam 3 Total L of Beams (Length of hooks 12 10 1.27
included)
= 8m

Total L of 16mm  RSB


=8m (7)
=56m
Total Pieces of 6m-16mm  RSB
= 56𝑚/6
=9.33 pcs.

Total L of Stirrups
=67.25m
Total Pieces of 6m-10mm  RSB
= 67.2𝑚/6
=11.2 pcs.

Total connections
=224
Total G.I. Tie Wires
=(224)(0.3)/53
=1.27 Kg #16 G.I. Wire
Column 1 Total L of Column (Length of hooks 118 120 15.76
included)
= 89.7m
Total L of 16mm  RSB
=89.7m (8)
=717.6m
Total Pieces of 6m-16mm  RSB
= 717.6𝑚/6
=119.6 pcs.

Total L of Tie Bars


=705.6m
Total Pieces of 6m-10mm  RSB
= 705.6𝑚/6
=117.6 pcs.
Total connections for tie wires
=2784
Total G.I. Tie Wires
=(2784)(0.3)/53
=15.76 Kg #16 G.I. Wire
Column 2 Total L of Column (Length of hooks 94 98 12.498
included)
= 73.5m

Total L of 16mm  RSB


=73.5m (8)
=588m
Total Pieces of 6m-16mm  RSB
= 588𝑚/6
=98 pcs.

Total L of Tie Bars


=561.6m
Total Pieces of 6m-10mm  RSB
= 561.6𝑚/6
=93.6 pcs.

Total connections for tie wires


=2208
Total G.I. Tie Wires
=(2208)(0.3)/53
=12.498 Kg #16 G.I. Wire
Column 3 Total L of Column (Length of hooks 45 46 5.93
included)
= 34.4m
Total L of 16mm  RSB
=34.4m (8)
=275.2m
Total Pieces of 6m-16mm  RSB
= 275.2𝑚/6
=45.86 pcs.
Total L of Tie Bars
=266.4m
Total Pieces of 6m-10mm  RSB
= 266.4𝑚/6
=44.4 pcs.

Total connections for tie wires


=1048
Total G.I. Tie Wires
=(1048)(0.3)/53
=5.93 Kg #16 G.I. Wire
Slab 1st flr Total L of RSB (Length of hooks 151 5.95
included)
= 905.22m
Total Pieces of 6m-10mm  RSB
= 905.22𝑚/6
=150.87 pcs.
Total connections for tie wires
=1052
Total G.I. Tie Wires
=(1052)(0.3)/53
=5.95 Kg #16 G.I. Wire
Slab 2nd flr Total L of RSB (Length of hooks 207 9.48
included)
= 1239.01m
Total Pieces of 6m-12mm  RSB
= 1239.01𝑚/6
=206.5 pcs.

Total connections for tie wires


=1674
Total G.I. Tie Wires
=(1674)(0.3)/53
=9.48 Kg #16 G.I. Wire
Roof slab Total L of RSB (Length of hooks 184 9.11
included)
= 1099.52m
Total Pieces of 6m-12mm  RSB
= 1099.52𝑚/6
=183.25 pcs.

Total connections for tie wires


=1609
Total G.I. Tie Wires
=(1609)(0.3)/53
=9.11 Kg #16 G.I. Wire
Masonry 1st Total L of RSB (Length of hooks 63 1.34
flr included)
= 376.17m

Total Pieces of 6m-10mm  RSB


= 376.17𝑚/6
=62.69 pcs.

Total connections for tie wires


=236
Total G.I. Tie Wires
=(236)(0.3)/53
=1.34 Kg #16 G.I. Wire
Masonry 2nd Total L of RSB (Length of hooks 62 1.26
flr included)
= 366.9m
Total Pieces of 6m-10mm  RSB
= 366.9𝑚/6
=61.15 pcs.
Total connections for tie wires
=223
Total G.I. Tie Wires
=(223)(0.3)/53
=1.26 Kg #16 G.I. Wire
Stairs Total L of RSB (Length of hooks 15 0.84
included)
= 89.55m
Total Pieces of 6m-10mm  RSB
= 89.55𝑚/6
=14.92 pcs.

Total connections for tie wires


=148
Total G.I. Tie Wires
=(148)(0.3)/53
=0.84 Kg #16 G.I. Wire
TOTAL 1031 pcs. 391 pcs. 696 pcs. 123.237