You are on page 1of 2

Reliable and Interventionless

Intelligent Well Completion


Completion technology that reduces string in place. The PAFCV was run
This article, written by Assistant Tech-
operational risk and project cycle closed and actuated by a pressure dif-
nology Editor Karen Bybee, contains
time allows operators to exploit ferential from tubing to annulus. Once
highlights of paper OTC 14252,
hydrocarbon reserves economically. open, the PAFCV allowed flow from
“Reliable and Completely Intervention-
The full-length paper discusses the annulus into the tubing through
less Intelligent Well Completion Tech-
development and application of an flow ports. The valve could be run as
nology: Application and Field Study,”
intelligent well system that is reliable base pipe under the screen or included
by D.E. Johnson, D.M. Turner, SPE,
and completely interventionless. in a concentric string across the pro-
and D.J. Walker, SPE, OSCA Inc.,
ducing interval.
and D. Harris and D. McDaniel,
Introduction The AFV was designed to control a
Kerr-McGee, originally presented at
Initial intelligent well completions different flow path. In the running posi-
the 2002 Offshore Technology
focused on the ability to control reser- tion, the AFV blocks flow from the con-
Conference, Houston, 6–9 May.
voir access remotely from surface facili- centric area below the valve to the con-
ties to access multiple reservoirs with- centric area above the valve. In common
The paper has not been peer
out the expense of workover operations. applications, the AFV would be run
reviewed. Copyright 2002 Offshore
Objectives were defined for a next gen- above the screen in the upper-zone flow
Technology Conference.
eration intelligent well completion sys- path, eliminating flow when closed.
tem that would integrate all aspects of Application of a preset differential pres-
the completion from sand control to sure shifts the internal piston to open a devices would provide positive zonal
placing the well on production. Primary bypass area and allows flow from the isolation of each zone after gravel-pack
objectives included the following. concentric area below the valve to the operations and would maintain isola-
• Maintain fluid-loss and well con- concentric area above the valve. The tion until production began. Both
S m a r t We l l s

trol at all times before production valve enables backup mechanical access zones could be selectively or simulta-
begins. down the long string to mechanically neously opened by applying pressure
• Eliminate mechanical post-com- shift the valve if required. The valve is down the tubing to create the required
pletion intervention. balanced until the production seals are opening pressure differential.
• Use simple, reliable technologies. landed, preventing accidental actuation.
• Maximize production potential by Both the PAFCV and the AFV were con- Downhole Flow Control
maintaining optimum flow areas. sidered to be viable alternatives for the To meet the required flow-control
upper-zone completion. objective, available systems were ana-
System Development The primary difficulty in using either lyzed for form, fit, and function. A
Lower-Zone Completion. In the past, of these technologies on the lower zone hydraulic control system was chosen
lower-zone completions used mechani- was the inability to prevent upper-zone to meet the simplified technology
cal sleeves to gravel pack, isolate, and treating pressures from actuating the standard specified in the original
produce the reservoir. These sleeves lower-zone fluid-loss device. Installing objectives. Two independent axial-
were run concentrically inside the an AFV and PAFCV in tandem present- type sliding sleeves were selected. A
lower-zone screen assembly and ed a unique solution to this problem. three-line control system that used one
mechanically manipulated after the The valves were aligned so that the independent control line to open each
gravel pack was complete. Slickline or upper-zone treating pressure was rout- of the sleeves and a common close line
coiled tubing was used to reopen the ed into the inner diameter (ID) of the that allowed complete and individual
sleeves for production. This system met lower zone and into an artifically creat- operation of each valve assembly was
all the criteria for fluid loss and zone ed concentric space above the lower- selected. Valve position indication was
control but was not interventionless. zone AFV. During the gravel-pack/frac- based on pressure response and vol-
The interventionless solution to this pack treatment, pressure is balanced ume measurement. The valves were
problem was a derivative of systems across the valves, eliminating the developed with existing technology
originally developed for the upper chance of prematurely opening. This found in current mechanical sleeves.
zone. These systems included a pres- valve combination was chosen as the The hydraulic downhole flow-control
sure-actuated fluid-loss control valve primary design for the interventionless valve system was tested and certified
(PAFCV) and an annular flow valve lower-zone completion. to 10,000-psi static differential and
(AFV). PAFCV technology was used 2,500-psi cycling differential.
successfully in previous applications Upper Zone. On the basis of flow
where upper-zone isolation was parameters and well economics, the Case Histories
required and mechanical intervention AFV was selected for interventionless Case A. The first field trial was con-
was not possible with the production upper-zone completions. Use of these ducted on a well with two productive

70
SEPTEMBER 2002
intervals at depths greater than After completion of both zones, the However, because of debris in the sys-
12,000 ft measured depth and bottom- hydraulic downhole flow-control sys- tem, wireline was not able to get to
hole pressures greater than 8,000 psi. tem was installed in preparation for bottom, and coiled tubing was
The lower zone was completed with a production activities. The system test- required to clean out the wellbore.
high-rate water pack using a mechani- ed and performed as designed. Once The lower-zone mechanical fluid-loss
cally actuated fluid-loss control system the well was ready for production, the system was actuated with slickline.
for well and fluid-loss control. The schedule was to actuate the lower Both zones were flow tested indepen-
upper zone was a frac-pack completion mechanical fluid-loss device with dently during this process and have
using a PAFCV. The PAFCV system is wireline and use pressure from the been on production since July 2000
actuated from the surface by use of a surface to actuate the PAFCV on the without incident.
pressure response and was designed for upper zone. Well production would
actuation in intervals with no mechan- be controlled with the upper and Case B. This well was a dual-zone
ical means for manipulation. lower downhole flow-control valves. completion in 95/8-in. casing with a
measured depth greater than
12,000 ft and pressure greater than
7,000 psi. Both zones were oil-pro-
ducing reservoirs completed with
high-rate water-pack treatments. The
lower interval used an AFV/PAFCV
combination for fluid-loss and well
control after treatment. An AFV with
an extended seal bore was used in the
upper interval to control the well and
simplify spacing out production seals
and landing the hanger.
After completing the lower zone, the
work string and sand-control equip-
ment were removed from the well, and
the new AFVs were tested success-
fully. The upper zone was treated
without incident. The AFV/PAFCV
S m a r t We l l s

provided well control while the down-


hole flow-control valves were in-
stalled. The system was installed suc-
cessfully in the 95/8-in. casing above
the upper gravel pack. The com-
pletion fluid was replaced with a
lighter packer fluid and the hanger
landed and locked. After successful-
ly testing the packer, downhole flow-
control valves were manipulated as
necessary, and pressure from the
surface was applied to actuate the
fluid-loss devices. Both zones were
flowed successfully.

Conclusions
1. A simple smart-well approach
provides necessary functionality with-
out extraneous features or unneces-
sary cost.
2. Additional capital cost of the new
smart-well equipment is estimated to
be approximately 20% of the total
completion-equipment cost.
3. The system provides total posi-
tive zonal isolation of the producing
reservoirs after each well is gravel
packed.
4. The system eliminates all slick-
line/mechanical intervention work
requirements below the tubing hanger
during and after the completion. JPT

72
SEPTEMBER 2002

You might also like